ODOT contract 250412 bid tabulation
HIG-US 62-17.10 (BRIDGE REPAIR). Let by Ohio DOT on September 11, 2025, HIG. 3 bids received; low bid $221,601 by Double Z Construction Company, +12% against the engineer's estimate of $197,000.
- Owner
- Ohio DOT
- Letting
- 11 SEP 2025
- Pay items
- 22
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Double Z Construction Company | $221,601 | Low | +12% |
| 2 | Complete General Construction Company | $304,509 | +37% | +55% |
| 3 | KT Holden Construction LLC | $323,890 | +46% | +64% |
Engineer's estimate: $197,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Double Z Construction Company | 2. Complete General Construction Company | 3. KT Holden Construction LLC |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,000.00 | $9,000.00 | $10,500 |
| 2 | Seeding and mulching (659E10000) | SY | 565 | $12.00 | $3.75 | $2.25 |
| 3 | Repair seeding and mulching (659E14000) | SY | 28 | $1.00 | $1.00 | $2.20 |
| 4 | Commercial fertilizer (659E20000) | TON | 0.08 | $1,500.00 | $1,500.00 | $1,400.00 |
| 5 | Lime (659E31000) | ACRE | 0.12 | $200.00 | $200.00 | $450.00 |
| 6 | Water (659E35000) | MGAL | 3 | $1.00 | $1.00 | $3.50 |
| 7 | Erosion control (832E30000) | EACH | 2,000 | $1.00 | $1.00 | $1.00 |
| 8 | Water (616E10000) | MGAL | 1 | $1.00 | $150.00 | $20.00 |
| 9 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $10,000 | $45,000 | $29,590 |
| 10 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $60,000 | $75,000 | $118,045 |
| 11 | Unclassified excavation (503E21300) | LS | 1 | $15,000 | $9,000.00 | $14,500 |
| 12 | Epoxy coated steel reinforcement (509E10000) | LB | 715 | $3.00 | $11.00 | $7.00 |
| 13 | Dowel holes with nonshrink, nonmetallic grout, as per plan (510E10001) | EACH | 176 | $40.00 | $50.00 | $26.00 |
| 14 | Class QC SCC concrete, abutment (511E45720) | CY | 5 | $3,650.00 | $7,500.00 | $5,615.00 |
| 15 | Refurbish bearing device, as per plan (516E45305) | EACH | 2 | $6,200.00 | $7,500.00 | $5,000.00 |
| 16 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $24,500 | $35,000 | $49,780 |
| 17 | Patching concrete structure (519E11100) | SF | 50 | $200.00 | $365.00 | $230.00 |
| 18 | Rock channel protection, type A with aggregate filter (601E32010) | CY | 18 | $245.00 | $425.00 | $255.00 |
| 19 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $1,900.00 | $2,500.00 | $6,155.00 |
| 20 | Maintaining traffic (614E11000) | LS | 1 | $20,000 | $11,000 | $10,000 |
| 21 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,000.00 | $4,000.00 | $1,850.00 |
| 22 | Mobilization (624E10000) | LS | 1 | $20,000 | $14,500 | $16,195 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.