ODOT contract 260225 bid tabulation
WAR-Central Greenway SUP Seg D (BIKEWAYS). Let by Ohio DOT on April 23, 2026, WAR. 5 bids received; low bid $697,462 by Fillmore Construction, -3.0% against the engineer's estimate of $719,000.
- Owner
- Ohio DOT
- Letting
- 23 APR 2026
- Pay items
- 52
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Fillmore Construction | $697,462 | Low | -3.0% |
| 2 | Brumbaugh Construction Inc | $707,952 | +2.0% | -2.0% |
| 3 | KT Holden Construction LLC | $787,976 | +13% | +10% |
| 4 | Sunesis Construction Co | $814,719 | +17% | +13% |
| 5 | Barrett Paving Materials Inc | $868,892 | +25% | +21% |
Engineer's estimate: $719,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fillmore Construction | 2. Brumbaugh Construction Inc | 3. KT Holden Construction LLC | 4. Sunesis Construction Co | 5. Barrett Paving Materials Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $50,000 | $55,862 | $40,160 | $50,000 | $40,000 |
| 2 | Pavement removed (202E23000) | SY | 270 | $10.00 | $13.00 | $12.00 | $14.84 | $20.00 |
| 3 | Walk removed (202E30000) | SF | 115 | $10.00 | $4.00 | $5.00 | $5.81 | $15.00 |
| 4 | Curb removed (202E32000) | FT | 234 | $10.00 | $12.00 | $9.00 | $14.90 | $11.00 |
| 5 | Excavation (203E10000) | CY | 4,124 | $30.00 | $24.00 | $33.00 | $39.45 | $40.00 |
| 6 | Embankment (203E20000) | CY | 458 | $50.00 | $20.00 | $23.00 | $9.52 | $30.00 |
| 7 | Excavation of subgrade (204E13000) | CY | 1,200 | $30.00 | $24.00 | $38.50 | $48.10 | $40.00 |
| 8 | Granular material, type B (204E30010) | CY | 1,200 | $60.00 | $55.00 | $56.50 | $83.54 | $80.00 |
| 9 | Geotextile fabric (204E50000) | SY | 3,600 | $2.00 | $2.00 | $3.60 | $1.59 | $2.50 |
| 10 | Fence, misc.:wood fence (607E98000) | FT | 150 | $80.00 | $70.00 | $65.00 | $70.00 | $50.00 |
| 11 | Curb ramp (608E52000) | SF | 66 | $50.00 | $250.00 | $35.00 | $103.74 | $100.00 |
| 12 | Special - bollard (690E50600) | EACH | 2 | $3,500.00 | $800.00 | $750.00 | $2,502.48 | $1,300.00 |
| 15 | Rock channel protection, type C with filter (601E32200) | CY | 3 | $180.00 | $380.00 | $400.00 | $566.55 | $1,000.00 |
| 16 | Topsoil (659E00300) | CY | 515 | $60.00 | $69.00 | $62.00 | $33.75 | $65.00 |
| 17 | Seeding and mulching, class 1 (659E00500) | SY | 4,624 | $1.45 | $1.50 | $1.45 | $2.55 | $1.25 |
| 18 | Repair seeding and mulching (659E14000) | SY | 231 | $2.20 | $1.50 | $2.20 | $2.20 | $1.25 |
| 19 | Commercial fertilizer (659E20000) | TON | 0.62 | $1,400.00 | $1,075.00 | $1,400.00 | $1,400.00 | $1,000.00 |
| 20 | Water (659E35000) | MGAL | 25 | $10.00 | $1.00 | $3.50 | $0.01 | $1.00 |
| 21 | Slope erosion protection (670E00500) | SY | 1,723 | $2.00 | $4.00 | $2.00 | $3.10 | $3.50 |
| 22 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,500.00 | $2,750.00 | $3,500.00 | $12,673 | $3,000.00 |
| 23 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $7,500.00 | $8,500.00 | $4,000.00 | $0.48 | $10,000 |
| 24 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $10,000 | $16,500 | $13,000 | $15,000 | $15,000 |
| 25 | Erosion control (832E30000) | EACH | 40,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 26 | Concrete masonry (602E20000) | CY | 1.47 | $3,000.00 | $5,650.00 | $4,150.00 | $1,074.17 | $6,000.00 |
| 27 | 12" conduit, type C (611E04600) | FT | 162 | $100.00 | $80.00 | $130.00 | $83.92 | $110.00 |
| 28 | 12" conduit, type D (611E04900) | FT | 86 | $80.00 | $80.00 | $95.00 | $80.53 | $110.00 |
| 29 | Catch basin, no. 2-2C (611E98504) | EACH | 2 | $6,500.00 | $2,900.00 | $3,000.00 | $3,488.71 | $5,250.00 |
| 30 | Catch basin adjusted to grade (611E98630) | EACH | 1 | $1,500.00 | $350.00 | $915.00 | $1,046.57 | $2,325.00 |
| 31 | Manhole, no. 3 (611E99574) | EACH | 1 | $10,000 | $3,200.00 | $3,000.00 | $4,517.53 | $6,100.00 |
| 32 | Subgrade compaction (204E10000) | SY | 3,440 | $3.00 | $1.25 | $5.50 | $2.50 | $2.50 |
| 33 | Proof rolling (204E45000) | HR | 4 | $150.00 | $300.00 | $390.00 | $256.84 | $250.00 |
| 34 | Aggregate base (304E20000) | CY | 575 | $80.00 | $75.00 | $100.00 | $94.62 | $115.00 |
| 35 | Non-tracking tack coat (407E20000) | GAL | 344 | $3.50 | $5.00 | $5.00 | $4.50 | $5.00 |
| 36 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 119 | $246.00 | $325.00 | $334.00 | $350.00 | $400.00 |
| 37 | Asphalt concrete intermediate course, type 2, (448) (441E50300) | CY | 94 | $242.00 | $305.00 | $315.00 | $379.20 | $375.00 |
| 38 | Curb, type 6 (609E26000) | FT | 145 | $50.00 | $100.00 | $78.00 | $84.67 | $82.00 |
| 39 | Ground mounted support, no. 3 post (630E03100) | FT | 144 | $15.00 | $17.00 | $16.00 | $20.00 | $15.00 |
| 40 | Sign, flat sheet (630E80100) | SF | 52.50 | $16.00 | $26.00 | $25.00 | $30.00 | $16.00 |
| 41 | Removal of ground mounted sign and disposal (630E84900) | EACH | 1 | $20.00 | $16.00 | $15.00 | $25.00 | $20.00 |
| 42 | Removal of ground mounted sign and reerection (630E85100) | EACH | 1 | $45.00 | $75.00 | $70.00 | $250.00 | $45.00 |
| 43 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $65.00 | $50.00 | $50.00 | $25.00 | $65.00 |
| 44 | Signing, misc.:solar powered rectangular rapid fla (630E97700) | EACH | 2 | $7,495.00 | $9,250.00 | $8,600.00 | $10,340 | $7,500.00 |
| 45 | Pedestal foundation (632E64020) | EACH | 2 | $2,500.00 | $1,300.00 | $1,250.00 | $2,500.00 | $3,000.00 |
| 46 | Stop line, type 1 (642E00500) | FT | 12 | $12.31 | $13.00 | $12.35 | $12.31 | $12.31 |
| 47 | Crosswalk line, 24", type 1 (642E00630) | FT | 180 | $12.31 | $13.00 | $12.35 | $12.31 | $12.31 |
| 48 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $4,500.00 | $6,500.00 | $13,790 | $5,210.71 | $5,000.00 |
| 49 | Maintaining traffic (614E11000) | LS | 1 | $17,500 | $2,000.00 | $33,700 | $5,973.68 | $25,000 |
| 50 | Field office, type B (619E16010) | MNTH | 3 | $1,000.00 | $2,750.00 | $1,600.00 | $1,551.67 | $3,000.00 |
| 51 | Construction layout stakes and surveying (623E10000) | LS | 1 | $7,500.00 | $15,000 | $21,050 | $11,400 | $24,905 |
| 52 | Mobilization (624E10000) | LS | 1 | $18,000 | $55,000 | $39,400 | $46,140 | $30,000 |
| 100 | Special - trash receptacle, alternate 2 [alternate group AA2] (690E98000) | EACH | 1 | $2,500.00 | $750.00 | $460.00 | $1,100.00 | $900.00 |
| 101 | Special - bench, alternate 2 [alternate group AA2] (690E98000) | EACH | 1 | $5,000.00 | $2,500.00 | $4,820.00 | $1,100.00 | $5,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 23, 2026. Compiled by Mirage Metrics.