ODOT contract 260122 bid tabulation
HAM-CR 299-05.78 Loveland Madeira (SIDEWALK). Let by Ohio DOT on March 12, 2026, HAM. 5 bids received; low bid $1,795,733 by Sunesis Construction Co, -4.2% against the engineer's estimate of $1,874,000.
- Owner
- Ohio DOT
- Letting
- 12 MAR 2026
- Pay items
- 91
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Sunesis Construction Co | $1,795,733 | Low | -4.0% |
| 2 | KT Holden Construction LLC | $1,871,213 | +4.0% | 0.0% |
| 3 | Prus Construction Company | $1,871,720 | +4.0% | 0.0% |
| 4 | John R Jurgensen Company | $2,312,714 | +29% | +23% |
| 5 | Ford Development Corp | $2,348,018 | +31% | +25% |
Engineer's estimate: $1,874,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sunesis Construction Co | 2. KT Holden Construction LLC | 3. Prus Construction Company | 4. John R Jurgensen Company | 5. Ford Development Corp |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $14,678 | $12,000 | $21,075 | $10,160 | $20,000 |
| 2 | Structure removed (202E11004) | EACH | 1 | $327.02 | $640.00 | $2,000.00 | $592.97 | $1,000.00 |
| 3 | Pavement removed (202E23000) | SY | 686 | $16.10 | $33.00 | $29.00 | $25.36 | $10.00 |
| 4 | Walk removed (202E30000) | SF | 228 | $3.09 | $6.50 | $3.75 | $6.11 | $3.00 |
| 5 | Curb removed (202E32000) | FT | 506 | $5.23 | $9.50 | $9.75 | $19.60 | $6.00 |
| 6 | Curb and gutter removed (202E32500) | FT | 145 | $5.93 | $20.00 | $14.00 | $18.49 | $10.00 |
| 7 | Pipe removed, 24" and under (202E35100) | FT | 114 | $12.54 | $6.00 | $13.00 | $70.63 | $20.00 |
| 8 | Guardrail removed (202E38000) | FT | 339 | $6.00 | $6.00 | $6.75 | $6.00 | $3.00 |
| 9 | Anchor assembly removed, type E (202E42010) | EACH | 1 | $175.00 | $175.00 | $195.00 | $175.00 | $150.00 |
| 10 | Anchor assembly removed, type T (202E42040) | EACH | 1 | $150.00 | $150.00 | $165.00 | $150.00 | $100.00 |
| 11 | Mailbox removed (202E53100) | EACH | 2 | $125.63 | $110.00 | $265.00 | $713.76 | $76.00 |
| 12 | Removal misc.:reflector post (202E98100) | EACH | 1 | $83.76 | $64.00 | $130.00 | $713.72 | $150.00 |
| 13 | Excavation (203E10000) | CY | 73 | $172.19 | $110.00 | $72.00 | $60.35 | $20.00 |
| 14 | Embankment (203E20000) | CY | 413 | $49.40 | $15.00 | $27.00 | $70.41 | $20.00 |
| 15 | Subgrade compaction (204E10000) | SY | 655 | $2.90 | $12.00 | $2.35 | $3.10 | $2.00 |
| 16 | 4" concrete walk (608E10000) | SF | 26,569 | $6.94 | $7.80 | $8.65 | $8.62 | $13.00 |
| 17 | Curb ramp (608E52000) | SF | 486 | $30.25 | $23.00 | $19.00 | $24.68 | $20.00 |
| 18 | Detectable warning (608E53020) | SF | 2 | $60.00 | $60.00 | $168.00 | $60.00 | $50.00 |
| 19 | Special - mailbox support (690E50000) | EACH | 2 | $199.27 | $350.00 | $275.00 | $708.01 | $200.00 |
| 20 | Rock channel protection, type C with filter (601E32200) | CY | 2 | $656.02 | $550.00 | $541.00 | $1,285.66 | $300.00 |
| 21 | Paved gutter, type 1-2 (601E37500) | FT | 265 | $84.98 | $92.00 | $122.00 | $188.00 | $180.00 |
| 22 | Paved gutter, type 1-2, as per plan (601E37501) | FT | 111 | $105.91 | $92.00 | $72.00 | $147.74 | $200.00 |
| 23 | Paved gutter, misc.: outlet (601E40000) | FT | 9 | $86.35 | $113.00 | $205.00 | $103.53 | $100.00 |
| 24 | Topsoil (659E00300) | CY | 106 | $49.08 | $80.00 | $108.00 | $115.00 | $20.00 |
| 25 | Seeding and mulching (659E10000) | SY | 951 | $10.46 | $2.50 | $5.50 | $2.50 | $1.00 |
| 26 | Commercial fertilizer (659E20000) | TON | 0.13 | $1,690.23 | $3,000.00 | $1,650.00 | $3,000.00 | $200.00 |
| 27 | Lime (659E31000) | ACRE | 0.20 | $543.30 | $250.00 | $220.00 | $250.00 | $100.00 |
| 28 | Water (659E35000) | MGAL | 5 | $1.39 | $50.00 | $1.00 | $50.00 | $10.00 |
| 29 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,100.00 | $2,100.00 | $2,350.00 | $2,000.00 | $2,000.00 |
| 30 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $6,420.24 | $12,840 | $5,400.00 | $14,400 | $4,000.00 |
| 31 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $16,174 | $16,200 | $17,800 | $16,174 | $10,000 |
| 32 | Erosion control (832E30000) | EACH | 34,650 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 33 | 6" base pipe underdrains (605E14000) | FT | 554 | $23.95 | $14.00 | $22.50 | $48.22 | $15.00 |
| 34 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 33 | $46.28 | $46.00 | $43.00 | $52.54 | $15.00 |
| 35 | Catch basin adjusted to grade (611E98630) | EACH | 1 | $703.64 | $1,200.00 | $2,300.00 | $1,594.18 | $1,000.00 |
| 36 | Catch basin reconstructed to grade (611E98634) | EACH | 2 | $1,783.17 | $1,300.00 | $1,350.00 | $3,600.65 | $1,500.00 |
| 37 | Manhole adjusted to grade (611E99654) | EACH | 1 | $452.76 | $625.00 | $1,000.00 | $1,594.18 | $1,000.00 |
| 38 | Trench drain, type A with pedestrian grate (839E29100) | FT | 20 | $411.04 | $500.00 | $475.00 | $668.84 | $400.00 |
| 39 | Full depth pavement sawing (252E01500) | FT | 66 | $4.55 | $4.20 | $2.00 | $3.00 | $2.00 |
| 40 | Pavement repair, as per plan (253E02001) | CY | 51 | $447.70 | $370.00 | $350.00 | $1,550.00 | $400.00 |
| 41 | Pavement planing, asphalt concrete (2") (254E01000) | SY | 67 | $36.90 | $44.00 | $24.25 | $90.00 | $20.00 |
| 42 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 19 | $438.90 | $495.00 | $485.00 | $1,700.00 | $600.00 |
| 43 | Tack coat (407E10000) | GAL | 8 | $41.34 | $41.35 | $10.00 | $10.00 | $10.00 |
| 44 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 22 | $511.88 | $555.00 | $475.00 | $875.00 | $800.00 |
| 45 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 5 | $933.86 | $1,100.00 | $795.00 | $2,025.00 | $1,000.00 |
| 46 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 428 | $100.00 | $125.00 | $132.00 | $117.19 | $140.00 |
| 47 | Combination curb and gutter, type 2 (609E12000) | FT | 119 | $54.35 | $45.00 | $43.00 | $59.05 | $80.00 |
| 48 | Curb, type 6 (609E26000) | FT | 646 | $34.59 | $30.00 | $40.00 | $39.80 | $60.00 |
| 49 | Curb, type 6, as per plan (609E26001) | FT | 111 | $43.19 | $34.00 | $62.50 | $41.68 | $70.00 |
| 50 | Concrete median (609E72000) | SY | 41 | $329.38 | $125.00 | $200.00 | $137.84 | $200.00 |
| 51 | Special - special- consultant for concrete quality (690E98400) | LS | 1 | $15,351 | $20,570 | $22,750 | $18,555 | $25,000 |
| 53 | Manhole adjusted to grade (611E99654) | EACH | 3 | $593.49 | $980.00 | $1,050.00 | $2,217.15 | $1,000.00 |
| 54 | Pull box, misc.: adjusted to grade (625E31600) | EACH | 1 | $1,060.00 | $925.00 | $1,175.00 | $1,060.00 | $500.00 |
| 55 | Valve box adjusted to grade (638E10800) | EACH | 1 | $91.48 | $320.00 | $180.00 | $1,234.08 | $200.00 |
| 56 | Meter and vault removed and reset (638E11102) | EACH | 2 | $2,664.46 | $850.00 | $2,135.00 | $885.83 | $700.00 |
| 57 | Ground rod (625E32000) | EACH | 2 | $260.00 | $260.00 | $290.00 | $260.00 | $300.00 |
| 58 | Ground mounted support, no. 3 post (630E03100) | FT | 92.50 | $19.00 | $19.00 | $21.00 | $19.00 | $17.00 |
| 59 | Sign, flat sheet (630E80100) | SF | 9 | $28.01 | $28.00 | $31.00 | $28.00 | $18.00 |
| 60 | Removal of ground mounted sign and reerection (630E85100) | EACH | 7 | $150.00 | $150.00 | $165.00 | $150.00 | $50.00 |
| 61 | Removal of ground mounted post support and disposal (630E86002) | EACH | 7 | $35.00 | $35.00 | $40.00 | $35.00 | $30.00 |
| 62 | Signing, misc.:solar-powered rectangular rapid fla (630E97700) | EACH | 2 | $7,725.00 | $7,725.00 | $8,500.00 | $7,725.00 | $8,500.00 |
| 63 | Pedestal foundation (632E64020) | EACH | 2 | $1,340.00 | $1,340.00 | $1,475.00 | $1,340.00 | $1,500.00 |
| 64 | Signalization, misc.:removal of pedestrian signal (632E90400) | EACH | 2 | $280.00 | $280.00 | $310.00 | $280.00 | $800.00 |
| 65 | Edge line, 6", type 1 (642E00104) | MI | 0.04 | $770.00 | $770.00 | $1,105.00 | $770.00 | $2,800.00 |
| 66 | Center line, type 1 (642E00300) | MI | 1.41 | $900.00 | $900.00 | $2,205.00 | $900.00 | $1,650.00 |
| 67 | Channelizing line, 8", type 1 (642E00400) | FT | 224 | $0.75 | $0.75 | $1.35 | $0.75 | $2.00 |
| 68 | Stop line, type 1 (642E00500) | FT | 48 | $4.00 | $4.00 | $5.50 | $4.00 | $6.00 |
| 69 | Crosswalk line, 12", type 1 (642E00620) | FT | 87 | $4.00 | $4.00 | $3.25 | $4.00 | $6.00 |
| 70 | Lane arrow, type 1 (642E01300) | EACH | 5 | $90.00 | $90.00 | $101.00 | $90.00 | $90.00 |
| 71 | Two way left turn arrow, type 1 (642E01352) | EACH | 7 | $110.00 | $110.00 | $202.50 | $110.00 | $180.00 |
| 72 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $3,000.00 | $0.01 | $80,000 | $996.90 | $230,000 |
| 73 | Unclassified excavation (503E21300) | LS | 1 | $26,159 | $49,980 | $40,000 | $90,713 | $63,000 |
| 74 | Epoxy coated steel reinforcement (509E10000) | LB | 28,651 | $1.74 | $1.75 | $1.75 | $1.66 | $2.00 |
| 75 | Class QC1 concrete with QC/QA, retaining/wingwall not including footing (511E46012) | CY | 111 | $1,991.27 | $1,695.00 | $1,425.00 | $2,164.26 | $1,500.00 |
| 76 | Class QC1 concrete with QC/QA, footing (511E46512) | CY | 172 | $548.66 | $520.00 | $565.00 | $1,355.03 | $800.00 |
| 77 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 230 | $61.09 | $43.00 | $145.00 | $25.00 | $28.00 |
| 78 | Type 2 waterproofing (512E33000) | SY | 25 | $73.00 | $60.00 | $58.00 | $71.99 | $40.00 |
| 79 | 1" preformed expansion joint filler (516E13600) | SF | 23 | $5.65 | $10.00 | $10.00 | $25.22 | $15.00 |
| 80 | Railing, misc.: wall mounted decorative railing (517E76300) | FT | 260 | $357.50 | $357.50 | $395.00 | $357.50 | $400.00 |
| 81 | Porous backfill with geotextile fabric (518E21200) | CY | 429 | $144.56 | $80.00 | $125.00 | $138.90 | $135.00 |
| 82 | 6" perforated corrugated plastic pipe (518E40000) | FT | 266 | $3.61 | $12.00 | $5.50 | $19.26 | $15.00 |
| 83 | Special - form liner (530E13000) | SF | 1,798 | $20.79 | $25.00 | $6.00 | $9.38 | $10.00 |
| 84 | Prefabricated modular retaining wall (870E10000) | SF | 4,742 | $87.69 | $92.00 | $85.00 | $86.75 | $100.00 |
| 85 | 6" drainage pipe, perforated (870E12000) | FT | 415 | $3.02 | $10.00 | $5.00 | $17.19 | $15.00 |
| 86 | 6" drainage pipe, non-perforated (870E12100) | FT | 10 | $25.04 | $73.00 | $31.00 | $74.27 | $15.00 |
| 87 | On-site assistance (870E14000) | DAY | 2 | $0.01 | $500.00 | $875.00 | $687.30 | $500.00 |
| 88 | PMRW inspection and compaction testing (870E15000) | LS | 1 | $3,655.00 | $8,575.00 | $33,300 | $6,363.75 | $2,000.00 |
| 89 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,131 | $28,065 | $7,725.00 | $13,915 | $23,000 |
| 90 | Maintaining traffic (614E11000) | LS | 1 | $58,427 | $87,800 | $60,975 | $118,119 | $79,700 |
| 91 | Construction layout stakes and surveying (623E10000) | LS | 1 | $33,600 | $33,600 | $22,000 | $13,569 | $25,000 |
| 92 | Mobilization (624E10000) | LS | 1 | $71,597 | $90,560 | $40,000 | $112,500 | $100,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 12, 2026. Compiled by Mirage Metrics.