ODOT contract 250136 bid tabulation

WAR-US 42-20.23 (INTERSECTION). Let by Ohio DOT on February 27, 2025, WAR. 5 bids received; low bid $1,290,000 by Barrett Paving Materials Inc, +14% against the engineer's estimate of $1,128,000.

Owner
Ohio DOT
Letting
27 FEB 2025
Pay items
136
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Barrett Paving Materials Inc$1,290,000Low+14%
2KT Holden Construction LLC$1,303,469+1.0%+16%
3John R Jurgensen Company$1,352,658+5.0%+20%
4Complete General Construction Company$1,424,794+10%+26%
5Sunesis Construction Co$1,476,404+14%+31%
ODOT contract 250136: bids by rank

Engineer's estimate: $1,128,000.

Bid tabulation

LinePay itemUnitQuantity1. Barrett Paving Materials Inc2. KT Holden Construction LLC3. John R Jurgensen Company4. Complete General Construction Company5. Sunesis Construction Co
1Clearing and grubbing (201E11000)LS1$5,000.00$7,500.00$2,750.75$5,000.00$24,685
2Pavement removed (202E23000)SY765$25.00$33.50$48.18$35.00$76.54
3Walk removed (202E30000)SF1,185$6.00$3.30$5.22$7.00$4.54
4Concrete median removed (202E30600)SY74$90.00$32.10$34.48$52.00$29.55
5Curb removed (202E32000)FT974$9.00$9.10$5.93$10.00$8.82
6Pipe removed, 24" and under (202E35100)FT60$30.00$32.55$77.14$95.00$35.15
7Catch basin removed (202E58100)EACH5$240.00$678.00$670.14$450.00$594.98
8Removal misc.:decorative plaque (202E98100)EACH1$400.00$344.00$465.44$1,800.00$159.62
9Excavation (203E10000)CY567$42.00$47.60$75.38$35.00$94.89
10Embankment (203E20000)CY131$42.00$43.10$61.07$25.00$46.31
11Subgrade compaction (204E10000)SY1,506$4.00$10.40$3.65$4.00$7.86
12Excavation of subgrade (204E13000)CY465$45.00$54.50$83.89$42.00$65.08
13Granular material, type C (204E30020)CY465$70.00$71.50$101.59$46.00$122.24
14Proof rolling (204E45000)HR0.90$1,500.00$406.00$278.13$386.00$435.26
15Geotextile fabric (204E50000)SY1,393$5.00$1.10$3.98$2.50$4.13
164" concrete walk (608E10000)SF1,140$7.00$11.50$8.71$15.00$18.38
17Curb ramp (608E52000)SF332$20.00$29.00$25.13$35.00$37.38
18Soil analysis test (659E00100)EACH2$135.00$150.00$135.00$135.00$75.00
19Topsoil (659E00300)CY85$115.00$90.60$85.13$115.00$48.26
20Seeding and mulching (659E10000)SY763$3.46$2.25$3.46$3.46$9.16
21Repair seeding and mulching (659E14000)SY38$3.46$2.00$3.46$3.46$2.91
22Inter-seeding (659E15000)SY38$1.00$2.00$1.00$1.00$2.91
23Commercial fertilizer (659E20000)TON0.17$1,000.00$1,400.00$1,000.00$1,000.00$2,033.82
24Lime (659E31000)ACRE0.16$190.00$450.00$190.00$190.00$653.75
25Water (659E35000)MGAL4$10.00$10.00$10.00$10.00$20.00
26Mowing (659E40000)MSF2$200.00$15.00$200.00$200.00$21.79
27Erosion control (832E30000)EACH20,000$1.00$1.00$1.00$1.00$1.00
28Rock channel protection, type C with filter (601E32200)CY1.10$300.00$1,085.00$2,691.61$578.25$713.55
29Concrete masonry (602E20000)CY0.20$2,000.00$5,600.00$17,047$5,000.00$5,659.60
306" base pipe underdrains (605E14000)FT1,502$16.00$15.05$38.92$25.00$21.03
316" conduit, type F for underdrain outlets (611E00510)FT132$35.00$37.50$54.23$34.00$53.25
3212" conduit, type B (611E04400)FT304$220.00$157.00$132.32$200.00$117.99
3312" conduit, type C (611E04600)FT10$450.00$136.30$213.34$195.00$424.92
3415" conduit, type B (611E05900)FT28$500.00$285.00$410.54$230.00$411.77
3524" conduit, type B (611E10400)FT16$560.00$315.50$615.48$350.00$397.00
3624" conduit, type C (611E10600)FT14$700.00$440.50$765.80$300.00$471.17
37Catch basin, no. 3 (611E98150)EACH2$6,000.00$5,910.00$5,479.34$5,500.00$6,544.13
38Catch basin, no. 3A (611E98180)EACH4$3,500.00$3,830.00$3,357.30$5,000.00$4,161.83
39Catch basin, no. 6 (611E98370)EACH2$4,750.00$3,620.00$4,917.78$5,800.00$4,401.84
40Catch basin, no. 2-2B (611E98470)EACH1$2,250.00$2,147.00$1,933.47$3,500.00$2,039.49
41Manhole, no. 3 (611E99574)EACH3$7,000.00$7,620.00$8,708.24$5,500.00$5,332.89
42Trench drain, type A with standard grate (839E29000)FT190$325.00$397.00$338.95$350.00$602.49
43Asphalt concrete base, PG64-22, (449) (301E56000)CY297$250.00$425.00$425.00$425.00$432.54
44Aggregate base (304E20000)CY240$115.00$128.60$143.77$90.00$116.95
45Non-tracking tack coat (407E20000)GAL198$3.75$5.00$5.00$5.00$5.00
46Asphalt concrete surface course, 12.5 MM, type A (449) (442E22100)CY100$535.00$605.00$605.00$605.00$605.00
478" non-reinforced concrete pavement, class QC 1P (452E12010)SY113$104.00$124.00$115.24$140.00$104.00
48Curb, type 4-C (609E24510)FT523$22.00$27.20$26.60$55.00$33.10
49Curb, type 6 (609E26000)FT208$23.00$28.30$27.93$60.00$34.20
50Concrete median (609E72000)SY138$63.00$85.00$71.11$115.00$63.00
51Fire hydrant extended and adjusted to grade (638E10300)EACH1$7,500.00$15,100$9,861.56$1,500.00$15,447
52RPM (621E00100)EACH29$120.00$120.00$120.00$103.00$120.00
53Raised pavement marker removed (621E54000)EACH4$1.00$25.50$14.02$20.00$36.99
54Ground mounted support, no. 3 post (630E03100)FT140$19.80$19.80$19.80$19.80$14.75
55Sign post reflector (630E08600)EACH1$60.00$60.00$60.00$60.00$60.00
56Sign, flat sheet (630E80100)SF54.50$20.00$20.00$20.00$20.00$22.50
57Removal of ground mounted sign and disposal (630E84900)EACH21$15.00$15.00$15.00$15.00$25.00
58Removal of ground mounted post support and disposal (630E86002)EACH11$20.00$20.00$20.00$20.00$75.00
59Removal of ground mounted pipe support and disposal (630E86272)EACH1$60.00$60.00$60.00$60.00$75.00
60Edge line, 6" (644E00104)MI0.12$14,000$14,000$14,000$4,500.00$14,000
61Center line (644E00300)MI0.08$15,000$15,000$15,000$9,038.00$15,000
62Channelizing line, 12" (644E00404)FT636$2.00$2.00$2.00$2.00$2.00
63Stop line (644E00500)FT109$6.00$6.00$6.00$8.00$6.00
64Transverse/diagonal line (644E00700)FT190$5.25$5.25$5.25$8.00$5.25
65Chevron marking (644E00720)FT196$5.25$5.25$5.25$7.00$5.25
66Island marking (644E00900)SF23$5.00$5.00$5.00$10.00$5.00
67Lane arrow (644E01300)EACH6$150.00$150.00$150.00$130.00$150.00
68Removal of pavement marking (644E30000)FT414$5.00$5.00$5.00$6.04$5.00
69Crosswalk line, 24", type B90 (647E20080)FT200$14.00$14.00$14.00$19.78$14.00
70Connection, fused pull apart (625E00450)EACH2$110.00$110.00$110.00$175.00$209.00
71Connection, unfused pull apart (625E00460)EACH2$110.00$110.00$110.00$175.00$209.00
72Bracket arm, 10' (625E18000)EACH2$850.00$850.00$850.00$1,500.00$819.00
73No. 8 AWG 600 volt distribution cable (625E23304)FT1,062$2.50$2.50$2.50$3.00$2.75
74No. 10 AWG pole and bracket cable (625E23400)FT240$1.50$1.50$1.50$2.50$2.15
75Conduit, 2", 725.051 (625E25408)FT62$13.00$13.00$13.00$15.00$9.50
76Conduit, 3", 725.051 (625E25504)FT161$16.50$16.50$16.50$16.00$14.95
77Conduit, 4", 725.051 (625E25604)FT96$20.00$20.00$20.00$30.00$19.00
78Conduit, concrete encased, 2" (625E25802)FT4$125.00$125.00$125.00$90.00$111.90
79Conduit, jacked or drilled, 725.052, 2" (625E25908)FT268$36.00$36.00$36.00$40.00$38.40
80Conduit, jacked or drilled, 725.052, 4" (625E25908)FT268$41.00$41.00$41.00$70.00$46.90
81Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH2$525.00$525.00$525.00$1,125.00$553.00
82Trench (625E29000)FT272$14.00$14.00$14.00$13.00$16.95
83Pull box, 725.08, 24" (625E30706)EACH3$1,250.00$1,250.00$1,250.00$1,400.00$2,921.97
84Ground rod (625E32000)EACH8$265.00$265.00$265.00$300.00$292.00
85Sign hanger assembly, mast arm (630E79100)EACH6$450.00$450.00$450.00$450.00$559.00
86Sign support assembly, pole mounted (630E79500)EACH6$295.00$295.00$295.00$295.00$180.00
87Sign, flat sheet (630E80100)SF22$21.50$21.50$21.50$21.50$22.50
88Sign, street name (630E80510)EACH6$195.00$195.00$195.00$195.00$355.00
89Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006)EACH11$1,275.00$1,275.00$1,275.00$1,300.00$1,300.00
90Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731)EACH4$850.00$850.00$850.00$800.00$1,006.00
91Covering of vehicular signal head (632E25000)EACH11$40.00$40.00$40.00$40.00$47.00
92Covering of pedestrian signal head (632E25010)EACH4$30.00$30.00$30.00$35.00$47.00
93Pedestrian pushbutton (632E26000)EACH4$275.00$275.00$275.00$400.00$277.00
94Signal cable, 5 conductor, no. 14 AWG (632E40500)FT1,956$3.00$3.00$3.00$3.25$2.90
95Signal cable, 7 conductor, no. 14 AWG (632E40700)FT515$3.25$3.25$3.25$3.50$3.50
96Signal support foundation, as per plan (632E64011)EACH3$7,900.00$7,900.00$7,900.00$13,000$8,795.00
97Pedestal foundation, as per plan (632E64021)EACH4$1,150.00$1,150.00$1,150.00$2,000.00$1,321.00
98Loop detector lead-in cable (632E65200)FT821$2.00$2.00$2.00$2.25$2.25
99Power cable, 2 conductor, no. 6 AWG (632E68200)FT83$5.75$5.75$5.75$5.00$4.75
100Power cable, 3 conductor, no. 6 AWG (632E68300)FT50$8.25$8.25$8.25$5.50$5.95
101Power service, as per plan (632E70001)EACH1$2,500.00$2,500.00$2,500.00$4,000.00$4,252.00
102Conduit riser, 2" diameter (632E70400)EACH1$600.00$600.00$600.00$1,250.00$773.00
103Signal support, type TC-81.22, design 12, as per plan (632E72131)EACH1$14,500$14,500$14,500$20,000$19,373
104Combination signal support, type TC-12.31 design 1 (632E78497)EACH1$39,000$39,000$39,000$46,000$51,856
105Combination signal support, type TC-81.22, design 14, as per plan (632E79151)EACH1$21,350$21,350$21,350$22,500$25,238
106Pedestal, 11', transformer base (632E90000)EACH3$1,000.00$1,000.00$1,000.00$2,000.00$1,063.00
107Pedestal, misc.: pedestal, 17' transformer base (632E90010)EACH1$1,990.00$1,990.00$1,990.00$2,500.00$2,684.00
108Removal of traffic signal installation, as per plan (632E90101)EACH1$2,500.00$2,500.00$2,500.00$4,000.00$4,134.00
109Cabinet, type TS-2, as per plan (633E65511)EACH1$17,500$17,500$17,500$19,000$19,143
110Cabinet foundation (633E67100)EACH1$2,850.00$2,850.00$2,850.00$4,750.00$1,910.00
111Controller work pad (633E67200)EACH1$850.00$850.00$850.00$3,000.00$718.00
112Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001)EACH1$8,950.00$8,950.00$8,950.00$8,000.00$9,256.00
113Advance radar detection, as per plan (809E69001)EACH2$9,900.00$9,900.00$9,900.00$9,000.00$9,656.00
114Stop line radar detection, as per plan (809E69101)EACH4$9,700.00$9,700.00$9,700.00$8,800.00$9,311.00
115Atc controller, as per plan (809E69123)EACH1$5,800.00$5,800.00$5,800.00$4,800.00$6,036.00
116Law enforcement officer with patrol car for assistance (614E11110)HR104$100.00$80.00$136.46$90.00$85.00
117Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380)EACH4$2,400.00$2,400.00$2,400.00$2,520.00$2,400.00
118Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384)EACH3$2,400.00$2,400.00$2,400.00$2,520.00$2,400.00
119Work zone raised pavement marker (614E12800)EACH16$21.00$21.00$38.53$40.00$21.00
120Barrier reflector, type 1, one-way (614E13310)EACH29$14.00$14.00$14.00$20.00$14.00
121Object marker, one way (614E13350)EACH29$18.00$18.00$18.00$22.00$18.00
122Portable changeable message sign (614E18600)SNMT12$700.00$700.00$950.00$2,075.64$700.00
123Work zone center line, class III, 642 paint (614E21550)MI0.08$14,000$14,000$14,000$11,590$14,000
124Work zone edge line, class I, 6", 740.06, type I (614E22210)MI0.60$7,600.00$7,600.00$7,600.00$17,629$7,600.00
125Work zone edge line, class III, 6", 642 paint (614E22360)MI0.12$7,200.00$7,200.00$7,200.00$5,808.00$7,200.00
126Work zone channelizing line, class I, 12", 740.06, type I (614E23410)FT507$3.00$3.00$3.00$2.00$3.00
127Work zone channelizing line, class III, 12", 642 paint (614E23690)FT636$2.90$2.90$2.90$1.00$2.90
128Work zone dotted line, class I, 6", 740.06, type I (614E24402)FT1,166$1.50$1.50$1.50$1.50$1.50
129Water (616E10000)MGAL0.80$15.00$30.00$9.10$7,500.00$16.09
130Portable barrier, unanchored (622E41100)FT1,445$28.25$31.25$28.25$28.00$28.25
131Premium for contract performance bond and for payment bond (103E05000)LS1$9,306.49$19,550$8,601.69$13,000$8,521.08
132Maintaining traffic (614E11000)LS1$150,000$64,735$42,124$65,000$60,939
133Construction layout stakes and surveying (623E10000)LS1$30,000$12,740$5,671.61$41,000$13,500
134Mobilization (624E10000)LS1$20,000$65,170$67,500$75,000$62,807
135Special - consultant for concrete quality control (690E98400)LS1$15,000$9,740.00$4,605.00$15,000$3,000.00
136Inspection and compaction testing of unbound materials (878E25000)LS1$20,000$4,890.00$13,195$5,000.00$4,352.00
ODOT contract 250136: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of February 27, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy