ODOT contract 260006 bid tabulation
ATH-SR 13-13.71 (SLIDE REPAIR). Let by Ohio DOT on January 15, 2026, ATH. 7 bids received; low bid $984,857 by Allard Excavation LLC, -3.8% against the engineer's estimate of $1,024,000.
- Owner
- Ohio DOT
- Letting
- 15 JAN 2026
- Pay items
- 41
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Allard Excavation LLC | $984,857 | Low | -4.0% |
| 2 | D G M Inc | $886,436 | -10% | -13% |
| 3 | Shelly & Sands Inc | $1,046,102 | +6.0% | +2.0% |
| 4 | R C Construction Company and Son Inc | $1,216,645 | +24% | +19% |
| 5 | Alan Stone Co Inc | $1,294,430 | +31% | +26% |
| 6 | MC Kee Paving & Sealing LLC | $1,323,892 | +34% | +29% |
| 7 | Sunesis Construction Co | $2,052,228 | +108% | +100% |
Engineer's estimate: $1,024,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Allard Excavation LLC | 2. D G M Inc | 3. Shelly & Sands Inc | 4. R C Construction Company and Son Inc | 5. Alan Stone Co Inc | 6. MC Kee Paving & Sealing LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $65,000 | $80,000 | $121,300 | $125,000 | $140,000 | $90,000 |
| 2 | Excavation (203E10000) | CY | 25,147 | $26.00 | $20.00 | $24.50 | $23.00 | $30.00 | $35.00 |
| 3 | Pre-blast condition survey (208E10000) | LS | 1 | $4,647.00 | $1,000.00 | $4,280.00 | $10,000 | $6,500.00 | $1,250.00 |
| 4 | Blasting consultant (208E12000) | LS | 1 | $7,388.00 | $3,000.00 | $7,000.00 | $10,000 | $8,500.00 | $6,800.00 |
| 5 | Air blast and noise control (208E13000) | LS | 1 | $1,705.00 | $500.00 | $7,700.00 | $10,000 | $5,200.00 | $1,650.00 |
| 6 | Vibration control and monitoring (208E14000) | LS | 1 | $1,705.00 | $500.00 | $7,700.00 | $10,000 | $5,200.00 | $1,650.00 |
| 7 | Presplitting (208E15000) | SY | 581 | $37.00 | $40.00 | $19.00 | $175.00 | $75.00 | $45.00 |
| 8 | Hydrologist (208E16000) | LS | 1 | $4,547.00 | $12,000 | $38,000 | $10,000 | $21,000 | $18,000 |
| 9 | Seeding and mulching (659E10000) | SY | 538 | $2.00 | $1.00 | $2.00 | $5.00 | $4.27 | $2.25 |
| 10 | Seeding and mulching, as per plan (659E10001) | SY | 7,423 | $2.00 | $2.00 | $1.00 | $5.00 | $8.87 | $2.00 |
| 11 | Commercial fertilizer (659E20000) | TON | 1.07 | $1,421.00 | $1,500.00 | $1,250.00 | $2,900.00 | $979.41 | $1,300.00 |
| 12 | Lime (659E31000) | ACRE | 1.64 | $171.00 | $300.00 | $150.00 | $2,800.00 | $400.06 | $200.00 |
| 13 | Water (659E35000) | MGAL | 64 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 14 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,273.00 | $2,500.00 | $2,000.00 | $10,000 | $3,000.00 | $3,500.00 |
| 15 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $6,820.00 | $7,000.00 | $6,000.00 | $20,000 | $6,672.69 | $13,000 |
| 16 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $3,524.00 | $10,000 | $9,932.00 | $10,000 | $8,230.64 | $10,500 |
| 17 | Erosion control (832E30000) | EACH | 15,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 18 | Conduit, misc.: review of drainage facilities (611E97300) | LS | 1 | $1,564.00 | $500.00 | $500.00 | $15,000 | $2,300.00 | $1,500.00 |
| 19 | Tack coat (407E10000) | GAL | 147 | $4.10 | $4.75 | $3.27 | $10.00 | $4.72 | $4.00 |
| 20 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 72 | $386.00 | $450.00 | $450.00 | $575.00 | $377.56 | $350.00 |
| 21 | RPM (621E00100) | EACH | 18 | $171.00 | $160.00 | $150.00 | $200.00 | $232.88 | $175.00 |
| 22 | Raised pavement marker removed (621E54000) | EACH | 18 | $10.00 | $1.00 | $31.00 | $50.00 | $24.15 | $5.00 |
| 23 | Ground mounted support, no. 3 post (630E03100) | FT | 48 | $36.00 | $45.00 | $32.00 | $35.00 | $19.90 | $45.00 |
| 24 | Sign post reflector (630E08600) | EACH | 2 | $114.00 | $140.00 | $100.00 | $250.00 | $60.00 | $115.00 |
| 25 | Sign, flat sheet (630E80100) | SF | 16 | $91.00 | $50.00 | $80.00 | $250.00 | $34.43 | $100.00 |
| 26 | Removal of ground mounted sign and disposal (630E84900) | EACH | 2 | $28.00 | $40.00 | $250.00 | $50.00 | $31.14 | $300.00 |
| 27 | Removal of ground mounted post support and disposal (630E86002) | EACH | 4 | $28.00 | $30.00 | $125.00 | $50.00 | $37.13 | $150.00 |
| 28 | Edge line, 6", type 1 (642E00104) | MI | 0.26 | $2,273.00 | $3,500.00 | $2,000.00 | $9,500.00 | $6,518.65 | $4,000.00 |
| 29 | Center line, type 1 (642E00300) | MI | 0.13 | $4,547.00 | $3,500.00 | $4,000.00 | $9,500.00 | $11,359 | $7,000.00 |
| 30 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 16 | $97.00 | $60.00 | $105.00 | $20.00 | $80.00 | $125.00 |
| 31 | Increased barrier delineation (614E11630) | FT | 480 | $2.00 | $2.00 | $1.40 | $10.00 | $3.30 | $2.25 |
| 32 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 2 | $697.00 | $2,500.00 | $2,350.00 | $3,000.00 | $3,400.00 | $4,500.00 |
| 33 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $1,705.00 | $1,000.00 | $1,500.00 | $2,000.00 | $2,000.00 | $1,800.00 |
| 34 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 0.12 | $9,548.00 | $14,000 | $8,400.00 | $12,500 | $5,023.67 | $9,500.00 |
| 35 | Work zone stop line, class I, 642 paint (614E26200) | FT | 24 | $14.00 | $15.00 | $12.00 | $100.00 | $1.00 | $12.25 |
| 36 | Water (616E10000) | MGAL | 50 | $1.00 | $1.00 | $70.00 | $1.00 | $1.00 | $1.00 |
| 37 | Portable barrier, unanchored (622E41100) | FT | 480 | $43.00 | $30.00 | $32.00 | $30.00 | $21.00 | $81.00 |
| 38 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $7,456.22 | $45,000 | $5,000.00 | $30,000 | $18,000 | $20,000 |
| 39 | Maintaining traffic (614E11000) | LS | 1 | $38,874 | $57,500 | $29,000 | $30,000 | $70,000 | $40,000 |
| 40 | Construction layout stakes and surveying (623E10000) | LS | 1 | $8,525.00 | $13,000 | $21,000 | $40,000 | $22,000 | $12,500 |
| 41 | Mobilization (624E10000) | LS | 1 | $50,000 | $25,000 | $57,000 | $45,000 | $25,000 | $65,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 15, 2026. Compiled by Mirage Metrics.