ODOT contract 250319 bid tabulation
HAM-IR 74-11.25 (MISCELLANEOUS). Let by Ohio DOT on June 26, 2025, HAM. 4 bids received; low bid $429,044 by Sunesis Construction Co, -0.7% against the engineer's estimate of $432,000.
- Owner
- Ohio DOT
- Letting
- 26 JUN 2025
- Pay items
- 42
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Sunesis Construction Co | $429,044 | Low | -1.0% |
| 2 | KT Holden Construction LLC | $440,069 | +3.0% | +2.0% |
| 3 | Rack & Ballauer Excavating Co Inc | $694,000 | +62% | +61% |
| 4 | John R Jurgensen Company | $893,342 | +108% | +107% |
Engineer's estimate: $432,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sunesis Construction Co | 2. KT Holden Construction LLC | 3. Rack & Ballauer Excavating Co Inc | 4. John R Jurgensen Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $9,015.03 | $9,000.00 | $25,000 | $70,113 |
| 2 | Headwall removed (202E20010) | EACH | 1 | $314.91 | $550.00 | $846.00 | $2,004.94 |
| 3 | Concrete slope protection removed, as per plan (202E32801) | SY | 613 | $36.39 | $35.00 | $75.00 | $165.81 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 130 | $13.68 | $11.00 | $30.00 | $152.23 |
| 5 | Fence removed (202E75000) | FT | 508 | $7.24 | $3.50 | $7.00 | $3.50 |
| 6 | Fence, type CLT (607E23000) | FT | 294 | $55.00 | $42.50 | $43.00 | $42.50 |
| 7 | Fence removed and rebuilt, as per plan (607E35001) | FT | 35 | $75.00 | $59.20 | $60.00 | $59.20 |
| 8 | Monument assembly, type C (623E38500) | EACH | 3 | $1,657.91 | $1,600.00 | $3,000.00 | $2,058.25 |
| 9 | Riprap, type A, as per plan (601E10971) | SY | 197 | $46.94 | $200.00 | $375.00 | $525.47 |
| 10 | Soil analysis test (659E00100) | EACH | 2 | $90.00 | $90.00 | $150.00 | $150.00 |
| 11 | Topsoil (659E00300) | CY | 810 | $64.92 | $65.00 | $90.00 | $65.25 |
| 12 | Seeding and mulching, class 1 (659E00500) | SY | 1,238 | $4.50 | $3.00 | $2.50 | $2.30 |
| 13 | Seeding and mulching, class 5B (659E00580) | SY | 6,053 | $4.54 | $3.00 | $2.00 | $1.92 |
| 14 | Repair seeding and mulching (659E14000) | SY | 365 | $3.00 | $3.00 | $2.40 | $2.30 |
| 15 | Inter-seeding (659E15000) | SY | 365 | $3.00 | $3.00 | $1.00 | $1.25 |
| 16 | Commercial fertilizer (659E20000) | TON | 1.02 | $760.00 | $760.00 | $900.00 | $900.00 |
| 17 | Lime (659E31000) | ACRE | 1.51 | $30.00 | $30.00 | $100.00 | $100.00 |
| 18 | Water (659E35000) | MGAL | 40 | $30.00 | $30.00 | $1.00 | $1.00 |
| 19 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,575.00 | $3,000.00 | $3,000.00 | $2,635.00 |
| 20 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $1,680.00 | $6,200.00 | $10,500 | $9,250.00 |
| 21 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $15,000 | $11,500 | $11,500 | $11,333 |
| 22 | Erosion control (832E30000) | EACH | 29,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 23 | Concrete masonry, as per plan (602E20001) | CY | 3 | $6,021.67 | $1,660.00 | $10,000 | $6,215.85 |
| 24 | Conduit, misc.: type B for drainage discharge cont (611E97400) | FT | 100 | $53.77 | $19.00 | $70.00 | $100.24 |
| 25 | Conduit, misc.: type C for drainage discharge cont (611E97400) | FT | 100 | $46.87 | $19.00 | $60.00 | $95.17 |
| 26 | Conduit, misc.: type E for drainage discharge cont (611E97400) | FT | 100 | $43.79 | $19.00 | $50.00 | $90.15 |
| 27 | Conduit, misc.: type F for drainage discharge cont (611E97400) | FT | 100 | $43.79 | $19.00 | $40.00 | $90.15 |
| 28 | Deciduous tree, 1" caliper, black tupelo (nyssa SY (661E40040) | EACH | 5 | $380.00 | $380.00 | $400.00 | $400.00 |
| 29 | Deciduous tree, 1" caliper, silver maple (acer SA (661E40040) | EACH | 5 | $380.00 | $380.00 | $350.00 | $350.00 |
| 30 | Deciduous tree, 1" caliper, sycamore (platanus occ (661E40040) | EACH | 5 | $380.00 | $380.00 | $350.00 | $350.00 |
| 31 | Deciduous tree, 1" caliper, white oak (quercus alb (661E40040) | EACH | 5 | $380.00 | $380.00 | $700.00 | $700.00 |
| 32 | Water (616E10000) | MGAL | 5 | $17.83 | $25.00 | $1.00 | $150.98 |
| 33 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $19,421 | $57,510 | $7,500.00 | $75,137 |
| 34 | Concrete repair by epoxy injection (512E10600) | FT | 10 | $128.38 | $550.00 | $500.00 | $500.62 |
| 35 | Drilled shafts, 36" diameter, above bedrock, as per plan (524E94703) | FT | 25 | $127.57 | $100.00 | $220.00 | $550.77 |
| 36 | Drilled shafts, 36" diameter, above bedrock, as per plan (524E94703) | FT | 30 | $368.29 | $101.00 | $445.00 | $770.29 |
| 37 | Drilled shafts, 36" diameter, into bedrock, as per plan (524E94705) | FT | 95 | $272.81 | $198.00 | $260.00 | $400.79 |
| 38 | Drilled shafts, 36" diameter, into bedrock, as per plan (524E94705) | FT | 174 | $462.77 | $390.00 | $450.00 | $580.52 |
| 39 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,089.12 | $8,580.00 | $7,000.00 | $10,070 |
| 40 | Maintaining traffic (614E11000) | LS | 1 | $1,709.98 | $7,600.00 | $15,000 | $59,161 |
| 41 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,950.00 | $5,000.00 | $15,000 | $15,699 |
| 42 | Mobilization (624E10000) | LS | 1 | $26,946 | $21,780 | $140,000 | $44,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of June 26, 2025. Compiled by Mirage Metrics.