ODOT contract 260005 bid tabulation
JAC-SR 327/SR 32-13.58/17.51 (CULVERT REPLACEMENT). Let by Ohio DOT on January 15, 2026, JAC. 5 bids received; low bid $536,376 by D G M Inc, +13% against the engineer's estimate of $475,000.
- Owner
- Ohio DOT
- Letting
- 15 JAN 2026
- Pay items
- 61
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | D G M Inc | $536,376 | Low | +13% |
| 2 | R C Construction Company and Son Inc | $588,633 | +10% | +24% |
| 3 | Fillmore Construction | $589,770 | +10% | +24% |
| 4 | Axis Civil Construction LLC | $595,818 | +11% | +25% |
| 5 | Complete General Construction Company | $660,155 | +23% | +39% |
Engineer's estimate: $475,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D G M Inc | 2. R C Construction Company and Son Inc | 3. Fillmore Construction | 4. Axis Civil Construction LLC | 5. Complete General Construction Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $18,000 | $10,000 | $6,000.00 | $18,500 | $25,000 |
| 2 | Pavement removed (202E23000) | SY | 233 | $17.00 | $35.00 | $10.00 | $11.00 | $30.00 |
| 3 | Excavation (203E10000) | CY | 182 | $30.00 | $25.00 | $35.00 | $35.00 | $32.00 |
| 4 | Embankment (203E20000) | CY | 320 | $30.00 | $45.00 | $60.00 | $35.00 | $40.00 |
| 5 | Subgrade compaction (204E10000) | SY | 376 | $10.00 | $2.00 | $5.00 | $3.00 | $4.00 |
| 6 | Seeding and mulching (659E10000) | SY | 1,608 | $3.00 | $10.00 | $3.00 | $2.00 | $3.75 |
| 7 | Repair seeding and mulching (659E14000) | SY | 81 | $0.05 | $0.20 | $3.00 | $2.00 | $1.00 |
| 8 | Commercial fertilizer (659E20000) | TON | 0.22 | $1,500.00 | $2,900.00 | $2,500.00 | $1,250.00 | $1,500.00 |
| 9 | Lime (659E31000) | ACRE | 0.33 | $300.00 | $2,200.00 | $1,000.00 | $150.00 | $200.00 |
| 10 | Water (659E35000) | MGAL | 8.70 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 11 | Erosion control (832E30000) | EACH | 2,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 12 | Full depth pavement sawing (252E01500) | FT | 45 | $20.00 | $65.00 | $20.00 | $6.00 | $4.00 |
| 13 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 41 | $420.00 | $475.00 | $300.00 | $345.00 | $500.00 |
| 14 | Aggregate base (304E20000) | CY | 43 | $135.00 | $150.00 | $100.00 | $160.00 | $150.00 |
| 15 | Tack coat (407E10000) | GAL | 53 | $4.00 | $10.00 | $10.00 | $6.00 | $10.00 |
| 16 | Stabilized crushed aggregate (411E10000) | CY | 28 | $150.00 | $150.00 | $120.00 | $250.00 | $180.00 |
| 17 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 31 | $520.00 | $575.00 | $450.00 | $440.00 | $500.00 |
| 18 | Removal of delineator (620E31200) | EACH | 1 | $20.00 | $500.00 | $100.00 | $100.00 | $25.00 |
| 19 | RPM (621E00100) | EACH | 3 | $900.00 | $950.00 | $900.00 | $900.00 | $900.00 |
| 20 | Raised pavement marker removed (621E54000) | EACH | 3 | $1.00 | $50.00 | $10.00 | $60.00 | $50.00 |
| 21 | Edge line, 6", type 1 (642E00104) | MI | 0.08 | $8,000.00 | $15,000 | $7,000.00 | $7,000.00 | $7,000.00 |
| 22 | Center line, type 1 (642E00300) | MI | 0.04 | $16,000 | $25,000 | $14,000 | $14,000 | $14,000 |
| 23 | Pavement repair (253E02000) | CY | 30 | $320.00 | $10.00 | $300.00 | $165.00 | $500.00 |
| 24 | Tack coat (407E10000) | GAL | 30 | $3.50 | $1.00 | $10.00 | $5.00 | $10.00 |
| 25 | Stabilized crushed aggregate (411E10000) | CY | 30 | $85.00 | $10.00 | $120.00 | $100.00 | $180.00 |
| 26 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 30 | $210.00 | $50.00 | $450.00 | $195.00 | $300.00 |
| 27 | Detour signing (614E12420) | LS | 1 | $4,200.00 | $35,000 | $3,950.00 | $3,950.00 | $5,000.00 |
| 28 | Asphalt concrete for maintaining traffic (614E13000) | CY | 30 | $180.00 | $50.00 | $300.00 | $195.00 | $400.00 |
| 29 | Water (616E10000) | MGAL | 2 | $1.00 | $1.00 | $1.00 | $1.00 | $150.00 |
| 30 | Removal misc.: portions of structure removed MSE W (202E98000) | LS | 1 | $60,500 | $25,000 | $20,000 | $60,000 | $35,000 |
| 31 | Epoxy coated steel reinforcement (509E10000) | LB | 192 | $10.00 | $20.00 | $10.00 | $20.00 | $15.00 |
| 32 | Class QC1 concrete, misc.: MSE wall repair (511E53010) | CY | 4 | $3,000.00 | $6,500.00 | $5,000.00 | $3,500.00 | $18,000 |
| 33 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 22 | $75.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 34 | Joint sealer, as per plan (516E31001) | FT | 152 | $20.00 | $100.00 | $30.00 | $15.00 | $22.00 |
| 35 | Removal misc.: portions of structure removed MSE W (202E98000) | LS | 1 | $32,000 | $25,000 | $20,000 | $60,000 | $10,000 |
| 36 | Epoxy coated steel reinforcement (509E10000) | LB | 72 | $10.00 | $20.00 | $10.00 | $20.00 | $20.00 |
| 37 | Class QC1 concrete, misc.: MSE wall repair (511E53010) | CY | 2 | $3,000.00 | $6,500.00 | $5,000.00 | $3,500.00 | $18,000 |
| 38 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 7 | $75.00 | $100.00 | $150.00 | $150.00 | $150.00 |
| 39 | Joint sealer, as per plan (516E31001) | FT | 50 | $20.00 | $100.00 | $32.50 | $15.00 | $22.00 |
| 40 | Headwall removed (202E20010) | EACH | 2 | $500.00 | $1,500.00 | $2,500.00 | $1,500.00 | $1,800.00 |
| 41 | Pipe removed, over 24" diameter (202E35200) | FT | 140 | $80.00 | $100.00 | $50.00 | $45.00 | $25.00 |
| 42 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $500.00 | $15,000 | $10,000 | $18,000 | $27,500 |
| 43 | Unclassified excavation, as per plan (503E21301) | LS | 1 | $15,000 | $15,000 | $10,000 | $28,000 | $35,000 |
| 44 | Rock excavation, as per plan (503E31101) | CY | 15 | $100.00 | $400.00 | $200.00 | $140.00 | $80.00 |
| 45 | Epoxy coated steel reinforcement (509E10000) | LB | 3,195 | $2.50 | $3.00 | $3.00 | $2.80 | $2.25 |
| 46 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 9 | $1,500.00 | $1,100.00 | $1,000.00 | $2,200.00 | $2,600.00 |
| 47 | Class QC1 concrete, footing (511E46510) | CY | 28 | $750.00 | $1,100.00 | $1,200.00 | $790.00 | $700.00 |
| 48 | Class QC1 concrete, headwall (511E46610) | CY | 2 | $1,500.00 | $1,100.00 | $2,000.00 | $1,400.00 | $1,950.00 |
| 49 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 42 | $60.00 | $100.00 | $50.00 | $65.00 | $65.00 |
| 50 | Type 2 waterproofing (512E33000) | SY | 93 | $20.00 | $40.00 | $24.00 | $29.00 | $25.50 |
| 51 | Type 3 waterproofing (512E33010) | SY | 96 | $35.00 | $60.00 | $50.00 | $75.00 | $42.00 |
| 52 | 1" preformed expansion joint filler (516E13600) | SF | 28 | $15.00 | $50.00 | $30.00 | $11.00 | $15.00 |
| 53 | Porous backfill with geotextile fabric (518E21200) | CY | 11 | $150.00 | $175.00 | $140.00 | $280.00 | $150.00 |
| 54 | Rock channel protection, type B with aggregate filter (601E32110) | CY | 8 | $220.00 | $200.00 | $140.00 | $200.00 | $140.00 |
| 55 | 8' X 4' conduit, type A, 706.05 (611E94800) | FT | 76 | $1,850.00 | $1,100.00 | $1,500.00 | $1,650.00 | $1,400.00 |
| 56 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $23,500 | $25,000 | $50,000 | $6,500.00 | $7,500.00 |
| 57 | Maintaining traffic (614E11000) | LS | 1 | $27,500 | $35,000 | $50,000 | $25,000 | $30,000 |
| 58 | Construction layout stakes and surveying (623E10000) | LS | 1 | $4,000.00 | $10,000 | $25,000 | $10,000 | $19,500 |
| 59 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,000.00 | $2,500.00 | $1,500.00 | $800.00 | $2,100.00 |
| 60 | Post construction survey monument verification and report (623E51000) | LS | 1 | $1,000.00 | $2,500.00 | $2,500.00 | $800.00 | $2,100.00 |
| 61 | Mobilization (624E10000) | LS | 1 | $8,000.00 | $35,000 | $38,000 | $30,000 | $30,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 15, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.