ODOT contract 268008 bid tabulation
HAM-CR 128/CR 161 Roundabout (INTERSECTION). Let by Ohio DOT on May 7, 2026, HAM. 4 bids received; low bid $2,342,902 by Sunesis Construction Co, +15% against the engineer's estimate of $2,036,000.
- Owner
- Ohio DOT
- Letting
- 07 MAY 2026
- Pay items
- 118
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Sunesis Construction Co | $2,342,902 | Low | +15% |
| 2 | John R Jurgensen Company | $2,400,809 | +2.0% | +18% |
| 3 | Prus Construction Company | $2,631,205 | +12% | +29% |
| 4 | Barrett Paving Materials Inc | $3,125,990 | +33% | +54% |
Engineer's estimate: $2,036,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sunesis Construction Co | 2. John R Jurgensen Company | 3. Prus Construction Company | 4. Barrett Paving Materials Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $13,000 | $26,043 | $5,500.00 | $50,000 |
| 2 | Headwall removed (202E20010) | EACH | 1 | $411.83 | $1,252.66 | $495.00 | $300.00 |
| 3 | Pavement removed (202E23000) | SY | 3,807 | $12.75 | $13.98 | $12.00 | $25.00 |
| 4 | Walk removed (202E30000) | SF | 160 | $1.94 | $13.39 | $8.00 | $5.00 |
| 5 | Curb removed (202E32000) | FT | 179 | $7.58 | $15.51 | $13.00 | $20.00 |
| 6 | Pipe removed, 24" and under (202E35100) | FT | 199 | $26.78 | $77.70 | $55.00 | $40.00 |
| 7 | Catch basin removed (202E58100) | EACH | 1 | $333.83 | $1,252.66 | $550.00 | $1,000.00 |
| 8 | Special - fill and plug existing conduit (202E70000) | FT | 101 | $23.13 | $59.79 | $20.00 | $30.00 |
| 9 | Removal misc.: remove EX. storm structure (202E98100) | EACH | 1 | $3,474.56 | $1,252.66 | $1,000.00 | $1,000.00 |
| 10 | Removal misc.: remove EX. wooden retaining wall (202E98200) | FT | 34 | $22.67 | $24.85 | $18.00 | $30.00 |
| 11 | Excavation (203E10000) | CY | 5,681 | $37.01 | $32.38 | $25.00 | $65.00 |
| 12 | Embankment (203E20000) | CY | 327 | $53.31 | $25.56 | $38.25 | $45.00 |
| 13 | Roadway, misc.:EX. tank, reconstructed (203E98600) | EACH | 1 | $8,020.83 | $24,769 | $11,500 | $2,500.00 |
| 14 | Subgrade compaction (204E10000) | SY | 5,118 | $4.66 | $1.97 | $2.50 | $5.00 |
| 15 | Excavation of subgrade (204E13000) | CY | 1,315 | $39.45 | $45.71 | $18.50 | $65.00 |
| 16 | Granular material, type B (204E30010) | CY | 1,315 | $97.70 | $102.93 | $75.00 | $125.00 |
| 17 | Proof rolling (204E45000) | HR | 2 | $309.41 | $262.45 | $146.00 | $2,000.00 |
| 18 | Geotextile fabric (204E50000) | SY | 3,942 | $2.21 | $2.82 | $2.00 | $4.00 |
| 19 | Fence removed and rebuilt (607E35000) | FT | 320 | $85.00 | $56.50 | $93.50 | $85.00 |
| 20 | 5" concrete walk (608E12000) | SF | 88 | $14.34 | $19.61 | $37.50 | $10.00 |
| 21 | Concrete steps, type A (608E40000) | FT | 24 | $708.52 | $769.11 | $610.00 | $665.00 |
| 22 | Monument assembly, type C (623E38500) | EACH | 6 | $989.04 | $2,065.93 | $1,500.00 | $1,700.00 |
| 23 | Right-of-way monument, type B (623E40520) | EACH | 13 | $347.97 | $703.19 | $370.00 | $500.00 |
| 24 | Special - mailbox support (690E50000) | EACH | 9 | $80.37 | $618.80 | $280.00 | $250.00 |
| 25 | Special - mailbox removed and reset (690E50350) | EACH | 9 | $95.76 | $436.84 | $280.00 | $250.00 |
| 26 | Topsoil (659E00300) | CY | 340 | $71.31 | $74.74 | $77.00 | $70.00 |
| 27 | Seeding and mulching (659E10000) | SY | 3,061 | $3.01 | $2.05 | $1.71 | $1.55 |
| 28 | Repair seeding and mulching (659E14000) | SY | 153 | $2.20 | $1.05 | $1.71 | $1.55 |
| 29 | Commercial fertilizer (659E20000) | TON | 0.40 | $1,400.00 | $850.00 | $1,072.50 | $975.00 |
| 30 | Lime (659E31000) | ACRE | 0.60 | $450.00 | $2.00 | $110.00 | $100.00 |
| 31 | Water (659E35000) | MGAL | 8 | $1.39 | $0.50 | $1.10 | $1.00 |
| 32 | Mowing (659E40000) | MSF | 7 | $10.00 | $15.00 | $62.70 | $57.00 |
| 33 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,850.00 | $2,250.00 | $3,410.00 | $2,500.00 |
| 34 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $6,900.00 | $4,400.00 | $4,268.00 | $5,000.00 |
| 35 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $9,422.38 | $9,422.38 | $10,365 | $10,000 |
| 36 | Erosion control (832E30000) | EACH | 30,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 37 | 6" base pipe underdrains (605E14000) | FT | 2,153 | $19.90 | $23.85 | $20.00 | $25.00 |
| 38 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 260 | $40.85 | $56.52 | $36.50 | $50.00 |
| 39 | 12" conduit, type B (611E04400) | FT | 506 | $152.93 | $144.94 | $141.00 | $280.00 |
| 40 | 12" conduit, type C (611E04600) | FT | 12 | $197.41 | $209.86 | $213.00 | $380.00 |
| 41 | 15" conduit, type B (611E05900) | FT | 155 | $238.53 | $250.75 | $288.00 | $480.00 |
| 42 | 24" conduit, type B (611E10400) | FT | 4 | $1,008.44 | $810.42 | $1,167.00 | $1,200.00 |
| 43 | Catch basin, no. 3 (611E98150) | EACH | 4 | $5,901.60 | $4,892.01 | $6,225.00 | $7,000.00 |
| 44 | Catch basin, no. 3A (611E98180) | EACH | 6 | $3,836.24 | $3,216.59 | $3,720.00 | $5,000.00 |
| 45 | Catch basin, no. 2-2B (611E98470) | EACH | 1 | $2,525.54 | $2,339.47 | $3,100.00 | $3,000.00 |
| 46 | Catch basin adjusted to grade (611E98630) | EACH | 2 | $533.69 | $1,323.60 | $1,000.00 | $1,000.00 |
| 47 | Catch basin, misc.: CB/MH combo per hceo (611E98690) | EACH | 1 | $7,979.66 | $9,639.61 | $8,275.00 | $12,000 |
| 48 | Manhole, no. 3 (611E99574) | EACH | 2 | $4,204.18 | $8,398.74 | $5,560.00 | $7,000.00 |
| 49 | Manhole, no. 3 with 90" base I.D. and 8" weir (611E99582) | EACH | 1 | $16,828 | $14,517 | $20,100 | $30,000 |
| 50 | Manhole adjusted to grade (611E99654) | EACH | 9 | $615.64 | $1,455.06 | $1,005.00 | $1,000.00 |
| 51 | Special - gas valve box adjusted to grade (611E99700) | EACH | 8 | $72.58 | $774.58 | $225.00 | $700.00 |
| 52 | Manufactured water quality structure, type 2 (895E10020) | EACH | 1 | $29,303 | $56,241 | $34,100 | $40,000 |
| 53 | Pavement planing, asphalt concrete (3") (254E01000) | SY | 3,215 | $4.76 | $6.00 | $6.60 | $7.00 |
| 54 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 552 | $276.00 | $300.00 | $330.00 | $300.00 |
| 55 | Asphalt concrete base, PG64-22, (449), (driveways) (301E56100) | CY | 57 | $400.00 | $735.00 | $808.50 | $400.00 |
| 56 | Aggregate base (304E20000) | CY | 439 | $130.38 | $129.12 | $110.00 | $100.00 |
| 57 | Non-tracking tack coat (407E20000) | GAL | 816 | $4.00 | $5.00 | $5.50 | $4.00 |
| 58 | Asphalt concrete intermediate course, type 1, (449) (441E70200) | CY | 243 | $300.00 | $455.00 | $500.50 | $300.00 |
| 59 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 24 | $700.00 | $905.00 | $995.50 | $700.00 |
| 60 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 30 | $450.00 | $523.00 | $575.30 | $450.00 |
| 61 | Asphalt concrete intermediate course, 12.5 MM, type A (446) (442E10080) | CY | 30 | $425.00 | $905.00 | $995.50 | $425.00 |
| 62 | Asphalt concrete surface course, 12.5 MM, type A (449) (442E22100) | CY | 243 | $325.00 | $523.00 | $575.30 | $325.00 |
| 63 | Reinforced concrete pavement, misc.: 9" truck apro (451E20000) | SY | 275 | $158.60 | $174.01 | $288.89 | $157.00 |
| 64 | 7" non-reinforced concrete pavement, class QC 1P with QC/QA (452E11020) | SY | 483 | $96.28 | $107.09 | $150.00 | $88.00 |
| 65 | Curb, type 6 (609E26000) | FT | 2,427 | $32.75 | $32.74 | $39.00 | $24.00 |
| 66 | Combination curb and gutter, type 9 (609E31000) | FT | 251 | $43.22 | $38.46 | $62.00 | $30.00 |
| 67 | 9" concrete traffic island (609E58000) | SY | 274 | $107.00 | $124.06 | $195.00 | $107.00 |
| 68 | Unclassified excavation, as per plan (503E21101) | CY | 5 | $149.15 | $300.00 | $1.00 | $75.00 |
| 69 | Unclassified excavation, as per plan (503E21101) | CY | 5 | $61.53 | $300.00 | $1.00 | $150.00 |
| 70 | Concrete, misc.: concrete, cincinnati spec 1110 (511E71100) | CY | 9 | $337.92 | $300.00 | $200.00 | $125.00 |
| 71 | Structural steel, misc.: reinforcing steel, cincin (513E90000) | LB | 635 | $2.52 | $10.00 | $1.00 | $1.00 |
| 72 | Special - structures, sheeting and bracing ordered (530E10700) | MFBM | 1 | $3.83 | $2,814.09 | $1.00 | $1.00 |
| 73 | Brick masonry (602E10000) | CY | 1 | $1,117.67 | $1,000.00 | $1.00 | $1.00 |
| 74 | Valve box adjusted to grade (638E10800) | EACH | 13 | $72.58 | $750.00 | $185.00 | $65.00 |
| 75 | Water work, misc.: disconnecting existing 3/4" ser (638E98000) | EACH | 1 | $274.33 | $1,000.00 | $835.00 | $788.00 |
| 76 | Water work, misc.: furnishing and installing curb (638E98000) | EACH | 1 | $1,051.77 | $1,200.00 | $435.00 | $237.00 |
| 77 | Water work, misc.: furnishing and installing curb (638E98000) | EACH | 9 | $1,262.63 | $1,000.00 | $350.00 | $237.00 |
| 78 | Water work, misc.: furnishing and installing fire (638E98000) | EACH | 1 | $2,006.64 | $1,200.00 | $725.00 | $1,421.00 |
| 79 | Water work, misc.: furnishing and installing fire (638E98000) | EACH | 1 | $1,996.94 | $1,500.00 | $800.00 | $1,581.00 |
| 80 | Water work, misc.: furnishing and installing fire (638E98000) | EACH | 2 | $3,989.13 | $7,500.00 | $6,675.00 | $888.00 |
| 81 | Water work, misc.: furnishing and installing valve (638E98000) | EACH | 5 | $4,421.45 | $750.00 | $615.00 | $230.00 |
| 82 | Water work, misc.: furnishing and installing valve (638E98000) | EACH | 4 | $2,331.29 | $1,000.00 | $1,485.00 | $1,334.00 |
| 83 | Water work, misc.: removing existing manhole curb (638E98000) | EACH | 3 | $1,226.11 | $1,200.00 | $450.00 | $350.00 |
| 84 | Water work, misc.: removing existing valve box, CI (638E98000) | EACH | 2 | $195.91 | $750.00 | $265.00 | $10.00 |
| 85 | Water work, misc.: removing fire hydrant, cincinna (638E98000) | EACH | 2 | $947.24 | $1,200.00 | $420.00 | $75.00 |
| 86 | Water work, misc.: resetting existing curb and roa (638E98000) | EACH | 2 | $576.22 | $1,000.00 | $435.00 | $10.00 |
| 87 | Water work, misc.: resetting existing valve boxes (638E98000) | EACH | 1 | $481.10 | $1,000.00 | $765.00 | $10.00 |
| 88 | Water work, misc.: water manhole adjusted to grade (638E98000) | EACH | 2 | $479.94 | $1,000.00 | $805.00 | $250.00 |
| 89 | Water work, misc.: furnishing and installing 3/4" (638E98600) | FT | 233 | $266.83 | $150.00 | $183.00 | $297.75 |
| 90 | Water work, misc.: furnishing and laying 12" ducti (638E98600) | FT | 492 | $452.79 | $225.00 | $365.00 | $431.25 |
| 91 | Water work, misc.: furnishing and laying 6" ductil (638E98600) | FT | 38 | $279.50 | $145.00 | $330.00 | $417.00 |
| 92 | Water work, misc.: furnishing and laying 8" ductil (638E98600) | FT | 138 | $333.65 | $190.00 | $277.00 | $350.50 |
| 93 | Conduit, 2", 725.051, as per plan (625E25409) | FT | 435 | $10.00 | $10.00 | $6.45 | $5.86 |
| 94 | Conduit, jacked or drilled, 725.052, as per plan (625E25909) | FT | 60 | $45.00 | $45.00 | $173.89 | $158.08 |
| 95 | Trench, 30" deep (625E29010) | FT | 435 | $15.00 | $15.00 | $16.34 | $14.85 |
| 96 | Pull box, misc.: duke pull box, installation only (625E31600) | EACH | 2 | $1,500.00 | $1,500.00 | $786.50 | $715.00 |
| 97 | Underground warning marking tape (625E36010) | FT | 435 | $1.00 | $1.00 | $2.42 | $2.20 |
| 98 | Conduit riser, 2" diameter (632E70400) | EACH | 2 | $1,000.00 | $1,000.00 | $1,270.41 | $1,154.92 |
| 99 | Special - special - duke energy lighting work AL (690E98000) | EACH | 50,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 100 | Pull box, misc.: EX. telecom pull box, atg (625E31600) | EACH | 1 | $1,000.00 | $1,000.00 | $544.50 | $495.00 |
| 101 | Ground mounted support, no. 3 post (630E03100) | FT | 343.50 | $15.50 | $15.50 | $16.50 | $15.00 |
| 102 | Sign post reflector (630E08600) | EACH | 8 | $55.00 | $55.00 | $83.60 | $76.00 |
| 103 | Sign, flat sheet (630E80100) | SF | 174.50 | $16.00 | $16.00 | $26.40 | $24.00 |
| 104 | Removal of ground mounted sign and disposal (630E84900) | EACH | 20 | $20.00 | $20.00 | $22.00 | $20.00 |
| 105 | Removal of ground mounted post support and disposal (630E86002) | EACH | 11 | $25.00 | $25.00 | $33.00 | $30.00 |
| 106 | Edge line, 4" (644E00100) | MI | 0.82 | $6,500.00 | $4,600.00 | $5,060.00 | $4,600.00 |
| 107 | Center line (644E00300) | MI | 0.34 | $12,730 | $5,300.00 | $5,830.00 | $5,300.00 |
| 108 | Transverse/diagonal line (644E00700) | FT | 140 | $8.00 | $7.00 | $7.70 | $7.00 |
| 109 | Dotted line, 8" (644E01514) | FT | 108 | $5.00 | $7.00 | $7.70 | $7.00 |
| 110 | Yield line (644E20800) | FT | 45 | $50.00 | $9.00 | $9.90 | $9.00 |
| 111 | Planting, misc.: EX. landscaping bed, remove and R (661E99900) | EACH | 1 | $6,683.49 | $22,780 | $23,701 | $25,000 |
| 112 | Detour signing (614E12420) | LS | 1 | $10,150 | $7,910.00 | $8,701.00 | $15,000 |
| 113 | 1/4" preformed expansion joint filler (516E13000) | SF | 311 | $4.07 | $9.75 | $1.16 | $10.00 |
| 114 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $12,888 | $24,103 | $9,800.00 | $15,566 |
| 115 | Maintaining traffic (614E11000) | LS | 1 | $32,169 | $16,201 | $230,000 | $287,000 |
| 116 | Construction layout stakes and surveying (623E10000) | LS | 1 | $65,750 | $13,661 | $25,000 | $85,000 |
| 117 | Mobilization (624E10000) | LS | 1 | $62,759 | $100,000 | $100,000 | $100,000 |
| 200 | Maintaining traffic, misc.:temporary lighting (614E18002) | LS | 1 | $29,175 | $25,000 | $34,762 | $50,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 7, 2026. Compiled by Mirage Metrics.