ODOT contract 260439 bid tabulation

WAR-SR 73-01.49 S Main St Resurf (TWO LANE RESURFACING). Let by Ohio DOT on October 1, 2026, WAR. 3 bids received; low bid $891,840 by Fillmore Construction, +9.0% against the engineer's estimate of $818,000.

Owner
Ohio DOT
Letting
01 OCT 2026
Pay items
66
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Fillmore Construction$891,840Low+9.0%
2Barrett Paving Materials Inc$929,890+4.0%+14%
3John R Jurgensen Company$1,211,178+36%+48%
ODOT contract 260439: bids by rank

Engineer's estimate: $818,000.

Bid tabulation

LinePay itemUnitQuantity1. Fillmore Construction2. Barrett Paving Materials Inc3. John R Jurgensen Company
1Clearing and grubbing (201E11000)LS1$10,000$400.00$500.00
2Pavement removed (202E23000)SY1,052$20.00$56.25$55.32
3Walk removed (202E30000)SF8,429$10.00$2.40$5.16
4Curb removed (202E32000)FT2,222$15.00$5.75$15.80
5Catch basin removed (202E58100)EACH4$500.00$1,300.00$1,002.36
6Excavation (203E10000)CY3$500.00$440.00$100.00
7Embankment (203E20000)CY41$300.00$300.00$350.05
8Granular material, type B (203E35110)CY240$100.00$180.00$169.28
9Subgrade compaction (204E10000)SY432$5.00$13.00$4.71
10Subgrade compaction (204E10000)SY988$10.00$13.00$4.39
11Excavation of subgrade (204E13000)CY240$50.00$140.00$182.58
124" concrete walk (608E10000)SF8,745$10.00$7.25$11.41
13Curb ramp (608E52000)SF375$50.00$25.00$31.31
14Topsoil (659E00300)CY160$50.00$78.00$60.87
15Seeding and mulching, class 1 (659E00500)SY1,437$1.75$3.17$3.75
16Commercial fertilizer (659E20000)TON0.20$1,400.00$950.00$1,500.00
17Lime (659E31000)ACRE0.30$450.00$100.00$200.00
18Water (659E35000)MGAL8$1.00$1.00$1.00
19Erosion control (832E30000)EACH5,200$1.00$1.00$1.00
204" base pipe underdrains (605E06000)FT2,140$15.00$16.50$37.92
214" conduit, type F (611E00406)FT40$50.00$125.00$84.73
2212" conduit, type B (611E04400)FT20$340.00$390.00$736.51
2312" conduit, type C (611E04600)FT4$200.00$435.00$668.42
24Catch basin, no. 3 (611E98150)EACH3$7,500.00$7,125.00$5,458.33
25Catch basin, no. 6 (611E98370)EACH1$10,000$6,050.00$4,438.14
26Manhole adjusted to grade (611E99654)EACH5$1,500.00$1,800.00$1,306.93
27Valve box adjusted to grade (638E10800)EACH12$750.00$1,200.00$799.62
28Pavement repair, as per plan (253E02001)CY32$420.00$1,450.00$1,675.69
29Pavement planing, asphalt concrete, 3" (254E01000)SY3,813$3.50$6.90$6.48
30Asphalt concrete base, PG64-22, (449) (301E56000)CY83$268.00$465.00$533.79
31Aggregate base (304E20000)CY125$200.00$227.50$192.91
32Non-tracking tack coat (407E20000)GAL380$5.00$4.50$5.00
33Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY180$340.00$385.00$470.78
34Asphalt concrete intermediate course, type 2, (449) (441E70300)CY180$300.00$350.00$400.55
356" non-reinforced concrete pavement, class QC 1P (452E10010)SY270$100.00$98.00$131.90
368" non-reinforced concrete pavement, class QC 1P (452E12010)SY162$120.00$110.00$133.40
37Curb, type 4-C (609E24510)FT2,222$28.00$21.00$31.47
38Ground mounted support, no. 3 post (630E03100)FT75$15.50$15.50$15.50
39Sign post reflector (630E08600)EACH1$55.00$55.00$55.00
40Sign, flat sheet (630E80100)SF21$16.00$16.00$16.00
41Removal of ground mounted sign and disposal (630E84900)EACH7$20.00$20.00$20.00
42Removal of ground mounted post support and disposal (630E86002)EACH5$25.00$25.00$25.00
43Edge line, 6" (644E00104)MI0.40$6,700.00$6,700.00$6,700.00
44Center line (644E00300)MI0.21$8,932.00$8,932.00$8,932.00
45Stop line (644E00500)FT40$10.00$10.00$10.00
46Crosswalk line, 12" (644E00620)FT88$5.00$5.00$5.00
47Transverse/diagonal line (644E00700)FT169$9.15$9.15$9.15
48Railroad symbol marking (644E01000)EACH1$830.00$830.00$830.00
49Law enforcement officer with patrol car for assistance (614E11110)HR8$125.00$100.00$144.60
50Work zone center line, class I (614E21000)MI0.21$4,630.00$4,630.00$4,630.00
51Work zone center line, class III, 642 paint (614E21550)MI0.21$4,630.00$4,630.00$4,630.00
52Work zone edge line, class I, 6" (614E22010)MI0.40$3,080.00$3,080.00$3,080.00
53Work zone edge line, class III, 6", 642 paint (614E22360)MI0.40$3,080.00$3,080.00$3,080.00
54Work zone transverse/diagonal line, class I (614E25000)FT169$1.85$1.85$1.85
55Work zone transverse/diagonal line, class III, 642 paint (614E25620)FT169$1.85$1.85$1.85
56Work zone stop line, class I (614E26000)FT40$4.80$4.80$4.80
57Work zone stop line, class III, 642 paint (614E26610)FT40$4.80$4.80$4.80
58Work zone crosswalk line, class I, 12" (614E27010)FT88$3.00$3.00$3.00
59Work zone crosswalk line, class III, 12", 642 paint (614E27250)FT88$3.00$3.00$3.00
60Premium on railroads' protective public liability and property damage liability insurance (100E00300)LS1$10,000$14,000$5,000.00
61Premium for contract performance bond and for payment bond (103E05000)LS1$10,000$2,500.00$6,043.94
62Maintaining traffic (614E11000)LS1$82,000$83,200$166,522
63Construction layout stakes and surveying (623E10000)LS1$15,000$7,500.00$5,800.40
64Mobilization (624E10000)LS1$25,000$30,000$50,000
65Special - railroad flagging services (900E11000)EACH7,500$1.00$1.00$1.00
100Pipe removed (202E34900)FT24$20.00$66.00$129.16
ODOT contract 260439: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of October 1, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy