ODOT contract 260018 bid tabulation
HIG-SR 73-21.04 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on January 15, 2026, HIG. 4 bids received; low bid $2,244,819 by D G M Inc, -5.7% against the engineer's estimate of $2,380,000.
- Owner
- Ohio DOT
- Letting
- 15 JAN 2026
- Pay items
- 97
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | D G M Inc | $2,244,819 | Low | -6.0% |
| 2 | Double Z Construction Company | $2,249,311 | 0.0% | -5.0% |
| 3 | George J Igel & Co Inc | $2,265,279 | +1.0% | -5.0% |
| 4 | Complete General Construction Company | $2,461,288 | +10% | +3.0% |
Engineer's estimate: $2,380,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D G M Inc | 2. Double Z Construction Company | 3. George J Igel & Co Inc | 4. Complete General Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $30,000 | $15,000 | $8,000.00 | $5,000.00 |
| 2 | Pavement removed (202E23000) | SY | 1,512 | $12.00 | $28.00 | $12.15 | $25.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 25 | $25.00 | $16.00 | $6.50 | $45.00 |
| 4 | Guardrail removed (202E38000) | FT | 866 | $1.00 | $5.50 | $5.50 | $2.00 |
| 5 | Removal misc.: concrete gutter (202E98400) | SF | 280 | $4.00 | $7.00 | $3.00 | $30.00 |
| 6 | Excavation (203E10000) | CY | 345 | $25.00 | $30.00 | $30.00 | $25.00 |
| 7 | Excavation, as per plan (203E10001) | CY | 25 | $60.00 | $120.00 | $145.00 | $90.00 |
| 8 | Embankment (203E20000) | CY | 1,096 | $30.00 | $30.00 | $40.00 | $25.00 |
| 9 | Subgrade compaction (204E10000) | SY | 2,029 | $4.00 | $4.75 | $5.00 | $5.00 |
| 10 | Proof rolling (204E45000) | HR | 2 | $75.00 | $200.00 | $131.50 | $350.00 |
| 11 | Guardrail, type MGS (606E15050) | FT | 675 | $23.00 | $21.00 | $37.00 | $19.80 |
| 12 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 3 | $2,550.00 | $2,500.00 | $3,450.00 | $2,420.00 |
| 13 | Anchor assembly, type T (606E26500) | EACH | 1 | $1,250.00 | $1,200.00 | $2,150.00 | $1,360.00 |
| 14 | MGS bridge terminal assembly, type TST-2 (606E34600) | EACH | 4 | $2,550.00 | $2,500.00 | $3,125.00 | $2,480.00 |
| 15 | Rock channel protection, type B with geotextile fabric (601E32104) | CY | 213 | $95.00 | $65.00 | $110.00 | $95.00 |
| 16 | Topsoil (659E00300) | CY | 451 | $20.00 | $35.00 | $9.50 | $25.00 |
| 17 | Seeding and mulching (659E10000) | SY | 3,356 | $2.25 | $4.50 | $3.50 | $1.10 |
| 18 | Repair seeding and mulching (659E14000) | SY | 168 | $0.05 | $1.10 | $1.10 | $1.10 |
| 19 | Commercial fertilizer (659E20000) | TON | 0.45 | $1,500.00 | $1,250.00 | $1,250.00 | $1,250.00 |
| 20 | Lime (659E31000) | ACRE | 0.69 | $300.00 | $150.00 | $150.00 | $150.00 |
| 21 | Water (659E35000) | MGAL | 18 | $1.00 | $1.00 | $1.00 | $1.00 |
| 22 | Slope erosion protection (670E00500) | SY | 702 | $2.50 | $2.00 | $2.00 | $2.00 |
| 23 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,000.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 24 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $10,000 | $8,600.00 | $9,550.00 | $8,600.00 |
| 25 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $11,000 | $10,500 | $9,000.00 | $10,500 |
| 26 | Erosion control (832E30000) | EACH | 19,138 | $1.00 | $1.00 | $1.00 | $1.00 |
| 27 | Seeding and erosion control with turf reinforcing mat, type 1 (836E10000) | SY | 69 | $4.00 | $12.00 | $6.00 | $6.00 |
| 28 | Aggregate drains (605E31100) | FT | 180 | $25.00 | $20.00 | $42.00 | $23.30 |
| 29 | 6" conduit, type E (611E01400) | FT | 30 | $8.00 | $11.00 | $34.00 | $6.00 |
| 30 | 6" conduit, type F (611E01500) | FT | 30 | $8.00 | $12.00 | $34.00 | $6.00 |
| 31 | 12" conduit, type D (611E04900) | FT | 25 | $90.00 | $70.00 | $100.00 | $95.00 |
| 32 | Pavement planing, asphalt concrete (1.5") (254E01000) | SY | 374 | $8.25 | $32.35 | $18.00 | $8.25 |
| 33 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 330 | $250.00 | $235.96 | $245.00 | $240.00 |
| 34 | Aggregate base (304E20000) | CY | 338 | $90.00 | $90.00 | $68.00 | $75.00 |
| 35 | Tack coat (407E10000) | GAL | 328 | $4.50 | $4.18 | $10.00 | $4.50 |
| 36 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 151 | $410.00 | $309.17 | $335.00 | $390.00 |
| 37 | Asphalt concrete intermediate course, type 1, (449) (441E70200) | CY | 17 | $340.00 | $462.63 | $485.00 | $325.00 |
| 38 | RPM (621E00100) | EACH | 8 | $378.00 | $475.00 | $378.00 | $355.00 |
| 39 | Raised pavement marker removed (621E54000) | EACH | 8 | $1.00 | $19.00 | $50.00 | $75.00 |
| 40 | Barrier reflector, type 1 (BI-directional) (626E00102) | EACH | 2 | $15.00 | $10.00 | $13.00 | $13.00 |
| 41 | Barrier reflector, type 3 (BI-directional) (626E00112) | EACH | 10 | $15.00 | $12.00 | $13.00 | $15.00 |
| 42 | Ground mounted support, no. 3 post (630E03100) | FT | 12 | $20.00 | $20.00 | $18.00 | $25.00 |
| 43 | Sign post reflector (630E08600) | EACH | 1 | $75.00 | $50.00 | $75.00 | $55.00 |
| 44 | Sign, flat sheet (630E80100) | SF | 9 | $25.00 | $25.00 | $20.00 | $35.00 |
| 45 | Removal of ground mounted sign and disposal (630E84900) | EACH | 1 | $25.00 | $25.00 | $45.00 | $10.00 |
| 46 | Removal of ground mounted post support and disposal (630E86002) | EACH | 1 | $25.00 | $25.00 | $55.00 | $15.00 |
| 47 | Edge line, 6", type 1 (642E00104) | MI | 0.28 | $6,000.00 | $3,555.00 | $5,266.00 | $3,555.00 |
| 48 | Center line, type 1 (642E00300) | MI | 0.14 | $12,000 | $6,675.00 | $10,532 | $6,675.00 |
| 49 | Traffic compacted surface, type A or B (410E12000) | CY | 25 | $70.00 | $75.00 | $57.00 | $95.00 |
| 50 | Traffic compacted surface, type C (410E13000) | CY | 25 | $70.00 | $80.00 | $60.00 | $95.00 |
| 51 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 6 | $2,000.00 | $2,000.00 | $2,740.00 | $1,850.00 |
| 52 | Barrier reflector, type 1 (BI-directional) (614E13310) | EACH | 44 | $25.00 | $22.00 | $15.00 | $12.00 |
| 53 | Barrier reflector, type 3 (BI-directional) (614E13314) | EACH | 18 | $25.00 | $30.00 | $20.00 | $12.00 |
| 54 | Object marker, two way (614E13360) | EACH | 62 | $25.00 | $18.00 | $22.00 | $20.00 |
| 55 | Work zone edge line, class I, 6" (614E22010) | MI | 0.92 | $7,000.00 | $2,950.00 | $6,539.00 | $4,015.00 |
| 56 | Work zone stop line, class I (614E26000) | FT | 48 | $5.00 | $14.00 | $5.00 | $5.00 |
| 57 | Roads for maintaining traffic, as per plan (615E10001) | LS | 1 | $3,000.00 | $20,000 | $21,000 | $27,000 |
| 58 | Pavement for maintaining traffic, class B (615E25000) | SY | 238 | $105.00 | $146.00 | $100.00 | $125.00 |
| 59 | Water (616E10000) | MGAL | 7 | $1.00 | $50.00 | $70.00 | $100.00 |
| 60 | Portable barrier, unanchored (622E41100) | FT | 1,080 | $20.00 | $32.00 | $45.00 | $29.00 |
| 61 | Portable barrier, anchored (622E41110) | FT | 730 | $30.00 | $38.00 | $55.00 | $35.00 |
| 62 | Structure removed, over 20 foot span, as per plan (202E11003) | LS | 1 | $125,000 | $96,000 | $95,500 | $150,000 |
| 63 | Approach slab removed (202E22900) | SY | 80 | $35.00 | $55.00 | $50.00 | $75.00 |
| 64 | Wearing course removed (202E23500) | SY | 571 | $8.00 | $12.75 | $15.00 | $20.00 |
| 65 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $130,000 | $85,000 | $35,000 | $170,000 |
| 66 | Unclassified excavation (503E21100) | CY | 130 | $20.00 | $85.00 | $70.00 | $90.00 |
| 67 | Shale excavation, as per plan (503E31121) | CY | 139 | $50.00 | $105.00 | $140.00 | $80.00 |
| 68 | Epoxy coated steel reinforcement (509E10000) | LB | 50,856 | $1.35 | $1.80 | $2.10 | $1.75 |
| 69 | Class QC2 concrete with QC/QA, superstructure, as per plan (511E33419) | CY | 62 | $1,010.00 | $965.00 | $1,035.00 | $800.00 |
| 70 | Semi-integral diaphragm guide (511E33500) | EACH | 2 | $3,500.00 | $4,600.00 | $6,000.00 | $6,000.00 |
| 71 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 112 | $1,840.00 | $1,835.00 | $1,615.00 | $1,700.00 |
| 72 | Class QC1 concrete with QC/QA, abutment not including footing (511E44112) | CY | 87 | $720.00 | $1,050.00 | $1,030.00 | $1,500.00 |
| 73 | Class QC1 concrete with QC/QA, footing (511E46512) | CY | 67 | $710.00 | $675.00 | $785.00 | $950.00 |
| 74 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 386 | $35.00 | $26.50 | $37.50 | $26.50 |
| 75 | Type 2 waterproofing (512E33000) | SY | 27 | $30.00 | $52.00 | $65.00 | $30.00 |
| 76 | Draped strand prestressed concrete bridge I-beam members, level 3, type 4 (515E15020) | EACH | 5 | $86,000 | $66,500 | $72,900 | $68,000 |
| 77 | Intermediate diaphragms (515E20000) | EACH | 12 | $2,250.00 | $1,800.00 | $2,350.00 | $3,500.00 |
| 78 | 2" preformed expansion joint filler (516E13900) | SF | 40 | $25.00 | $22.00 | $15.00 | $12.00 |
| 79 | Semi-integral abutment expansion joint seal (516E14020) | FT | 107 | $50.00 | $36.00 | $42.00 | $48.00 |
| 80 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 10 | $3,000.00 | $2,430.00 | $1,900.00 | $1,660.00 |
| 81 | Railing (three steel tube bridge railing) (517E70100) | FT | 236 | $445.00 | $440.00 | $450.00 | $475.00 |
| 82 | Porous backfill with geotextile fabric (518E21200) | CY | 75 | $120.00 | $123.00 | $125.00 | $150.00 |
| 83 | Special - steel drip strip (518E22300) | FT | 294 | $20.00 | $19.00 | $15.00 | $15.50 |
| 84 | 6" perforated corrugated plastic pipe (518E40000) | FT | 128 | $30.00 | $15.00 | $11.00 | $15.00 |
| 85 | 6" non-perforated corrugated plastic pipe, including specials, as per plan (518E40011) | FT | 26 | $30.00 | $100.00 | $35.00 | $50.00 |
| 86 | Drilled shafts, 30" diameter, into bedrock (524E94604) | FT | 140 | $485.00 | $480.00 | $365.00 | $695.00 |
| 87 | Drilled shafts, 36" diameter, above bedrock (524E94702) | FT | 10 | $485.00 | $1,400.00 | $150.00 | $300.00 |
| 88 | Reinforced concrete approach slabs with QC/QA (T=1 (526E25010) | SY | 178 | $380.00 | $440.00 | $483.00 | $375.00 |
| 89 | Type A installation (526E90010) | FT | 64 | $280.00 | $225.00 | $295.00 | $350.00 |
| 90 | Low strength mortar backfill, as per plan (613E41201) | CY | 189 | $140.00 | $125.00 | $140.00 | $175.00 |
| 91 | Structure grounding system (625E33000) | EACH | 1 | $21,000 | $13,000 | $12,840 | $10,000 |
| 92 | Thermal integrity profiling (tip) test (894E10000) | EACH | 2 | $4,000.00 | $3,350.00 | $4,400.00 | $10,000 |
| 93 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $31,000 | $12,250 | $22,000 | $15,000 |
| 94 | Maintaining traffic (614E11000) | LS | 1 | $69,000 | $90,000 | $80,000 | $50,000 |
| 95 | Field office, type A (619E16000) | MNTH | 6 | $750.00 | $1,500.00 | $1,605.00 | $1,500.00 |
| 96 | Construction layout stakes and surveying (623E10000) | LS | 1 | $12,000 | $12,000 | $16,000 | $32,000 |
| 97 | Mobilization (624E10000) | LS | 1 | $40,000 | $100,000 | $113,000 | $125,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 15, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way