ODOT contract 250342 bid tabulation
CLI-SR 28-16.91 (BRIDGE REPAIR). Let by Ohio DOT on July 17, 2025, CLI. 4 bids received; low bid $462,732 by Sunesis Construction Co.
- Owner
- Ohio DOT
- Letting
- 17 JUL 2025
- Pay items
- 57
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Sunesis Construction Co | $462,732 | Low |
| 2 | KT Holden Construction LLC | $595,954 | +29% |
| 3 | Axis Civil Construction LLC | $674,167 | +46% |
| 4 | Complete General Construction Company | $702,827 | +52% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sunesis Construction Co | 2. KT Holden Construction LLC | 3. Axis Civil Construction LLC | 4. Complete General Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $6,238.00 | $17,244 | $15,000 | $6,000.00 |
| 2 | Pavement removed (202E23000) | SY | 36 | $56.00 | $78.75 | $40.00 | $185.00 |
| 3 | Embankment (203E20000) | CY | 7 | $44.00 | $187.27 | $65.00 | $70.00 |
| 4 | Subgrade compaction (204E10000) | SY | 37 | $12.00 | $32.51 | $10.00 | $20.00 |
| 5 | Topsoil (659E00300) | CY | 7 | $45.00 | $262.65 | $80.00 | $100.00 |
| 6 | Seeding and mulching (659E10000) | SY | 67 | $50.00 | $38.50 | $8.00 | $38.50 |
| 7 | Repair seeding and mulching (659E14000) | SY | 3 | $125.00 | $10.00 | $8.00 | $10.00 |
| 8 | Inter-seeding (659E15000) | SY | 3 | $125.00 | $0.50 | $5.00 | $0.50 |
| 9 | Commercial fertilizer (659E20000) | TON | 0.01 | $3,000.00 | $1,750.00 | $1,500.00 | $1,750.00 |
| 10 | Lime (659E31000) | ACRE | 0.01 | $1,000.00 | $50.00 | $2,000.00 | $50.00 |
| 11 | Water (659E35000) | MGAL | 1 | $10.00 | $1.00 | $1.00 | $1.00 |
| 12 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 13 | Pavement planing, asphalt concrete (T=1-1/4") (254E01000) | SY | 1,431 | $3.00 | $6.68 | $8.00 | $10.00 |
| 14 | Pavement planing, asphalt concrete (T=1-1/4"-3") (254E01000) | SY | 313 | $3.00 | $10.47 | $18.00 | $12.50 |
| 15 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 6 | $130.00 | $4,000.00 | $600.00 | $4,000.00 |
| 16 | Aggregate base (304E20000) | CY | 6 | $260.00 | $415.35 | $200.00 | $250.00 |
| 17 | Non-tracking tack coat (407E20000) | GAL | 145 | $5.00 | $10.00 | $9.00 | $10.00 |
| 18 | Stabilized crushed aggregate (411E10000) | CY | 6 | $1,021.00 | $449.83 | $290.00 | $200.00 |
| 19 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 61 | $185.00 | $550.00 | $450.00 | $550.00 |
| 20 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 2 | $165.00 | $4,000.00 | $750.00 | $4,000.00 |
| 21 | Manhole adjusted to grade (611E99654) | EACH | 2 | $600.00 | $1,274.67 | $1,600.00 | $2,000.00 |
| 22 | Barrier reflector, type 1 (bidirectional) (626E00102) | EACH | 2 | $10.00 | $12.75 | $20.00 | $95.00 |
| 23 | Barrier reflector, type 2 (bidirectional) (626E00110) | EACH | 7 | $8.00 | $12.84 | $20.00 | $95.00 |
| 24 | Edge line, 4" (644E00100) | MI | 0.18 | $9,645.00 | $10,690 | $18,495 | $9,645.00 |
| 25 | Center line (644E00300) | MI | 0.09 | $19,288 | $19,665 | $19,925 | $19,288 |
| 26 | Edge line, 4" (646E10000) | MI | 0.01 | $255,000 | $112,475 | $358,940 | $255,000 |
| 27 | Center line (646E10200) | MI | 0.01 | $50,000 | $224,885 | $360,330 | $50,000 |
| 28 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 48 | $80.00 | $80.00 | $80.00 | $95.00 |
| 29 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 4 | $2,204.00 | $2,203.78 | $2,500.00 | $2,497.00 |
| 30 | Detour signing (614E12420) | LS | 1 | $9,907.00 | $10,069 | $7,475.00 | $8,222.50 |
| 31 | Barrier reflector, type 1 (bidirectional) (614E13310) | EACH | 18 | $12.00 | $11.73 | $40.00 | $22.00 |
| 32 | Barrier reflector, type 2 (bidirectional) (614E13312) | EACH | 11 | $12.00 | $11.73 | $40.00 | $22.00 |
| 33 | Object marker, two way (614E13360) | EACH | 29 | $20.00 | $19.88 | $35.00 | $55.00 |
| 34 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 0.36 | $13,225 | $9,570.00 | $10,310 | $14,548 |
| 35 | Work zone stop line, class I, 642 paint (614E26200) | FT | 24 | $10.00 | $5.00 | $52.00 | $11.00 |
| 36 | Portable barrier, anchored (622E41110) | FT | 430 | $43.00 | $42.85 | $38.00 | $45.00 |
| 37 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $44,056 | $20,790 | $35,000 | $50,000 |
| 38 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $76.00 | $18,404 | $28,000 | $35,000 |
| 39 | Unclassified excavation (503E21300) | LS | 1 | $1,684.00 | $10,475 | $25,000 | $15,000 |
| 40 | Galvanized steel reinforcement (509E26000) | LB | 7,118 | $4.00 | $4.49 | $4.50 | $3.50 |
| 41 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 1,181 | $20.00 | $23.83 | $40.00 | $20.00 |
| 42 | Class QC2 concrete, superstructure, as per plan (511E33413) | CY | 26 | $2,070.00 | $1,967.13 | $2,950.00 | $2,500.00 |
| 43 | Class QC2 concrete, superstructure, as per plan (511E33413) | CY | 8 | $3,718.00 | $7,234.38 | $7,900.00 | $7,500.00 |
| 44 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 11 | $445.00 | $391.31 | $185.00 | $100.00 |
| 45 | Sealing concrete bridge decks with HMWM resin (512E10300) | SY | 19 | $325.00 | $698.77 | $160.00 | $55.00 |
| 46 | Special - composite fiber wrap system (519E00100) | SF | 173 | $38.00 | $33.54 | $96.00 | $185.00 |
| 47 | Patching concrete structure, as per plan (519E11101) | SF | 38 | $165.00 | $145.34 | $1,250.00 | $200.00 |
| 48 | Special - structures, misc.: temporary support (530E00200) | LS | 1 | $33,186 | $39,368 | $35,000 | $50,000 |
| 49 | Special - asbestos abatement - work involving asbe (690E71000) | LS | 1 | $304.00 | $1,743.79 | $200.00 | $6,000.00 |
| 50 | Micro silica modified concrete overlay, as per plan (847E10001) | SY | 22 | $515.00 | $779.95 | $280.00 | $2,000.00 |
| 51 | Wearing course removed, asphalt (847E30300) | SY | 113 | $63.00 | $115.63 | $85.00 | $90.00 |
| 52 | Existing concrete overlay removed, as per plan (1- (847E30401) | SY | 13 | $1,449.00 | $93.65 | $250.00 | $1,000.00 |
| 53 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,332.00 | $11,621 | $6,500.00 | $5,500.00 |
| 54 | Maintaining traffic (614E11000) | LS | 1 | $19,710 | $40,417 | $35,000 | $30,000 |
| 55 | Field office, type B (619E16010) | MNTH | 6 | $2,227.00 | $2,325.41 | $2,800.00 | $2,500.00 |
| 56 | Construction layout stakes and surveying (623E10000) | LS | 1 | $6,700.00 | $7,460.00 | $7,500.00 | $7,500.00 |
| 57 | Mobilization (624E10000) | LS | 1 | $44,177 | $29,798 | $40,000 | $35,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 17, 2025. Compiled by Mirage Metrics.