ODOT contract 250526 bid tabulation
HIG-SR 73-00.26 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on November 13, 2025, HIG. 8 bids received; low bid $1,743,419 by D G M Inc, -18% against the engineer's estimate of $2,125,000.
- Owner
- Ohio DOT
- Letting
- 13 NOV 2025
- Pay items
- 103
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | D G M Inc | $1,743,419 | Low | -18% |
| 2 | George J Igel & Co Inc | $2,046,912 | +17% | -4.0% |
| 3 | Alan Stone Co Inc | $2,091,921 | +20% | -2.0% |
| 4 | Double Z Construction Company | $2,139,927 | +23% | +1.0% |
| 5 | Complete General Construction Company | $2,192,366 | +26% | +3.0% |
| 6 | Sunesis Construction Co | $2,306,371 | +32% | +9.0% |
| 7 | KT Holden Construction LLC | $2,336,827 | +34% | +10% |
| 8 | Eagle Bridge Co | $2,348,246 | +35% | +11% |
Engineer's estimate: $2,125,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D G M Inc | 2. George J Igel & Co Inc | 3. Alan Stone Co Inc | 4. Double Z Construction Company | 5. Complete General Construction Company | 6. Sunesis Construction Co |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $20,000 | $22,500 | $25,000 | $20,000 | $5,000.00 | $20,824 |
| 2 | Pavement removed (202E23000) | SY | 1,611 | $4.00 | $14.25 | $20.00 | $18.00 | $12.50 | $7.11 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 207 | $15.00 | $15.00 | $20.00 | $15.00 | $50.00 | $27.69 |
| 4 | Fence removed (202E75000) | FT | 8 | $15.00 | $12.00 | $60.00 | $15.00 | $50.00 | $20.55 |
| 5 | Removal misc.: concrete retaining wall (202E98000) | LS | 1 | $6,000.00 | $2,500.00 | $4,700.00 | $1,800.00 | $8,000.00 | $1,085.76 |
| 6 | Excavation (203E10000) | CY | 446 | $20.00 | $25.00 | $55.00 | $25.00 | $35.00 | $2.66 |
| 7 | Embankment (203E20000) | CY | 721 | $22.50 | $20.00 | $15.00 | $30.00 | $35.00 | $36.74 |
| 8 | Subgrade compaction (204E10000) | SY | 2,551 | $3.00 | $4.00 | $4.00 | $5.00 | $5.50 | $2.62 |
| 9 | Proof rolling (204E45000) | HR | 2 | $75.00 | $132.00 | $280.00 | $200.00 | $375.00 | $426.91 |
| 10 | Guardrail, type MGS (606E15050) | FT | 275 | $25.00 | $23.00 | $25.00 | $21.00 | $36.94 | $23.00 |
| 11 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 2 | $2,600.00 | $2,550.00 | $2,900.00 | $2,500.00 | $2,400.00 | $2,550.00 |
| 12 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,450.00 | $1,400.00 | $1,400.00 | $1,200.00 | $1,100.00 | $1,400.00 |
| 13 | MGS bridge terminal assembly, type TST-2 (606E34600) | EACH | 4 | $2,800.00 | $2,750.00 | $2,900.00 | $2,500.00 | $2,290.00 | $2,750.00 |
| 14 | Monument assembly, type C (623E38500) | EACH | 1 | $1,000.00 | $1,300.00 | $3,500.00 | $1,600.00 | $2,000.00 | $3,038.81 |
| 15 | Right-of-way monument, type B (623E40520) | EACH | 3 | $300.00 | $350.00 | $340.00 | $500.00 | $1,000.00 | $283.34 |
| 16 | Special - mailbox removed and reset (690E50350) | EACH | 2 | $200.00 | $500.00 | $220.00 | $300.00 | $220.00 | $273.92 |
| 17 | Rock channel protection, type B with geotextile fabric (601E32104) | CY | 81 | $120.00 | $140.00 | $180.00 | $135.00 | $95.00 | $224.39 |
| 18 | Topsoil (659E00300) | CY | 371 | $17.50 | $10.25 | $15.00 | $50.00 | $25.00 | $33.13 |
| 19 | Seeding and mulching (659E10000) | SY | 2,717 | $2.00 | $3.50 | $2.00 | $5.00 | $1.30 | $2.74 |
| 20 | Repair seeding and mulching (659E14000) | SY | 136 | $0.05 | $1.30 | $1.00 | $1.30 | $1.30 | $1.30 |
| 21 | Commercial fertilizer (659E20000) | TON | 0.37 | $1,500.00 | $1,250.00 | $1,700.00 | $1,250.00 | $1,250.00 | $1,250.00 |
| 22 | Lime (659E31000) | ACRE | 0.56 | $300.00 | $150.00 | $230.00 | $150.00 | $150.00 | $150.00 |
| 23 | Water (659E35000) | MGAL | 15 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 24 | Slope erosion protection (670E00500) | SY | 623 | $2.50 | $2.50 | $3.00 | $2.50 | $2.50 | $2.50 |
| 25 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,500.00 | $2,000.00 | $3,100.00 | $2,700.00 | $2,000.00 | $2,700.00 |
| 26 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $10,000 | $8,850.00 | $9,800.00 | $6,420.00 | $9,550.00 | $6,420.02 |
| 27 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $12,000 | $9,100.00 | $14,000 | $13,000 | $12,500 | $12,073 |
| 28 | Erosion control (832E30000) | EACH | 16,309 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 29 | Aggregate drains (605E31100) | FT | 244 | $25.00 | $48.00 | $35.00 | $20.00 | $20.00 | $19.45 |
| 30 | 6" conduit, type E (611E01400) | FT | 30 | $10.00 | $36.00 | $40.00 | $8.00 | $10.00 | $23.02 |
| 31 | 6" conduit, type F (611E01500) | FT | 30 | $8.00 | $36.00 | $55.00 | $8.00 | $10.00 | $23.02 |
| 32 | 12" conduit, type D (611E04900) | FT | 136 | $80.00 | $85.00 | $150.00 | $80.00 | $105.00 | $79.02 |
| 33 | Catch basin, no. 2-2B (611E98470) | EACH | 2 | $1,300.00 | $2,500.00 | $8,100.00 | $3,000.00 | $4,000.00 | $1,726.89 |
| 34 | Catch basin adjusted to grade (611E98630) | EACH | 1 | $400.00 | $2,300.00 | $2,000.00 | $900.00 | $1,500.00 | $898.87 |
| 35 | Pavement planing, asphalt concrete (1.5") (254E01000) | SY | 135 | $15.00 | $15.00 | $65.00 | $14.00 | $14.00 | $14.00 |
| 36 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 510 | $220.00 | $220.00 | $250.00 | $210.00 | $210.00 | $210.00 |
| 37 | Aggregate base (304E20000) | CY | 430 | $77.50 | $92.00 | $110.00 | $95.00 | $95.00 | $98.74 |
| 38 | Tack coat (407E10000) | GAL | 402 | $4.50 | $10.50 | $5.00 | $4.50 | $4.50 | $4.50 |
| 39 | Traffic compacted surface, type A or B (410E12000) | CY | 25 | $40.00 | $68.10 | $130.00 | $90.00 | $95.00 | $109.06 |
| 40 | Traffic compacted surface, type C (410E13000) | CY | 25 | $45.00 | $82.05 | $90.00 | $75.00 | $95.00 | $109.06 |
| 41 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 180 | $265.00 | $295.00 | $340.00 | $265.00 | $265.00 | $265.00 |
| 42 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 3 | $720.00 | $600.00 | $2,100.00 | $700.00 | $700.00 | $700.00 |
| 43 | Rumble stripes, edge line (asphalt concrete) (618E40800) | FT | 1,089 | $4.00 | $10.00 | $7.00 | $8.00 | $7.00 | $4.63 |
| 44 | Rumble stripes, center line (asphalt concrete) (618E40900) | FT | 842 | $4.00 | $10.00 | $7.50 | $8.00 | $9.00 | $4.00 |
| 45 | RPM (621E00100) | EACH | 8 | $292.00 | $475.00 | $550.00 | $290.00 | $475.00 | $290.00 |
| 46 | Raised pavement marker removed (621E54000) | EACH | 8 | $1.00 | $30.00 | $140.00 | $15.00 | $50.00 | $24.34 |
| 47 | Barrier reflector, type 3 (BI-directional) (626E00112) | EACH | 12 | $15.00 | $13.00 | $15.00 | $12.00 | $10.00 | $12.23 |
| 48 | Ground mounted support, no. 3 post (630E03100) | FT | 36.40 | $18.00 | $16.00 | $20.00 | $16.00 | $15.00 | $30.21 |
| 49 | Sign post reflector (630E08600) | EACH | 1 | $60.00 | $55.00 | $65.00 | $55.00 | $30.00 | $89.72 |
| 50 | Sign, flat sheet (630E80100) | SF | 27 | $18.00 | $16.00 | $20.00 | $16.00 | $30.00 | $32.22 |
| 51 | Removal of ground mounted sign and disposal (630E84900) | EACH | 11 | $15.00 | $20.00 | $25.00 | $20.00 | $15.00 | $16.56 |
| 52 | Removal of ground mounted post support and disposal (630E86002) | EACH | 9 | $15.00 | $25.00 | $75.00 | $25.00 | $15.00 | $22.08 |
| 53 | Edge line, 6", type 1 (642E00104) | MI | 0.24 | $6,000.00 | $5,500.00 | $5,700.00 | $5,000.00 | $5,500.00 | $5,000.00 |
| 54 | Center line, type 1 (642E00300) | MI | 0.12 | $6,000.00 | $10,500 | $6,300.00 | $5,500.00 | $10,500 | $5,500.00 |
| 55 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 12 | $2,000.00 | $2,500.00 | $2,300.00 | $1,951.07 | $1,950.00 | $1,951.07 |
| 56 | Detour signing (614E12420) | LS | 1 | $8,000.00 | $6,000.00 | $6,900.00 | $4,775.00 | $6,000.00 | $9,952.52 |
| 57 | Barrier reflector, type 1 (BI-directional) (614E13310) | EACH | 32 | $20.00 | $44.00 | $50.00 | $15.00 | $44.00 | $10.05 |
| 58 | Barrier reflector, type 3 (BI-directional) (614E13314) | EACH | 5 | $20.00 | $50.00 | $60.00 | $15.00 | $50.00 | $11.18 |
| 59 | Object marker, two way (614E13360) | EACH | 37 | $20.00 | $40.00 | $45.00 | $15.00 | $40.00 | $19.88 |
| 60 | Work zone edge line, class I, 6" (614E22010) | MI | 0.93 | $4,000.00 | $3,652.00 | $4,000.00 | $3,500.00 | $3,652.00 | $3,500.00 |
| 61 | Work zone stop line, class I (614E26000) | FT | 48 | $10.00 | $14.00 | $8.00 | $7.00 | $14.00 | $7.00 |
| 62 | Pavement for maintaining traffic, class B (615E25000) | SY | 123 | $125.00 | $85.00 | $120.00 | $175.00 | $200.00 | $178.95 |
| 63 | Water (616E10000) | MGAL | 6 | $1.00 | $62.15 | $0.20 | $50.00 | $100.00 | $14.99 |
| 64 | Portable barrier, unanchored (622E41100) | FT | 1,210 | $18.00 | $28.00 | $20.00 | $24.00 | $27.50 | $27.82 |
| 65 | Portions of structure removed, over 20 foot span (202E11202) | LS | 1 | $76,500 | $82,500 | $37,000 | $105,000 | $137,000 | $35,572 |
| 66 | Approach slab removed (202E22900) | SY | 94 | $25.00 | $60.00 | $130.00 | $65.00 | $65.00 | $41.86 |
| 67 | Wearing course removed (202E23500) | SY | 265 | $8.00 | $8.50 | $20.00 | $33.00 | $55.00 | $5.41 |
| 68 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $94,000 | $70,000 | $65,000 | $180,000 | $82,500 | $73,547 |
| 69 | Unclassified excavation (503E21300) | LS | 1 | $11,000 | $91,000 | $10,000 | $50,000 | $80,000 | $25,448 |
| 70 | Rock excavation (503E31100) | CY | 85 | $60.00 | $120.00 | $150.00 | $170.00 | $50.00 | $97.24 |
| 71 | Epoxy coated steel reinforcement (509E10000) | LB | 38,585 | $1.35 | $1.60 | $1.50 | $1.70 | $1.75 | $2.06 |
| 72 | Semi-integral diaphragm guide (511E33500) | EACH | 2 | $2,400.00 | $4,325.00 | $6,800.00 | $3,500.00 | $7,475.00 | $3,109.06 |
| 73 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 105 | $1,575.00 | $2,100.00 | $2,400.00 | $1,785.00 | $1,600.00 | $2,993.05 |
| 74 | Class QC1 concrete with QC/QA, abutment not including footing (511E44112) | CY | 92 | $685.00 | $1,095.00 | $1,000.00 | $960.00 | $1,150.00 | $1,212.18 |
| 75 | Class QC1 concrete with QC/QA, footing (511E46512) | CY | 75 | $635.00 | $895.00 | $900.00 | $690.00 | $950.00 | $1,110.15 |
| 76 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 167 | $40.00 | $32.00 | $45.00 | $40.00 | $40.00 | $40.00 |
| 77 | Sealing concrete bridge decks with HMWM resin (512E10300) | SY | 20 | $40.00 | $60.00 | $30.00 | $36.00 | $100.00 | $71.61 |
| 78 | Type 2 waterproofing (512E33000) | SY | 33 | $25.00 | $38.05 | $95.00 | $36.00 | $75.00 | $44.11 |
| 79 | Structural steel members, level 1, as per plan (513E10221) | LB | 71,028 | $2.84 | $3.05 | $3.50 | $3.10 | $3.00 | $4.04 |
| 80 | Welded stud shear connectors (513E20000) | EACH | 2,664 | $7.00 | $5.90 | $6.50 | $5.90 | $5.80 | $6.31 |
| 81 | 2" preformed expansion joint filler (516E13900) | SF | 54 | $25.00 | $12.00 | $4.00 | $19.00 | $11.00 | $5.64 |
| 82 | Semi-integral abutment expansion joint seal (516E14020) | FT | 118 | $47.50 | $35.00 | $25.00 | $32.00 | $50.00 | $54.48 |
| 83 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44001) | EACH | 12 | $2,100.00 | $2,450.00 | $1,600.00 | $2,000.00 | $1,500.00 | $2,296.78 |
| 84 | Railing (three steel tube bridge railing) (517E70100) | FT | 134 | $475.00 | $464.79 | $510.00 | $455.00 | $465.00 | $457.00 |
| 85 | Porous backfill with geotextile fabric (518E21200) | CY | 79 | $120.00 | $175.00 | $200.00 | $120.00 | $150.00 | $105.97 |
| 86 | Special - steel drip strip (518E22300) | FT | 147 | $20.00 | $15.00 | $60.00 | $30.00 | $16.50 | $16.50 |
| 87 | 6" perforated corrugated plastic pipe (518E40000) | FT | 168 | $20.00 | $8.00 | $5.00 | $13.00 | $15.00 | $9.10 |
| 88 | 6" non-perforated corrugated plastic pipe, including specials, as per plan (518E40011) | FT | 40 | $60.00 | $60.00 | $55.00 | $13.00 | $25.00 | $15.38 |
| 89 | Drilled shafts, 30" diameter, into bedrock (524E94604) | FT | 160 | $600.00 | $385.00 | $330.00 | $600.00 | $725.00 | $438.62 |
| 90 | Drilled shafts, 36" diameter, into bedrock (524E94704) | FT | 9 | $600.00 | $270.00 | $990.00 | $715.00 | $550.00 | $369.82 |
| 91 | Reinforced concrete approach slabs with QC/QA (T=1 (526E25010) | SY | 200 | $320.00 | $475.00 | $520.00 | $425.00 | $450.00 | $514.56 |
| 92 | Type A installation (526E90010) | FT | 88 | $250.00 | $265.00 | $210.00 | $250.00 | $300.00 | $225.97 |
| 93 | Structure grounding system (625E33000) | EACH | 1 | $20,000 | $15,500 | $21,000 | $15,000 | $10,000 | $12,375 |
| 94 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $21,000 | $10,000 | $15,000 | $14,000 | $13,000 | $12,704 |
| 95 | Maintaining traffic (614E11000) | LS | 1 | $110,000 | $67,000 | $100,000 | $90,000 | $110,000 | $226,848 |
| 96 | Field office, type A (619E16000) | MNTH | 6 | $750.00 | $1,900.00 | $1,000.00 | $2,000.00 | $2,000.00 | $2,885.00 |
| 97 | Construction layout stakes and surveying (623E10000) | LS | 1 | $6,000.00 | $15,000 | $25,000 | $14,900 | $20,000 | $23,750 |
| 98 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,000.00 | $3,650.00 | $3,400.00 | $1,500.00 | $3,000.00 | $3,100.00 |
| 99 | Post construction survey monument verification and report (623E51000) | LS | 1 | $1,000.00 | $3,550.00 | $3,400.00 | $1,500.00 | $3,000.00 | $3,100.00 |
| 100 | Mobilization (624E10000) | LS | 1 | $40,000 | $100,000 | $55,000 | $100,000 | $109,000 | $104,705 |
| 200 | Pavement planing, asphalt concrete(1.0?) (254E01000) | SY | 354 | $30.00 | $22.00 | $28.00 | $31.46 | $28.00 | $28.00 |
| 201 | Roads for maintaining traffic (615E10000) | LS | 1 | $2,000.00 | $8,500.00 | $16,000 | $10,000 | $18,000 | $10,015 |
| 202 | Work zone center line, class I (614E21000) | MI | 0.20 | $4,000.00 | $7,800.00 | $11,208 | $3,500.00 | $10,500 | $3,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of November 13, 2025. Compiled by Mirage Metrics.