ODOT contract 254013 bid tabulation
GRE-IR 675-09.60, GRE-US 35-18.46 (CULVERT REPLACEMENT). Let by Ohio DOT on April 10, 2025, GRE. 5 bids received; low bid $1,046,347 by Axis Civil Construction LLC, -11% against the engineer's estimate of $1,175,000.
- Owner
- Ohio DOT
- Letting
- 10 APR 2025
- Pay items
- 49
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Axis Civil Construction LLC | $1,046,347 | Low | -11% |
| 2 | Performance Site Development | $1,279,903 | +22% | +9.0% |
| 3 | KT Holden Construction LLC | $1,296,330 | +24% | +10% |
| 4 | DJX Construction Company LLC | $1,302,344 | +24% | +11% |
| 5 | Madex Construction Co | $1,946,173 | +86% | +66% |
Engineer's estimate: $1,175,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Axis Civil Construction LLC | 2. Performance Site Development | 3. KT Holden Construction LLC | 4. DJX Construction Company LLC | 5. Madex Construction Co |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,000.00 | $32,500 | $5,850.00 | $3,433.55 | $9,299.38 |
| 2 | Headwall removed (202E20010) | EACH | 1 | $1,000.00 | $495.00 | $540.00 | $490.43 | $1,774.84 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 1,643 | $28.00 | $26.00 | $13.07 | $10.25 | $36.95 |
| 4 | Pipe removed, over 24" diameter (202E35200) | FT | 2,015 | $32.00 | $29.00 | $13.37 | $15.56 | $31.75 |
| 5 | Manhole removed (202E58000) | EACH | 2 | $1,500.00 | $710.00 | $1,025.00 | $1,459.55 | $2,065.15 |
| 6 | Catch basin removed (202E58100) | EACH | 12 | $1,500.00 | $425.00 | $1,025.00 | $526.17 | $2,117.24 |
| 7 | Removal misc.: concrete apron (202E98300) | SY | 39 | $30.00 | $16.00 | $165.00 | $47.80 | $52.95 |
| 8 | Removal misc.: rock channel protection (202E98300) | SY | 17 | $35.00 | $75.00 | $57.00 | $41.74 | $145.78 |
| 9 | Embankment (203E20000) | CY | 200 | $30.00 | $29.00 | $100.00 | $47.61 | $52.46 |
| 10 | Riprap (601E10000) | SY | 2 | $1,800.00 | $255.00 | $3,900.00 | $710.88 | $2,869.87 |
| 11 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 302 | $40.00 | $32.00 | $76.00 | $129.35 | $178.71 |
| 12 | Rock channel protection, type B with filter (601E32100) | CY | 4 | $250.00 | $255.00 | $700.00 | $1,455.12 | $212.88 |
| 13 | Water (616E10000) | MGAL | 10 | $1.00 | $60.00 | $26.14 | $89.80 | $35.27 |
| 14 | Topsoil (659E00300) | CY | 27 | $75.00 | $78.00 | $85.00 | $109.63 | $132.02 |
| 15 | Seeding and mulching, class 1 (659E00500) | SY | 242 | $7.00 | $12.00 | $10.00 | $98.57 | $12.94 |
| 16 | Repair seeding and mulching (659E14000) | SY | 12 | $2.50 | $1.25 | $1.00 | $1.13 | $6.27 |
| 17 | Commercial fertilizer (659E20000) | TON | 0.03 | $735.00 | $1,800.00 | $1,500.00 | $1,500.00 | $5,017.33 |
| 18 | Lime (659E31000) | ACRE | 0.05 | $500.00 | $240.00 | $200.00 | $200.00 | $1,410.60 |
| 19 | Water (659E35000) | MGAL | 1.30 | $1.00 | $50.00 | $1.00 | $1.00 | $54.25 |
| 20 | Ditch erosion protection (670E00700) | SY | 1,500 | $3.00 | $3.35 | $2.75 | $2.75 | $10.84 |
| 21 | Erosion control (832E30000) | EACH | 15,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 22 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $3,500.00 | $44,500 | $500.00 | $3,000.00 | $21,610 |
| 23 | Concrete masonry (602E20000) | CY | 0.40 | $6,500.00 | $3,250.00 | $4,700.00 | $3,478.37 | $6,897.62 |
| 24 | 6" conduit, type F (611E01500) | FT | 140 | $25.00 | $33.00 | $47.50 | $23.66 | $40.17 |
| 25 | 15" conduit, type C (611E06100) | FT | 20 | $50.00 | $103.00 | $850.00 | $185.73 | $100.94 |
| 26 | 18" conduit, type C (611E07600) | FT | 4 | $150.00 | $442.00 | $690.00 | $684.97 | $499.77 |
| 27 | 21" conduit, type F (611E09700) | FT | 63 | $70.00 | $129.00 | $325.00 | $285.15 | $174.21 |
| 28 | 24" conduit, type C (611E10600) | FT | 1,435 | $85.00 | $122.00 | $116.10 | $121.02 | $176.14 |
| 29 | 30" conduit, type C (611E13600) | FT | 2,166 | $98.00 | $123.60 | $144.75 | $153.48 | $199.34 |
| 30 | 30" conduit, type C (611E13600) | FT | 4 | $250.00 | $394.00 | $900.00 | $797.01 | $1,881.50 |
| 31 | Field paving of existing pipe, 42" CMP (611E96550) | FT | 223 | $380.00 | $145.00 | $197.00 | $208.37 | $992.23 |
| 32 | Catch basin, no. 4 (611E98230) | EACH | 12 | $4,250.00 | $5,622.00 | $8,000.00 | $7,812.04 | $9,607.06 |
| 33 | Manhole, no. 3 (611E99574) | EACH | 2 | $8,500.00 | $4,440.00 | $5,800.00 | $7,461.59 | $6,415.53 |
| 34 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $75.00 | $180.00 | $80.00 | $150.00 | $114.63 |
| 35 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 3 | $2,200.00 | $2,298.00 | $2,124.00 | $2,126.97 | $3,473.68 |
| 36 | Barrier reflector, type 1 (one-way) (614E13310) | EACH | 169 | $12.00 | $12.50 | $11.60 | $11.59 | $28.95 |
| 37 | Object marker, one way (614E13350) | EACH | 169 | $20.00 | $23.40 | $20.70 | $20.68 | $28.95 |
| 38 | Portable barrier, unanchored (622E41100) | FT | 8,300 | $27.00 | $34.00 | $31.40 | $31.41 | $37.05 |
| 39 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $33,500 | $19,427 | $16,026 | $67,202 |
| 40 | Maintaining traffic (614E11000) | LS | 1 | $40,000 | $49,850 | $45,655 | $38,169 | $60,676 |
| 41 | Construction layout stakes and surveying (623E10000) | LS | 1 | $12,500 | $19,995 | $15,500 | $10,200 | $25,938 |
| 42 | Mobilization (624E10000) | LS | 1 | $40,000 | $29,950 | $64,800 | $56,981 | $73,183 |
| 100 | Connection, fused pull apart (625E00450) | EACH | 3 | $235.00 | $244.00 | $211.00 | $225.00 | $578.95 |
| 101 | Conduit, 2", 725.051 (625E25408) | FT | 100 | $17.95 | $16.50 | $19.20 | $15.00 | $18.53 |
| 102 | Conduit, misc.:' remove and dispose existing 1-1/2 (625E25920) | FT | 100 | $23.60 | $8.70 | $135.00 | $8.00 | $10.42 |
| 103 | Trench, 24" deep (625E29002) | FT | 100 | $23.00 | $27.20 | $22.30 | $25.00 | $28.95 |
| 104 | Pull box, 725.08, 18" (625E30700) | EACH | 1 | $1,870.00 | $2,435.00 | $1,498.00 | $2,250.00 | $1,968.42 |
| 105 | Special - maintain existing lighting (625E40000) | LS | 1 | $1,240.00 | $22,695 | $10,293 | $21,000 | $3,421.05 |
| 106 | Disconnect circuit (625E75800) | EACH | 1 | $640.00 | $1,085.00 | $1,115.00 | $1,000.00 | $578.95 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 10, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.