ODOT contract 260022 bid tabulation

LUC-US 20A-09.77 Roundabout (INTERSECTION). Let by Ohio DOT on January 15, 2026, LUC. 4 bids received; low bid $1,529,372 by Vernon Nagel Inc, -17% against the engineer's estimate of $1,846,000.

Owner
Ohio DOT
Letting
15 JAN 2026
Pay items
121
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Vernon Nagel Inc$1,529,372Low-17%
2Advanced Excavating & Demolition LLC$1,576,377+3.0%-15%
3Gerken Paving Inc$1,635,749+7.0%-11%
4Geddis Paving & Excavating Inc$1,713,490+12%-7.0%
ODOT contract 260022: bids by rank

Engineer's estimate: $1,846,000.

Bid tabulation

LinePay itemUnitQuantity1. Vernon Nagel Inc2. Advanced Excavating & Demolition LLC3. Gerken Paving Inc4. Geddis Paving & Excavating Inc
1Clearing and grubbing (201E11000)LS1$2,303.08$20,000$22,000$4,500.00
2Pavement removed (202E23000)SY4,838$7.00$15.00$12.75$11.50
3Curb removed (202E32000)FT239$3.50$15.00$4.50$7.00
4Pipe removed, 24" and under (202E35100)FT737$16.00$20.00$22.00$35.00
5Catch basin removed (202E58100)EACH6$200.00$850.00$1,125.00$770.00
6Removal misc.: 4" gas line (202E98200)FT127$7.80$16.00$11.00$7.00
7Excavation (203E10000)CY1,246$40.00$13.00$26.00$28.00
8Embankment (203E20000)CY1,710$8.00$22.00$26.75$19.00
9Subgrade compaction (204E10000)SY83$4.00$5.00$8.25$0.50
10Proof rolling (204E45000)HR2$280.00$300.00$160.00$150.00
11Cement (206E10500)TON219$233.00$215.00$233.00$240.00
12Curing coat (206E11000)SY7,241$0.99$1.50$0.99$2.00
13Cement stabilized subgrade, 14 inches deep (206E15020)SY7,241$2.39$5.75$2.39$2.50
148" concrete walk (608E15000)SF7,703$10.00$9.00$9.50$11.50
15Curb ramp (608E52000)SF1,338$15.40$10.00$9.50$18.50
16Detectable warning (608E53020)SF226$40.00$40.00$34.00$45.00
17Monument assembly, type C (623E38500)EACH5$1,150.00$875.00$1,850.00$1,150.00
18Soil analysis test (659E00100)EACH2$60.00$150.00$60.00$67.00
19Topsoil (659E00300)CY1,071$40.00$45.00$70.00$76.00
20Seeding and mulching (659E10000)SY8,286$2.40$1.25$1.20$1.20
21Repair seeding and mulching (659E14000)SY415$1.20$2.00$1.20$1.20
22Inter-seeding (659E15000)SY415$1.00$0.75$1.00$1.00
23Commercial fertilizer (659E20000)TON1.16$850.00$900.00$850.00$950.00
24Lime (659E31000)ACRE1.71$35.00$5.00$35.00$40.94
25Water (659E35000)MGAL46$1.00$0.75$1.00$1.00
26Ditch erosion protection (670E00700)SY910$1.80$2.90$1.80$2.00
27Storm water pollution prevention plan (832E15000)LS1$3,100.00$925.00$925.00$1,050.00
28Storm water pollution prevention inspections (832E15002)LS1$1,860.00$3,500.00$3,125.00$3,500.00
29Storm water pollution prevention inspection software (832E15010)LS1$2,195.73$15,000$13,275$14,900
30Erosion control (832E30000)EACH29,000$1.00$1.00$1.00$1.00
31Tied concrete block mat with type 1 underlayment (601E21050)SY2$200.00$250.00$275.00$315.00
324" unclassified pipe underdrains (605E05200)FT1,005$13.00$15.00$15.00$22.50
334" base pipe underdrains (605E06000)FT1,993$13.00$17.00$11.75$16.00
34Aggregate drains (605E31100)FT100$17.50$15.00$27.00$8.50
354" conduit, type E (611E00400)FT140$22.00$40.00$28.00$73.00
364" conduit, type F (611E00406)FT206$22.00$40.00$21.00$73.00
376" conduit, type B (611E00900)FT100$20.00$55.00$34.00$49.00
386" conduit, type E (611E01400)FT100$17.50$50.00$17.00$8.00
396" conduit, type F (611E01500)FT100$17.50$50.00$17.00$8.00
4012" conduit, type B, as per plan (611E04401)FT472$84.40$95.00$80.00$105.00
4112" conduit, type C (611E04600)FT311$68.00$88.00$42.00$77.00
4212" conduit, type D (611E04900)FT93$61.00$65.00$47.00$77.00
4315" conduit, type B, as per plan (611E05901)FT115$68.00$90.00$76.00$120.00
4421" conduit, type B, as per plan (611E08901)FT58$225.00$110.00$155.00$170.00
4524" conduit, type B, as per plan (611E10401)FT40$275.00$92.00$195.00$250.00
4624" conduit, type C (611E10600)FT91$106.00$95.00$130.00$140.00
47Catch basin, no. 3A (611E98180)EACH12$3,250.00$3,000.00$3,500.00$2,900.00
48Catch basin, no. 2-2B (611E98470)EACH6$1,850.00$2,500.00$2,750.00$1,950.00
49Catch basin, no. 2-3 (611E98510)EACH1$3,150.00$2,650.00$4,250.00$2,700.00
50Manhole, no. 3 (611E99574)EACH5$5,450.00$3,700.00$5,250.00$3,200.00
51Manhole adjusted to grade (611E99654)EACH1$520.00$750.00$860.00$810.00
52Manhole reconstructed to grade (611E99660)EACH2$2,160.00$1,300.00$2,250.00$2,450.00
53Precast reinforced concrete outlet (611E99710)EACH1$500.00$500.00$335.00$725.00
54Asphalt concrete base, PG64-22, (449) (301E56000)CY856$145.00$150.00$156.00$150.00
55Aggregate base (304E20000)CY1,190$46.00$53.00$47.50$54.50
56Tack coat (407E10000)GAL613$2.00$2.00$2.50$2.00
57Stabilized crushed aggregate (411E10000)CY53$45.00$80.00$69.00$110.00
58Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100)CY231$205.00$210.00$225.00$210.00
59Asphalt concrete intermediate course, type 2, (449) (441E70300)CY347$174.00$180.00$180.00$175.00
60Non-reinforced concrete pavement, misc.: 8" concre (452E19200)SY779$101.00$95.00$101.00$115.00
61Combination curb and gutter, type 2 (609E12000)FT984$27.50$25.00$26.50$27.00
62Combination curb and gutter, type 3 (609E18000)FT140$27.50$25.00$26.75$29.00
63Curb, type 6 (609E26000)FT546$18.50$16.00$17.75$19.00
64Combination curb and gutter, type 9 (609E31000)FT314$23.50$20.00$20.75$24.50
65Curb, type 10 (609E33000)FT899$17.00$14.00$15.50$17.50
6612" water main ductile iron pipe ansi class 53, mechanical joints and fittings (638E02504)FT7$1,350.00$1,000.00$1,500.00$2,150.00
67Fire hydrant and gate valve removed and reset (638E10600)EACH1$4,400.00$5,000.00$5,500.00$3,950.00
68Water work, misc.:manhole adjusted to grade (638E98000)EACH4$400.00$1,250.00$2,400.00$1,200.00
69Water work, misc.:manhole reconstructed to grade (638E98000)EACH2$400.00$1,250.00$2,100.00$1,950.00
70Water work, misc.:manhole relocated (638E98000)EACH1$3,820.00$3,500.00$11,450$7,200.00
71Manhole reconstructed to grade (611E99660)EACH2$2,600.00$1,250.00$1,250.00$2,200.00
72Connection, fused pull apart (625E00450)EACH18$201.00$201.00$201.00$140.00
73Connection, unfused permanent (625E00480)EACH12$201.00$201.00$201.00$140.00
74Light pole, conventional, AT10B40 (625E10490)EACH3$5,528.00$5,528.00$5,528.00$4,100.00
75Light pole, conventional, AT12B40 (625E10490)EACH2$5,639.00$5,639.00$5,639.00$4,100.00
76Light pole, conventional, AT15B40 (625E10490)EACH4$5,675.00$5,676.00$5,676.00$4,500.00
77Light pole foundation, 24" X 8' deep (625E14100)EACH9$2,429.00$2,429.00$2,429.00$2,000.00
78No. 4 AWG 2400 volt distribution cable (625E23200)FT3,681$4.90$4.90$4.90$5.20
79No. 10 AWG pole and bracket cable (625E23400)FT948$2.00$2.00$2.00$2.50
80Conduit, 2", 725.04 (625E25400)FT892$6.80$6.80$6.80$21.00
81Conduit, 3", 725.04 (625E25500)FT175$7.90$7.90$7.90$34.00
82Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH9$625.00$625.00$625.00$460.00
83Trench (625E29000)FT1,067$9.60$9.60$9.60$12.00
84Pull box, 725.08, 18" (625E30700)EACH7$1,484.00$1,484.00$1,484.00$1,150.00
85Ground rod (625E32000)EACH9$516.00$516.00$516.00$275.00
86Power service, as per plan (625E34001)EACH1$8,847.00$8,847.00$8,847.00$8,400.00
87Underground warning marking tape (625E36010)FT1,067$2.70$2.70$2.70$2.00
88Temporary lighting (625E39000)LS1$111.00$111.00$111.00$8,000.00
89Arc flash calculations and label (PS-A) (625E76000)EACH1$1,178.00$1,778.00$1,778.00$3,400.00
90Delineator, misc.: base mounted (620E70000)EACH4$185.00$350.00$350.00$200.00
91RPM (621E00100)EACH107$82.50$86.00$82.50$95.50
92Ground mounted support, no. 3 post, as per plan (630E03101)FT559$15.20$14.00$14.00$17.00
93Sign post reflector, as per plan (630E08601)EACH16$45.00$40.00$40.00$50.50
94Sign, flat sheet (630E80100)SF286.20$21.00$21.00$21.00$23.50
95Removal of ground mounted sign and disposal (630E84900)EACH10$12.00$25.00$25.00$13.50
96Removal of ground mounted post support and disposal (630E86002)EACH7$19.00$25.00$25.00$21.50
97Edge line, 6" (644E00104)MI0.50$5,500.00$8,000.00$8,000.00$5,500.00
98Center line (644E00300)MI0.23$7,500.00$10,000$10,000$7,500.00
99Crosswalk line, 24" (644E00630)FT294$7.00$7.00$7.00$7.00
100Transverse/diagonal line (644E00700)FT133$7.00$7.00$7.00$7.00
101Lane arrow (644E01300)EACH4$125.00$100.00$100.00$125.00
102Dotted line, 6" (644E01510)FT216$2.00$1.50$1.50$2.00
103Yield line (644E20800)FT72$20.00$10.00$10.00$20.00
104Mulch (661E00500)CY9$90.00$90.00$90.00$90.00
105Perennials, schizachyrium scoparium (661E14000)EACH25$25.50$60.00$25.50$25.50
106Perennials, sporobolus heteroleps (661E14000)EACH38$25.50$60.00$25.50$25.50
107Deciduous shrub, 5' height, viburnum prunifolium (661E20100)EACH3$126.00$700.00$126.00$126.00
108Landscape watering (661E31000)GAL301$1.00$5.00$1.00$1.00
109Planting, misc.:landscaping fabric under washed ST (661E99930)SY448$6.75$2.60$6.75$7.50
110Planting, misc.:washed stone, 2" to 3" (661E99930)SY448$25.67$35.00$25.67$29.00
111Law enforcement officer with patrol car for assistance (614E11110)HR80$70.00$92.00$122.00$145.00
112Detour signing (614E12420)LS1$2,250.00$2,500.00$2,250.00$20,000
113Portable changeable message sign, as per plan (614E18601)SNMT16$1,000.00$1,000.00$1,000.00$1,150.00
114Work zone stop line, class I, 642 paint (614E26200)FT36$10.00$10.00$10.00$11.00
115Water (616E10000)MGAL10$26.00$10.00$60.00$11.50
116Premium for contract performance bond and for payment bond (103E05000)LS1$11,930$30,000$12,250$14,700
117CPM progress schedule short duration projects (108E30000)LS1$5,000.00$10,500$7,500.00$1,150.00
118Maintaining traffic (614E11000)LS1$57,450$30,000$12,228$29,999
119Field office, type B (619E16010)MNTH6$1,950.00$1,250.00$4,500.00$1,000.00
120Construction layout stakes and surveying (623E10000)LS1$30,000$23,000$25,760$38,800
121Mobilization (624E10000)LS1$74,520$30,000$80,500$50,000
ODOT contract 260022: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of January 15, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy