ODOT contract 260439 bid tabulation
WAR-SR 73-01.49 S Main St Resurf (TWO LANE RESURFACING). Let by Ohio DOT on October 1, 2026, WAR. 3 bids received; low bid $891,840 by Fillmore Construction, +9.0% against the engineer's estimate of $818,000.
- Owner
- Ohio DOT
- Letting
- 01 OCT 2026
- Pay items
- 66
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Fillmore Construction | $891,840 | Low | +9.0% |
| 2 | Barrett Paving Materials Inc | $929,890 | +4.0% | +14% |
| 3 | John R Jurgensen Company | $1,211,178 | +36% | +48% |
Engineer's estimate: $818,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fillmore Construction | 2. Barrett Paving Materials Inc | 3. John R Jurgensen Company |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,000 | $400.00 | $500.00 |
| 2 | Pavement removed (202E23000) | SY | 1,052 | $20.00 | $56.25 | $55.32 |
| 3 | Walk removed (202E30000) | SF | 8,429 | $10.00 | $2.40 | $5.16 |
| 4 | Curb removed (202E32000) | FT | 2,222 | $15.00 | $5.75 | $15.80 |
| 5 | Catch basin removed (202E58100) | EACH | 4 | $500.00 | $1,300.00 | $1,002.36 |
| 6 | Excavation (203E10000) | CY | 3 | $500.00 | $440.00 | $100.00 |
| 7 | Embankment (203E20000) | CY | 41 | $300.00 | $300.00 | $350.05 |
| 8 | Granular material, type B (203E35110) | CY | 240 | $100.00 | $180.00 | $169.28 |
| 9 | Subgrade compaction (204E10000) | SY | 432 | $5.00 | $13.00 | $4.71 |
| 10 | Subgrade compaction (204E10000) | SY | 988 | $10.00 | $13.00 | $4.39 |
| 11 | Excavation of subgrade (204E13000) | CY | 240 | $50.00 | $140.00 | $182.58 |
| 12 | 4" concrete walk (608E10000) | SF | 8,745 | $10.00 | $7.25 | $11.41 |
| 13 | Curb ramp (608E52000) | SF | 375 | $50.00 | $25.00 | $31.31 |
| 14 | Topsoil (659E00300) | CY | 160 | $50.00 | $78.00 | $60.87 |
| 15 | Seeding and mulching, class 1 (659E00500) | SY | 1,437 | $1.75 | $3.17 | $3.75 |
| 16 | Commercial fertilizer (659E20000) | TON | 0.20 | $1,400.00 | $950.00 | $1,500.00 |
| 17 | Lime (659E31000) | ACRE | 0.30 | $450.00 | $100.00 | $200.00 |
| 18 | Water (659E35000) | MGAL | 8 | $1.00 | $1.00 | $1.00 |
| 19 | Erosion control (832E30000) | EACH | 5,200 | $1.00 | $1.00 | $1.00 |
| 20 | 4" base pipe underdrains (605E06000) | FT | 2,140 | $15.00 | $16.50 | $37.92 |
| 21 | 4" conduit, type F (611E00406) | FT | 40 | $50.00 | $125.00 | $84.73 |
| 22 | 12" conduit, type B (611E04400) | FT | 20 | $340.00 | $390.00 | $736.51 |
| 23 | 12" conduit, type C (611E04600) | FT | 4 | $200.00 | $435.00 | $668.42 |
| 24 | Catch basin, no. 3 (611E98150) | EACH | 3 | $7,500.00 | $7,125.00 | $5,458.33 |
| 25 | Catch basin, no. 6 (611E98370) | EACH | 1 | $10,000 | $6,050.00 | $4,438.14 |
| 26 | Manhole adjusted to grade (611E99654) | EACH | 5 | $1,500.00 | $1,800.00 | $1,306.93 |
| 27 | Valve box adjusted to grade (638E10800) | EACH | 12 | $750.00 | $1,200.00 | $799.62 |
| 28 | Pavement repair, as per plan (253E02001) | CY | 32 | $420.00 | $1,450.00 | $1,675.69 |
| 29 | Pavement planing, asphalt concrete, 3" (254E01000) | SY | 3,813 | $3.50 | $6.90 | $6.48 |
| 30 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 83 | $268.00 | $465.00 | $533.79 |
| 31 | Aggregate base (304E20000) | CY | 125 | $200.00 | $227.50 | $192.91 |
| 32 | Non-tracking tack coat (407E20000) | GAL | 380 | $5.00 | $4.50 | $5.00 |
| 33 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 180 | $340.00 | $385.00 | $470.78 |
| 34 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 180 | $300.00 | $350.00 | $400.55 |
| 35 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 270 | $100.00 | $98.00 | $131.90 |
| 36 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 162 | $120.00 | $110.00 | $133.40 |
| 37 | Curb, type 4-C (609E24510) | FT | 2,222 | $28.00 | $21.00 | $31.47 |
| 38 | Ground mounted support, no. 3 post (630E03100) | FT | 75 | $15.50 | $15.50 | $15.50 |
| 39 | Sign post reflector (630E08600) | EACH | 1 | $55.00 | $55.00 | $55.00 |
| 40 | Sign, flat sheet (630E80100) | SF | 21 | $16.00 | $16.00 | $16.00 |
| 41 | Removal of ground mounted sign and disposal (630E84900) | EACH | 7 | $20.00 | $20.00 | $20.00 |
| 42 | Removal of ground mounted post support and disposal (630E86002) | EACH | 5 | $25.00 | $25.00 | $25.00 |
| 43 | Edge line, 6" (644E00104) | MI | 0.40 | $6,700.00 | $6,700.00 | $6,700.00 |
| 44 | Center line (644E00300) | MI | 0.21 | $8,932.00 | $8,932.00 | $8,932.00 |
| 45 | Stop line (644E00500) | FT | 40 | $10.00 | $10.00 | $10.00 |
| 46 | Crosswalk line, 12" (644E00620) | FT | 88 | $5.00 | $5.00 | $5.00 |
| 47 | Transverse/diagonal line (644E00700) | FT | 169 | $9.15 | $9.15 | $9.15 |
| 48 | Railroad symbol marking (644E01000) | EACH | 1 | $830.00 | $830.00 | $830.00 |
| 49 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 8 | $125.00 | $100.00 | $144.60 |
| 50 | Work zone center line, class I (614E21000) | MI | 0.21 | $4,630.00 | $4,630.00 | $4,630.00 |
| 51 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.21 | $4,630.00 | $4,630.00 | $4,630.00 |
| 52 | Work zone edge line, class I, 6" (614E22010) | MI | 0.40 | $3,080.00 | $3,080.00 | $3,080.00 |
| 53 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 0.40 | $3,080.00 | $3,080.00 | $3,080.00 |
| 54 | Work zone transverse/diagonal line, class I (614E25000) | FT | 169 | $1.85 | $1.85 | $1.85 |
| 55 | Work zone transverse/diagonal line, class III, 642 paint (614E25620) | FT | 169 | $1.85 | $1.85 | $1.85 |
| 56 | Work zone stop line, class I (614E26000) | FT | 40 | $4.80 | $4.80 | $4.80 |
| 57 | Work zone stop line, class III, 642 paint (614E26610) | FT | 40 | $4.80 | $4.80 | $4.80 |
| 58 | Work zone crosswalk line, class I, 12" (614E27010) | FT | 88 | $3.00 | $3.00 | $3.00 |
| 59 | Work zone crosswalk line, class III, 12", 642 paint (614E27250) | FT | 88 | $3.00 | $3.00 | $3.00 |
| 60 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $10,000 | $14,000 | $5,000.00 |
| 61 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $2,500.00 | $6,043.94 |
| 62 | Maintaining traffic (614E11000) | LS | 1 | $82,000 | $83,200 | $166,522 |
| 63 | Construction layout stakes and surveying (623E10000) | LS | 1 | $15,000 | $7,500.00 | $5,800.40 |
| 64 | Mobilization (624E10000) | LS | 1 | $25,000 | $30,000 | $50,000 |
| 65 | Special - railroad flagging services (900E11000) | EACH | 7,500 | $1.00 | $1.00 | $1.00 |
| 100 | Pipe removed (202E34900) | FT | 24 | $20.00 | $66.00 | $129.16 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 1, 2026. Compiled by Mirage Metrics.