ODOT contract 240582 bid tabulation
HAM-US 52-36.85 (SLIDE REPAIR). Let by Ohio DOT on January 16, 2025, HAM. 9 bids received; low bid $1,928,724 by Alan Stone Co Inc, +7.4% against the engineer's estimate of $1,796,000.
- Owner
- Ohio DOT
- Letting
- 16 JAN 2025
- Pay items
- 58
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Alan Stone Co Inc | $1,928,724 | Low | +7.0% |
| 2 | KT Holden Construction LLC | $1,956,795 | +1.0% | +9.0% |
| 3 | George J Igel & Co Inc | $1,967,630 | +2.0% | +10% |
| 4 | Ford Development Corp | $2,177,017 | +13% | +21% |
| 5 | Great Lakes Construction Co | $2,188,673 | +13% | +22% |
| 6 | Kokosing Construction Company Inc | $2,222,619 | +15% | +24% |
| 7 | Prus Construction Company | $2,234,530 | +16% | +24% |
| 8 | John R Jurgensen Company | $2,261,532 | +17% | +26% |
| 9 | Sunesis Construction Co | $2,805,492 | +45% | +56% |
Engineer's estimate: $1,796,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Alan Stone Co Inc | 2. KT Holden Construction LLC | 3. George J Igel & Co Inc | 4. Ford Development Corp | 5. Great Lakes Construction Co | 6. Kokosing Construction Company Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $20,000 | $18,350 | $15,000 | $15,000 | $5,000.00 | $10,000 |
| 2 | Guardrail removed (202E38000) | FT | 775 | $5.50 | $2.00 | $7.00 | $3.00 | $7.00 | $7.00 |
| 3 | Excavation (203E10000) | CY | 121 | $95.00 | $47.55 | $55.75 | $20.00 | $75.00 | $95.00 |
| 4 | Embankment (203E20000) | CY | 87 | $7.00 | $46.25 | $41.50 | $20.00 | $55.00 | $70.00 |
| 5 | Subgrade compaction (204E10000) | SY | 708 | $7.00 | $2.80 | $7.00 | $1.00 | $1.75 | $6.00 |
| 6 | Proof rolling (204E45000) | HR | 1 | $270.00 | $167.00 | $190.00 | $100.00 | $325.00 | $300.00 |
| 7 | Guardrail, type MGS half post spacing (606E15150) | FT | 50 | $35.00 | $33.20 | $35.00 | $40.00 | $35.00 | $35.00 |
| 8 | Guardrail, type MGS quarter post spacing (606E15250) | FT | 725 | $60.00 | $41.40 | $48.00 | $58.00 | $48.00 | $48.00 |
| 9 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 25 | $140.00 | $120.00 | $140.00 | $100.00 | $185.00 | $225.00 |
| 10 | Seeding and mulching (659E10000) | SY | 1,080 | $5.50 | $3.75 | $3.75 | $1.00 | $3.75 | $3.75 |
| 11 | Commercial fertilizer (659E20000) | TON | 0.14 | $630.00 | $1,500.00 | $1,500.00 | $300.00 | $1,500.00 | $1,500.00 |
| 12 | Lime (659E31000) | ACRE | 0.21 | $900.00 | $200.00 | $200.00 | $100.00 | $200.00 | $200.00 |
| 13 | Water (659E35000) | MGAL | 6 | $1.00 | $1.00 | $1.00 | $10.00 | $1.00 | $1.00 |
| 14 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 15 | 6" shallow pipe underdrains (605E11100) | FT | 668 | $15.00 | $14.85 | $22.50 | $12.00 | $16.00 | $50.00 |
| 16 | 6" base pipe underdrains (605E14000) | FT | 668 | $15.00 | $10.95 | $18.50 | $10.00 | $23.00 | $28.00 |
| 17 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 62 | $3.00 | $29.00 | $80.00 | $25.00 | $50.00 | $30.00 |
| 18 | Precast reinforced concrete outlet (611E99710) | EACH | 2 | $620.00 | $297.00 | $425.00 | $300.00 | $425.00 | $600.00 |
| 19 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 7,316 | $4.00 | $5.00 | $4.00 | $3.30 | $3.00 | $3.00 |
| 20 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 150 | $390.00 | $375.00 | $375.00 | $385.00 | $350.00 | $350.00 |
| 21 | Aggregate base (304E20000) | CY | 139 | $105.00 | $86.90 | $150.00 | $80.00 | $115.00 | $125.00 |
| 22 | Non-tracking tack coat (407E20000) | GAL | 719 | $5.00 | $5.00 | $5.00 | $3.30 | $3.00 | $3.00 |
| 23 | Asphalt concrete surface course, type 1, (446), PG64-22 (441E10000) | CY | 354 | $340.00 | $340.00 | $340.00 | $380.00 | $345.00 | $345.00 |
| 24 | Combination curb and gutter, type 2 (609E12000) | FT | 250 | $70.00 | $78.70 | $55.00 | $70.00 | $63.00 | $60.00 |
| 25 | RPM (621E00100) | EACH | 45 | $110.00 | $45.00 | $97.75 | $110.00 | $97.75 | $97.75 |
| 26 | Raised pavement marker removed (621E54000) | EACH | 45 | $9.00 | $10.50 | $20.18 | $4.00 | $40.00 | $40.00 |
| 27 | Barrier reflector, type 2 (unidirectional) (626E00110) | EACH | 8 | $15.00 | $12.50 | $13.00 | $15.00 | $13.00 | $13.00 |
| 28 | Ground mounted support, no. 3 post (630E03100) | FT | 28.50 | $15.00 | $20.00 | $15.50 | $17.00 | $15.50 | $15.50 |
| 29 | Sign, flat sheet (630E80100) | SF | 12 | $20.00 | $30.00 | $18.00 | $20.00 | $18.00 | $18.00 |
| 30 | Removal of ground mounted sign and disposal (630E84900) | EACH | 1 | $20.00 | $15.00 | $20.00 | $22.00 | $20.00 | $20.00 |
| 31 | Removal of ground mounted post support and disposal (630E86002) | EACH | 1 | $30.00 | $30.00 | $25.00 | $28.00 | $25.00 | $25.00 |
| 32 | Edge line, 6" (644E00104) | MI | 0.70 | $19,000 | $6,725.00 | $16,734 | $19,000 | $16,734 | $16,734 |
| 33 | Lane line, 6" (644E00204) | MI | 0.67 | $9,400.00 | $3,160.00 | $8,376.00 | $10,000 | $8,376.00 | $8,376.00 |
| 34 | Transverse/diagonal line (644E00700) | FT | 1,290 | $5.50 | $5.25 | $5.00 | $6.00 | $5.00 | $5.00 |
| 35 | Bike lane symbol marking (644E01630) | EACH | 3 | $620.00 | $495.00 | $550.00 | $600.00 | $550.00 | $550.00 |
| 36 | Green colored pavement for bike lanes (644E60000) | SF | 1,456 | $15.00 | $10.70 | $12.29 | $14.00 | $12.29 | $12.29 |
| 37 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $110.00 | $120.00 | $125.00 | $60.00 | $100.00 | $125.00 |
| 38 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 6 | $2,800.00 | $2,042.95 | $3,000.00 | $2,100.00 | $2,740.00 | $4,500.00 |
| 39 | Barrier reflector, type 1 (bidirectional) (614E13310) | EACH | 15 | $30.00 | $13.39 | $35.00 | $15.00 | $13.39 | $33.00 |
| 40 | Object marker, one way (614E13350) | EACH | 15 | $15.00 | $20.89 | $35.00 | $23.00 | $20.89 | $48.00 |
| 41 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.67 | $19,000 | $9,262.25 | $16,812 | $10,000 | $16,812 | $16,812 |
| 42 | Work zone dotted line, class I, 6", 740.06, type I (614E24402) | FT | 1,221 | $3.00 | $2.37 | $2.50 | $3.00 | $2.50 | $2.50 |
| 43 | Portable barrier, unanchored (622E41100) | FT | 1,490 | $21.00 | $22.97 | $23.50 | $26.00 | $27.50 | $40.00 |
| 44 | Steel piles, misc.: soldier piles W24X162 (507E00400) | FT | 2,400 | $136.00 | $155.40 | $150.00 | $154.00 | $148.00 | $165.00 |
| 45 | Steel piles, misc.: soldier piles W27X129 (507E00400) | FT | 1,424 | $110.00 | $119.75 | $120.00 | $120.00 | $115.00 | $135.00 |
| 46 | Concrete, misc.: consultant for concrete quality C (511E81200) | LS | 1 | $60,000 | $28,600 | $62,500 | $25,000 | $23,000 | $32,000 |
| 47 | Concrete, misc.: precast concrete panel (511E81300) | EACH | 249 | $440.00 | $346.00 | $400.00 | $700.00 | $460.00 | $480.00 |
| 49 | Porous backfill with geotextile fabric (518E21200) | CY | 60 | $190.00 | $178.00 | $200.00 | $150.00 | $275.00 | $115.00 |
| 52 | Drilled shafts, 36" diameter, above bedrock, as per plan (524E94703) | FT | 2,253 | $140.00 | $90.00 | $132.50 | $172.00 | $195.00 | $160.00 |
| 53 | Drilled shafts, 36" diameter, into bedrock, as per plan (524E94705) | FT | 1,060 | $130.00 | $305.00 | $145.00 | $207.00 | $200.00 | $165.00 |
| 54 | Drilled shafts, misc.: extension (524E95000) | FT | 3 | $170.00 | $900.00 | $200.00 | $200.00 | $191.00 | $690.00 |
| 55 | Drilled shafts, misc.: plug pile, 36" diameter, UN (524E95000) | FT | 1,626 | $96.50 | $100.00 | $110.00 | $117.00 | $130.00 | $120.00 |
| 56 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $17,000 | $29,350 | $10,000 | $25,000 | $15,000 | $20,000 |
| 57 | Maintaining traffic (614E11000) | LS | 1 | $25,000 | $19,300 | $50,000 | $20,500 | $18,000 | $31,858 |
| 58 | Construction layout stakes and surveying (623E10000) | LS | 1 | $15,000 | $6,400.00 | $10,000 | $10,000 | $11,000 | $20,000 |
| 59 | Mobilization (624E10000) | LS | 1 | $77,000 | $71,115 | $50,000 | $100,000 | $108,350 | $111,000 |
| 100 | Pavement removed (202E23000) | SY | 504 | $24.00 | $39.00 | $25.00 | $10.00 | $40.00 | $35.00 |
| 101 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $10,000 | $6,580.00 | $8,000.00 | $5,000.00 | $11,500 | $5,119.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 16, 2025. Compiled by Mirage Metrics.