ODOT contract 260010 bid tabulation
CUY-IR 480-13.04 Ramps (MINOR RECONSTRUCTION). Let by Ohio DOT on January 15, 2026, CUY. 9 bids received; low bid $1,870,651 by Tri-Mor Corp, -15% against the engineer's estimate of $2,200,000.
- Owner
- Ohio DOT
- Letting
- 15 JAN 2026
- Pay items
- 80
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Tri-Mor Corp | $1,870,651 | Low | -15% |
| 2 | Anthony Allega Cement Contractor Inc | $1,991,437 | +6.0% | -9.0% |
| 3 | Catts Construction Inc | $2,044,895 | +9.0% | -7.0% |
| 4 | Karvo Companies Inc | $2,117,187 | +13% | -4.0% |
| 5 | Great Lakes Construction Co | $2,271,659 | +21% | +3.0% |
| 6 | Perk Company Inc | $2,383,245 | +27% | +8.0% |
| 7 | Ruhlin Company | $2,483,324 | +33% | +13% |
| 8 | Fabrizi Trucking & Paving Co Inc | $2,747,715 | +47% | +25% |
| 9 | Kokosing Construction Company Inc | $2,789,694 | +49% | +27% |
Engineer's estimate: $2,200,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Tri-Mor Corp | 2. Anthony Allega Cement Contractor Inc | 3. Catts Construction Inc | 4. Karvo Companies Inc | 5. Great Lakes Construction Co | 6. Perk Company Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $7,000.00 | $896.00 | $1,800.00 | $3,000.00 | $20,000 | $9,170.00 |
| 2 | Pavement removed (202E23000) | SY | 8,469 | $12.50 | $8.36 | $13.50 | $17.00 | $15.25 | $18.90 |
| 3 | Walk removed (202E30000) | SF | 244 | $3.00 | $4.47 | $3.00 | $4.00 | $4.00 | $3.15 |
| 4 | Concrete median removed (202E30600) | SY | 105 | $15.00 | $11.64 | $7.00 | $150.00 | $25.00 | $34.00 |
| 5 | Curb removed (202E32000) | FT | 194 | $8.00 | $2.81 | $2.00 | $20.00 | $6.00 | $5.75 |
| 6 | Pipe removed, 24" and under (202E35100) | FT | 808 | $18.00 | $8.43 | $10.00 | $15.00 | $13.00 | $39.50 |
| 7 | Catch basin removed (202E58100) | EACH | 7 | $300.00 | $486.66 | $600.00 | $1,000.00 | $875.00 | $576.00 |
| 8 | Special - fill and plug existing conduit (202E70000) | FT | 117 | $13.00 | $21.86 | $22.00 | $25.00 | $25.00 | $34.50 |
| 9 | Special - pipe cleanout, 24" and under (202E70110) | FT | 190 | $5.00 | $28.00 | $4.50 | $20.00 | $30.00 | $33.60 |
| 10 | Excavation (203E10000) | CY | 2,751 | $19.00 | $27.02 | $39.00 | $50.01 | $42.00 | $39.55 |
| 11 | Embankment (203E20000) | CY | 150 | $10.00 | $33.75 | $10.00 | $50.00 | $12.50 | $25.25 |
| 12 | Subgrade compaction (204E10000) | SY | 8,946 | $1.00 | $0.32 | $1.00 | $1.00 | $1.80 | $1.60 |
| 13 | Excavation of subgrade (204E13000) | CY | 905 | $20.00 | $25.73 | $28.00 | $45.00 | $37.00 | $32.25 |
| 14 | Granular material, type B (204E30010) | CY | 905 | $50.00 | $70.96 | $29.00 | $50.00 | $65.00 | $84.00 |
| 15 | Proof rolling (204E45000) | HR | 5 | $200.00 | $145.69 | $289.00 | $275.00 | $300.00 | $572.00 |
| 16 | Linear grading, as per plan (209E60201) | STA | 20 | $1,350.00 | $764.03 | $500.00 | $250.00 | $500.00 | $378.10 |
| 17 | 4" concrete walk (608E10000) | SF | 258 | $12.00 | $24.68 | $10.00 | $8.00 | $22.00 | $16.10 |
| 18 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $2,800.00 | $1,008.00 | $5,500.00 | $1,200.00 | $3,000.00 | $4,640.00 |
| 19 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,800.00 | $1,008.00 | $5,500.00 | $1,200.00 | $3,000.00 | $4,640.00 |
| 20 | Soil analysis test (659E00100) | EACH | 2 | $200.00 | $420.00 | $90.00 | $135.00 | $375.00 | $500.00 |
| 21 | Topsoil (659E00300) | CY | 444 | $47.00 | $61.60 | $74.75 | $20.00 | $55.00 | $65.00 |
| 22 | Seeding and mulching, class 2 (659E00510) | SY | 3,991 | $2.25 | $1.34 | $2.00 | $2.00 | $1.20 | $2.00 |
| 23 | Repair seeding and mulching (659E14000) | SY | 201 | $2.25 | $2.24 | $1.00 | $5.00 | $2.00 | $2.00 |
| 24 | Inter-seeding (659E15000) | SY | 201 | $2.25 | $1.12 | $1.00 | $6.00 | $0.25 | $1.00 |
| 25 | Commercial fertilizer (659E20000) | TON | 0.57 | $3,500.00 | $1,344.00 | $1.00 | $884.74 | $1,200.00 | $1,000.00 |
| 26 | Lime (659E31000) | ACRE | 0.83 | $300.00 | $1.12 | $1.00 | $160.54 | $0.51 | $1,000.00 |
| 27 | Water (659E35000) | MGAL | 23 | $120.00 | $67.20 | $1.00 | $1.00 | $60.00 | $10.00 |
| 28 | Ditch erosion protection (670E00700) | SY | 375 | $16.00 | $3.36 | $1.00 | $5.00 | $3.00 | $3.80 |
| 29 | Ditch erosion protection mat, type B (670E00720) | SY | 305 | $3.00 | $4.48 | $2.50 | $5.00 | $4.00 | $4.70 |
| 30 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,200.00 | $3,248.00 | $5,000.00 | $5,000.00 | $2,985.00 | $2,900.00 |
| 31 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $8,300.00 | $9,475.20 | $8,000.00 | $12,500 | $8,800.00 | $3,720.00 |
| 32 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $12,000 | $12,467 | $11,131 | $15,000 | $8,750.00 | $15,133 |
| 33 | Erosion control (832E30000) | EACH | 32,623 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 34 | 6" shallow pipe underdrains with geotextile fabric (605E11110) | FT | 2,437 | $15.00 | $20.17 | $16.00 | $15.00 | $21.00 | $18.45 |
| 35 | 6" unclassified pipe underdrains (605E13300) | FT | 403 | $15.00 | $19.01 | $19.00 | $20.00 | $27.00 | $24.60 |
| 36 | 6" rock cut underdrains with geotextile fabric (605E13510) | FT | 2,398 | $20.00 | $24.36 | $17.00 | $15.00 | $26.00 | $27.00 |
| 37 | 6" base pipe underdrains with geotextile fabric (605E14020) | FT | 347 | $16.00 | $25.08 | $16.00 | $25.00 | $20.00 | $24.60 |
| 38 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 184 | $25.00 | $48.74 | $16.00 | $15.00 | $42.00 | $21.50 |
| 39 | 15" conduit, type B, as per plan (611E05901) | FT | 313 | $105.00 | $133.94 | $164.00 | $115.00 | $125.00 | $195.00 |
| 40 | 15" conduit, type C, as per plan (611E06101) | FT | 11 | $175.00 | $438.28 | $202.00 | $150.00 | $290.00 | $185.00 |
| 41 | 15" conduit, type C, as per plan (611E06101) | FT | 8 | $250.00 | $325.74 | $239.00 | $125.00 | $295.00 | $325.00 |
| 42 | 21" conduit, type C, as per plan (611E09101) | FT | 598 | $185.00 | $150.18 | $215.00 | $100.00 | $140.00 | $210.00 |
| 43 | Catch basin, no. 3 (611E98150) | EACH | 1 | $6,350.00 | $7,501.67 | $5,967.00 | $3,250.00 | $5,250.00 | $5,900.00 |
| 44 | Catch basin, no. 5 (611E98300) | EACH | 4 | $4,800.00 | $7,111.70 | $6,050.00 | $3,750.00 | $4,750.00 | $6,325.00 |
| 45 | Catch basin, no. 6 (611E98370) | EACH | 3 | $4,200.00 | $6,086.29 | $4,161.00 | $3,250.00 | $3,250.00 | $5,500.00 |
| 46 | Manhole, no. 1 (611E99550) | EACH | 1 | $5,100.00 | $6,245.62 | $6,240.00 | $5,500.00 | $3,750.00 | $6,725.00 |
| 47 | Full depth pavement sawing (252E01500) | FT | 198 | $8.00 | $5.60 | $4.50 | $5.00 | $15.00 | $3.50 |
| 48 | Diamond grinding portland cement concrete pavement, as per plan (257E10001) | SY | 153 | $55.00 | $47.11 | $80.00 | $25.00 | $41.00 | $43.10 |
| 49 | Aggregate base (304E20000) | CY | 1,530 | $60.00 | $77.64 | $73.00 | $50.00 | $75.00 | $85.80 |
| 50 | 6" reinforced concrete pavement, class QC 1P (451E10010) | SY | 72 | $85.00 | $228.60 | $98.00 | $80.00 | $210.00 | $210.00 |
| 51 | 11" reinforced concrete pavement, class QC 1P with QC/QA (451E15070) | SY | 634 | $110.00 | $115.10 | $122.00 | $175.00 | $139.00 | $138.85 |
| 52 | 11" non-reinforced concrete pavement, class QC 1P with QC/QA (452E14120) | SY | 7,867 | $93.00 | $95.40 | $104.50 | $105.00 | $119.00 | $111.40 |
| 53 | Curb, type 2-A (609E14000) | FT | 220 | $20.00 | $19.61 | $5.50 | $10.00 | $30.00 | $19.80 |
| 54 | Curb, type 3-B (609E22000) | FT | 8 | $20.00 | $61.58 | $28.00 | $95.00 | $230.00 | $19.70 |
| 55 | 4" concrete median (609E70000) | SY | 108 | $75.00 | $82.28 | $77.00 | $75.00 | $80.00 | $140.80 |
| 56 | Compacted aggregate, as per plan (617E10101) | CY | 18 | $86.00 | $202.54 | $52.00 | $275.00 | $210.00 | $212.00 |
| 57 | RPM (621E00100) | EACH | 69 | $100.00 | $89.32 | $259.00 | $80.00 | $79.75 | $75.00 |
| 58 | Ground mounted support, no. 3 post (630E03100) | FT | 349.90 | $10.00 | $16.80 | $19.00 | $15.00 | $8.15 | $14.00 |
| 59 | Sign post reflector (630E08600) | EACH | 12 | $18.00 | $42.00 | $78.00 | $37.50 | $15.50 | $65.00 |
| 60 | Sign, flat sheet (630E80100) | SF | 169.50 | $18.00 | $30.80 | $34.00 | $27.50 | $16.00 | $18.00 |
| 61 | Ramp reference marker (630E81010) | EACH | 2 | $85.00 | $140.00 | $156.00 | $125.00 | $65.00 | $180.00 |
| 62 | Removal of ground mounted sign and disposal (630E84900) | EACH | 12 | $30.00 | $11.20 | $12.50 | $10.00 | $25.25 | $30.00 |
| 63 | Removal of ground mounted post support and disposal (630E86002) | EACH | 19 | $30.00 | $11.20 | $12.50 | $10.00 | $26.00 | $40.00 |
| 64 | Edge line, 6" (646E10010) | MI | 0.83 | $6,000.00 | $5,656.00 | $10,590 | $8,500.00 | $5,050.00 | $6,500.00 |
| 65 | Lane line, 6" (646E10110) | MI | 0.14 | $2,500.00 | $2,290.43 | $5,295.00 | $4,250.00 | $2,045.00 | $5,500.00 |
| 66 | Channelizing line, 12" (646E10310) | FT | 202 | $2.00 | $2.07 | $3.00 | $2.25 | $1.85 | $2.50 |
| 67 | Crosswalk line, 12" (646E10510) | FT | 211 | $8.50 | $8.46 | $12.50 | $10.00 | $7.55 | $6.00 |
| 68 | Crosswalk line, 24" (646E10520) | FT | 39 | $14.00 | $13.87 | $15.50 | $12.50 | $12.38 | $11.00 |
| 69 | Lane reduction arrow (646E20350) | EACH | 5 | $300.00 | $299.04 | $436.00 | $350.00 | $267.00 | $200.00 |
| 70 | Dotted line (646E20500) | FT | 1,420 | $2.00 | $1.68 | $2.00 | $1.50 | $1.50 | $5.00 |
| 71 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 80 | $95.00 | $95.75 | $108.00 | $125.00 | $100.00 | $100.00 |
| 72 | Detour signing (614E12420) | LS | 1 | $25,000 | $22,148 | $24,636 | $25,000 | $13,500 | $21,600 |
| 73 | Portable changeable message sign, as per plan (614E18601) | SNMT | 8 | $1,000.00 | $952.00 | $1,059.00 | $1,000.00 | $750.00 | $1,292.50 |
| 74 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.44 | $15,000 | $14,000 | $15,572 | $12,500 | $11,125 | $12,500 |
| 75 | Water (616E10000) | MGAL | 3 | $200.00 | $165.64 | $698.00 | $113.93 | $65.00 | $238.50 |
| 76 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $19,000 | $9,489.68 | $20,698 | $15,000 | $15,000 | $25,000 |
| 77 | Maintaining traffic (614E11000) | LS | 1 | $75,000 | $56,007 | $63,700 | $50,000 | $34,550 | $112,000 |
| 78 | Field office, type B, as per plan (619E16011) | MNTH | 7 | $2,000.00 | $1,050.00 | $2,666.00 | $3,500.00 | $4,400.00 | $2,175.40 |
| 79 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $25,000 | $50,154 | $28,266 | $25,000 | $17,500 | $25,000 |
| 80 | Mobilization (624E10000) | LS | 1 | $50,000 | $93,651 | $14,000 | $126,000 | $113,000 | $34,259 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 15, 2026. Compiled by Mirage Metrics.