ODOT contract 260010 bid tabulation

CUY-IR 480-13.04 Ramps (MINOR RECONSTRUCTION). Let by Ohio DOT on January 15, 2026, CUY. 9 bids received; low bid $1,870,651 by Tri-Mor Corp, -15% against the engineer's estimate of $2,200,000.

Owner
Ohio DOT
Letting
15 JAN 2026
Pay items
80
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Tri-Mor Corp$1,870,651Low-15%
2Anthony Allega Cement Contractor Inc$1,991,437+6.0%-9.0%
3Catts Construction Inc$2,044,895+9.0%-7.0%
4Karvo Companies Inc$2,117,187+13%-4.0%
5Great Lakes Construction Co$2,271,659+21%+3.0%
6Perk Company Inc$2,383,245+27%+8.0%
7Ruhlin Company$2,483,324+33%+13%
8Fabrizi Trucking & Paving Co Inc$2,747,715+47%+25%
9Kokosing Construction Company Inc$2,789,694+49%+27%
ODOT contract 260010: bids by rank

Engineer's estimate: $2,200,000.

Bid tabulation

LinePay itemUnitQuantity1. Tri-Mor Corp2. Anthony Allega Cement Contractor Inc3. Catts Construction Inc4. Karvo Companies Inc5. Great Lakes Construction Co6. Perk Company Inc
1Clearing and grubbing (201E11000)LS1$7,000.00$896.00$1,800.00$3,000.00$20,000$9,170.00
2Pavement removed (202E23000)SY8,469$12.50$8.36$13.50$17.00$15.25$18.90
3Walk removed (202E30000)SF244$3.00$4.47$3.00$4.00$4.00$3.15
4Concrete median removed (202E30600)SY105$15.00$11.64$7.00$150.00$25.00$34.00
5Curb removed (202E32000)FT194$8.00$2.81$2.00$20.00$6.00$5.75
6Pipe removed, 24" and under (202E35100)FT808$18.00$8.43$10.00$15.00$13.00$39.50
7Catch basin removed (202E58100)EACH7$300.00$486.66$600.00$1,000.00$875.00$576.00
8Special - fill and plug existing conduit (202E70000)FT117$13.00$21.86$22.00$25.00$25.00$34.50
9Special - pipe cleanout, 24" and under (202E70110)FT190$5.00$28.00$4.50$20.00$30.00$33.60
10Excavation (203E10000)CY2,751$19.00$27.02$39.00$50.01$42.00$39.55
11Embankment (203E20000)CY150$10.00$33.75$10.00$50.00$12.50$25.25
12Subgrade compaction (204E10000)SY8,946$1.00$0.32$1.00$1.00$1.80$1.60
13Excavation of subgrade (204E13000)CY905$20.00$25.73$28.00$45.00$37.00$32.25
14Granular material, type B (204E30010)CY905$50.00$70.96$29.00$50.00$65.00$84.00
15Proof rolling (204E45000)HR5$200.00$145.69$289.00$275.00$300.00$572.00
16Linear grading, as per plan (209E60201)STA20$1,350.00$764.03$500.00$250.00$500.00$378.10
174" concrete walk (608E10000)SF258$12.00$24.68$10.00$8.00$22.00$16.10
18Preconstruction survey monument verification and report (623E50000)LS1$2,800.00$1,008.00$5,500.00$1,200.00$3,000.00$4,640.00
19Post construction survey monument verification and report (623E51000)LS1$2,800.00$1,008.00$5,500.00$1,200.00$3,000.00$4,640.00
20Soil analysis test (659E00100)EACH2$200.00$420.00$90.00$135.00$375.00$500.00
21Topsoil (659E00300)CY444$47.00$61.60$74.75$20.00$55.00$65.00
22Seeding and mulching, class 2 (659E00510)SY3,991$2.25$1.34$2.00$2.00$1.20$2.00
23Repair seeding and mulching (659E14000)SY201$2.25$2.24$1.00$5.00$2.00$2.00
24Inter-seeding (659E15000)SY201$2.25$1.12$1.00$6.00$0.25$1.00
25Commercial fertilizer (659E20000)TON0.57$3,500.00$1,344.00$1.00$884.74$1,200.00$1,000.00
26Lime (659E31000)ACRE0.83$300.00$1.12$1.00$160.54$0.51$1,000.00
27Water (659E35000)MGAL23$120.00$67.20$1.00$1.00$60.00$10.00
28Ditch erosion protection (670E00700)SY375$16.00$3.36$1.00$5.00$3.00$3.80
29Ditch erosion protection mat, type B (670E00720)SY305$3.00$4.48$2.50$5.00$4.00$4.70
30Storm water pollution prevention plan (832E15000)LS1$3,200.00$3,248.00$5,000.00$5,000.00$2,985.00$2,900.00
31Storm water pollution prevention inspections (832E15002)LS1$8,300.00$9,475.20$8,000.00$12,500$8,800.00$3,720.00
32Storm water pollution prevention inspection software (832E15010)LS1$12,000$12,467$11,131$15,000$8,750.00$15,133
33Erosion control (832E30000)EACH32,623$1.00$1.00$1.00$1.00$1.00$1.00
346" shallow pipe underdrains with geotextile fabric (605E11110)FT2,437$15.00$20.17$16.00$15.00$21.00$18.45
356" unclassified pipe underdrains (605E13300)FT403$15.00$19.01$19.00$20.00$27.00$24.60
366" rock cut underdrains with geotextile fabric (605E13510)FT2,398$20.00$24.36$17.00$15.00$26.00$27.00
376" base pipe underdrains with geotextile fabric (605E14020)FT347$16.00$25.08$16.00$25.00$20.00$24.60
386" conduit, type F for underdrain outlets (611E00510)FT184$25.00$48.74$16.00$15.00$42.00$21.50
3915" conduit, type B, as per plan (611E05901)FT313$105.00$133.94$164.00$115.00$125.00$195.00
4015" conduit, type C, as per plan (611E06101)FT11$175.00$438.28$202.00$150.00$290.00$185.00
4115" conduit, type C, as per plan (611E06101)FT8$250.00$325.74$239.00$125.00$295.00$325.00
4221" conduit, type C, as per plan (611E09101)FT598$185.00$150.18$215.00$100.00$140.00$210.00
43Catch basin, no. 3 (611E98150)EACH1$6,350.00$7,501.67$5,967.00$3,250.00$5,250.00$5,900.00
44Catch basin, no. 5 (611E98300)EACH4$4,800.00$7,111.70$6,050.00$3,750.00$4,750.00$6,325.00
45Catch basin, no. 6 (611E98370)EACH3$4,200.00$6,086.29$4,161.00$3,250.00$3,250.00$5,500.00
46Manhole, no. 1 (611E99550)EACH1$5,100.00$6,245.62$6,240.00$5,500.00$3,750.00$6,725.00
47Full depth pavement sawing (252E01500)FT198$8.00$5.60$4.50$5.00$15.00$3.50
48Diamond grinding portland cement concrete pavement, as per plan (257E10001)SY153$55.00$47.11$80.00$25.00$41.00$43.10
49Aggregate base (304E20000)CY1,530$60.00$77.64$73.00$50.00$75.00$85.80
506" reinforced concrete pavement, class QC 1P (451E10010)SY72$85.00$228.60$98.00$80.00$210.00$210.00
5111" reinforced concrete pavement, class QC 1P with QC/QA (451E15070)SY634$110.00$115.10$122.00$175.00$139.00$138.85
5211" non-reinforced concrete pavement, class QC 1P with QC/QA (452E14120)SY7,867$93.00$95.40$104.50$105.00$119.00$111.40
53Curb, type 2-A (609E14000)FT220$20.00$19.61$5.50$10.00$30.00$19.80
54Curb, type 3-B (609E22000)FT8$20.00$61.58$28.00$95.00$230.00$19.70
554" concrete median (609E70000)SY108$75.00$82.28$77.00$75.00$80.00$140.80
56Compacted aggregate, as per plan (617E10101)CY18$86.00$202.54$52.00$275.00$210.00$212.00
57RPM (621E00100)EACH69$100.00$89.32$259.00$80.00$79.75$75.00
58Ground mounted support, no. 3 post (630E03100)FT349.90$10.00$16.80$19.00$15.00$8.15$14.00
59Sign post reflector (630E08600)EACH12$18.00$42.00$78.00$37.50$15.50$65.00
60Sign, flat sheet (630E80100)SF169.50$18.00$30.80$34.00$27.50$16.00$18.00
61Ramp reference marker (630E81010)EACH2$85.00$140.00$156.00$125.00$65.00$180.00
62Removal of ground mounted sign and disposal (630E84900)EACH12$30.00$11.20$12.50$10.00$25.25$30.00
63Removal of ground mounted post support and disposal (630E86002)EACH19$30.00$11.20$12.50$10.00$26.00$40.00
64Edge line, 6" (646E10010)MI0.83$6,000.00$5,656.00$10,590$8,500.00$5,050.00$6,500.00
65Lane line, 6" (646E10110)MI0.14$2,500.00$2,290.43$5,295.00$4,250.00$2,045.00$5,500.00
66Channelizing line, 12" (646E10310)FT202$2.00$2.07$3.00$2.25$1.85$2.50
67Crosswalk line, 12" (646E10510)FT211$8.50$8.46$12.50$10.00$7.55$6.00
68Crosswalk line, 24" (646E10520)FT39$14.00$13.87$15.50$12.50$12.38$11.00
69Lane reduction arrow (646E20350)EACH5$300.00$299.04$436.00$350.00$267.00$200.00
70Dotted line (646E20500)FT1,420$2.00$1.68$2.00$1.50$1.50$5.00
71Law enforcement officer with patrol car for assistance (614E11110)HR80$95.00$95.75$108.00$125.00$100.00$100.00
72Detour signing (614E12420)LS1$25,000$22,148$24,636$25,000$13,500$21,600
73Portable changeable message sign, as per plan (614E18601)SNMT8$1,000.00$952.00$1,059.00$1,000.00$750.00$1,292.50
74Work zone edge line, class I, 6", 740.06, type I (614E22210)MI0.44$15,000$14,000$15,572$12,500$11,125$12,500
75Water (616E10000)MGAL3$200.00$165.64$698.00$113.93$65.00$238.50
76Premium for contract performance bond and for payment bond (103E05000)LS1$19,000$9,489.68$20,698$15,000$15,000$25,000
77Maintaining traffic (614E11000)LS1$75,000$56,007$63,700$50,000$34,550$112,000
78Field office, type B, as per plan (619E16011)MNTH7$2,000.00$1,050.00$2,666.00$3,500.00$4,400.00$2,175.40
79Construction layout stakes and surveying, as per plan (623E10001)LS1$25,000$50,154$28,266$25,000$17,500$25,000
80Mobilization (624E10000)LS1$50,000$93,651$14,000$126,000$113,000$34,259
ODOT contract 260010: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of January 15, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy