ODOT contract 260013 bid tabulation
D12-PPM FY2026 (SPOT PATCHING / PAVEMENT REPAIR). Let by Ohio DOT on January 15, 2026, District 12. 4 bids received; low bid $2,375,588 by Karvo Companies Inc, +13% against the engineer's estimate of $2,100,000.
- Owner
- Ohio DOT
- Letting
- 15 JAN 2026
- Pay items
- 92
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Karvo Companies Inc | $2,375,588 | Low | +13% |
| 2 | Geauga Highway Co | $2,503,549 | +5.0% | +19% |
| 3 | Ronyak Paving Inc | $2,720,671 | +15% | +30% |
| 4 | Kokosing Construction Company Inc | $3,647,098 | +54% | +74% |
Engineer's estimate: $2,100,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Karvo Companies Inc | 2. Geauga Highway Co | 3. Ronyak Paving Inc | 4. Kokosing Construction Company Inc |
|---|---|---|---|---|---|---|---|
| 1 | Walk removed (202E30000) | SF | 2,639 | $18.00 | $3.00 | $5.00 | $11.00 |
| 2 | Curb removed (202E32000) | FT | 445 | $50.00 | $4.50 | $15.00 | $15.00 |
| 3 | Excavation (203E10000) | CY | 25 | $25.00 | $80.00 | $60.00 | $50.00 |
| 4 | Linear grading, as per plan (209E60201) | STA | 62 | $45.00 | $100.00 | $100.00 | $85.00 |
| 5 | 4" concrete walk (608E10000) | SF | 107 | $15.00 | $12.50 | $30.00 | $27.00 |
| 6 | Curb ramp, as per plan (608E52001) | SF | 2,473 | $20.00 | $22.00 | $50.00 | $27.00 |
| 7 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 6 | $1,200.00 | $950.00 | $1,785.00 | $802.00 |
| 8 | Monument assembly reconstructed to grade, as per plan (623E39601) | EACH | 3 | $1,500.00 | $1,000.00 | $1,900.00 | $1,540.00 |
| 9 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 10 | Catch basin adjusted to grade (611E98630) | EACH | 1 | $2,000.00 | $1,100.00 | $2,100.00 | $1,750.00 |
| 11 | Catch basin adjusted to grade, as per plan (611E98631) | EACH | 6 | $2,000.00 | $1,150.00 | $2,100.00 | $1,675.00 |
| 12 | Catch basin reconstructed to grade (611E98634) | EACH | 3 | $2,250.00 | $1,850.00 | $1,625.00 | $2,625.00 |
| 13 | Inlet adjusted to grade, as per plan (611E99151) | EACH | 3 | $3,000.00 | $1,100.00 | $1,475.00 | $1,675.00 |
| 14 | Inlet reconstructed to grade (611E99154) | EACH | 3 | $3,500.00 | $1,850.00 | $1,625.00 | $2,625.00 |
| 15 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 3 | $2,000.00 | $1,100.00 | $1,450.00 | $1,450.00 |
| 16 | Special - miscellaneous metal (611E99820) | LB | 3,500 | $3.00 | $2.50 | $5.00 | $2.45 |
| 17 | Drainage structure, misc.: cleanout (611E99900) | EACH | 26 | $750.00 | $300.00 | $475.00 | $945.00 |
| 18 | Partial depth pavement repair (441), as per plan (251E01001) | SY | 526 | $150.00 | $80.00 | $170.00 | $275.00 |
| 19 | Full depth rigid pavement removal and flexible replacement, as per plan (252E01001) | SY | 100 | $350.00 | $350.00 | $475.00 | $950.00 |
| 20 | Full depth rigid pavement removal and flexible replacement, as per plan (252E01001) | SY | 50 | $250.00 | $230.00 | $700.00 | $850.00 |
| 21 | Full depth rigid pavement removal and flexible replacement, as per plan (252E01001) | SY | 100 | $350.00 | $350.00 | $750.00 | $950.00 |
| 22 | Pavement repair, as per plan (253E02001) | CY | 150 | $1,500.00 | $2,200.00 | $2,675.00 | $5,500.00 |
| 23 | Pavement planing, asphalt concrete, (1.5") (254E01000) | SY | 10,125 | $3.50 | $2.00 | $5.50 | $2.05 |
| 24 | Full depth pavement removal and rigid replacement, type 2, class QC1, as per plan (255E12001) | SY | 177 | $325.00 | $180.00 | $400.00 | $206.50 |
| 25 | Full depth pavement sawing (255E20000) | FT | 104 | $5.00 | $8.50 | $20.00 | $4.00 |
| 26 | Aggregate base (304E20000) | CY | 25 | $125.00 | $125.00 | $70.00 | $100.00 |
| 27 | Non-tracking tack coat (407E20000) | GAL | 5,075 | $2.30 | $4.00 | $7.00 | $2.79 |
| 28 | Fine graded polymer asphalt concrete, type B, (449) (424E14100) | CY | 1,286 | $325.00 | $290.00 | $305.00 | $417.00 |
| 29 | Asphalt concrete surface course, 12.5 MM, type A (449), as per plan (442E22101) | CY | 710 | $375.00 | $350.00 | $405.00 | $540.00 |
| 30 | Curb, type 6 (609E26000) | FT | 77 | $125.00 | $20.00 | $50.00 | $55.00 |
| 31 | Compacted aggregate, as per plan (617E10101) | CY | 40 | $200.00 | $200.00 | $200.00 | $75.00 |
| 32 | Longitudinal joint adhesive (875E10000) | LB | 2,483 | $1.00 | $3.50 | $4.00 | $0.85 |
| 33 | Pavement planing, asphalt concrete, class A, (1.0" (897E01010) | SY | 46,243 | $3.00 | $1.75 | $2.50 | $3.70 |
| 34 | Valve box adjusted to grade, as per plan (638E10801) | EACH | 3 | $1,500.00 | $650.00 | $1,000.00 | $1,540.00 |
| 35 | Delineator, post ground mounted (620E00500) | EACH | 35 | $125.00 | $125.00 | $125.00 | $245.00 |
| 36 | RPM (621E00100) | EACH | 106 | $96.00 | $50.00 | $96.00 | $96.00 |
| 37 | Raised pavement marker removed (621E54000) | EACH | 92 | $1.00 | $30.00 | $5.00 | $9.00 |
| 38 | Removal of ground mounted sign and disposal (630E84900) | EACH | 4 | $50.00 | $150.00 | $75.00 | $50.00 |
| 39 | Removal of ground mounted post support and disposal (630E86002) | EACH | 8 | $60.00 | $100.00 | $75.00 | $60.00 |
| 40 | Edge line, 4" (646E10000) | MI | 0.27 | $3,900.00 | $5,000.00 | $3,900.00 | $3,900.00 |
| 41 | Edge line, 6" (646E10010) | MI | 1.34 | $4,075.00 | $5,500.00 | $4,075.00 | $4,075.00 |
| 42 | Lane line, 4" (646E10100) | MI | 2.91 | $1,885.00 | $3,250.00 | $1,885.00 | $1,885.00 |
| 43 | Center line (646E10200) | MI | 1.88 | $4,755.00 | $5,750.00 | $4,755.00 | $4,755.00 |
| 44 | Channelizing line, 8" (646E10300) | FT | 1,745 | $1.65 | $2.50 | $1.65 | $1.65 |
| 45 | Channelizing line, 12" (646E10310) | FT | 395 | $2.25 | $3.50 | $2.25 | $2.25 |
| 46 | Stop line (646E10400) | FT | 431 | $12.75 | $10.00 | $12.75 | $12.75 |
| 47 | Crosswalk line, 12" (646E10510) | FT | 1,756 | $5.30 | $9.50 | $5.30 | $5.30 |
| 48 | Transverse/diagonal line (646E10600) | FT | 511 | $9.00 | $10.00 | $9.00 | $9.00 |
| 49 | Chevron marking (646E10620) | FT | 70 | $13.00 | $10.00 | $13.00 | $13.00 |
| 50 | Island marking (646E10800) | SF | 300 | $6.75 | $10.00 | $6.75 | $6.75 |
| 51 | Lane arrow (646E20300) | EACH | 47 | $165.00 | $185.00 | $165.00 | $165.00 |
| 52 | Wrong way arrow (646E20320) | EACH | 1 | $335.00 | $375.00 | $335.00 | $335.00 |
| 53 | Dotted line, 4" (646E20502) | FT | 135 | $1.99 | $2.00 | $1.99 | $1.99 |
| 54 | Special - inventory existing pavement markings (690E98400) | LS | 1 | $2,800.00 | $1,250.00 | $2,800.00 | $2,800.00 |
| 55 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 700 | $125.00 | $100.00 | $100.00 | $135.00 |
| 56 | Work zone increased penalties sign (614E12484) | EACH | 10 | $175.00 | $175.00 | $175.00 | $175.00 |
| 57 | Asphalt concrete for maintaining traffic (614E13000) | CY | 150 | $125.00 | $100.00 | $250.00 | $125.00 |
| 58 | Portable changeable message sign, as per plan (614E18601) | SNMT | 24 | $900.00 | $900.00 | $900.00 | $900.00 |
| 59 | Work zone lane line, class I, 4", 642 paint (614E20100) | MI | 2.91 | $775.00 | $675.00 | $775.00 | $775.00 |
| 60 | Work zone lane line, class III, 4", 642 paint (614E20550) | MI | 2.91 | $750.00 | $675.00 | $750.00 | $750.00 |
| 61 | Work zone center line, class I, 642 paint (614E21100) | MI | 1.88 | $1,355.00 | $1,250.00 | $1,355.00 | $1,355.00 |
| 62 | Work zone center line, class III, 642 paint (614E21550) | MI | 1.88 | $1,175.00 | $1,250.00 | $1,175.00 | $1,175.00 |
| 63 | Work zone edge line, class I, 4", 642 paint (614E22100) | MI | 0.27 | $788.00 | $850.00 | $788.00 | $788.00 |
| 64 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 2.26 | $888.00 | $1,250.00 | $888.00 | $888.00 |
| 65 | Work zone edge line, class III, 4", 642 paint (614E22350) | MI | 0.27 | $775.00 | $1,000.00 | $775.00 | $775.00 |
| 66 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 1.31 | $775.00 | $1,250.00 | $775.00 | $775.00 |
| 67 | Work zone channelizing line, class I, 8", 642 paint (614E23200) | FT | 1,745 | $0.76 | $0.75 | $0.76 | $0.76 |
| 68 | Work zone channelizing line, class I, 12", 642 paint (614E23210) | FT | 1,015 | $0.87 | $0.85 | $0.87 | $0.87 |
| 69 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 1,745 | $0.70 | $0.75 | $0.70 | $0.70 |
| 70 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 395 | $0.82 | $0.85 | $0.82 | $0.82 |
| 71 | Work zone dotted line, class I, 4", 642 paint (614E24200) | FT | 135 | $0.88 | $0.65 | $0.88 | $0.88 |
| 72 | Work zone dotted line, class III, 4", 642 paint (614E24610) | FT | 135 | $0.85 | $0.65 | $0.85 | $0.85 |
| 73 | Work zone transverse/diagonal line, class I, 642 paint (614E25200) | FT | 581 | $2.75 | $3.75 | $2.75 | $2.75 |
| 74 | Work zone transverse/diagonal line, class III, 642 paint (614E25620) | FT | 581 | $2.55 | $3.75 | $2.55 | $2.55 |
| 75 | Work zone stop line, class I, 642 paint (614E26200) | FT | 396 | $3.20 | $3.75 | $3.20 | $3.20 |
| 76 | Work zone stop line, class III, 642 paint (614E26610) | FT | 396 | $3.00 | $3.75 | $3.00 | $3.00 |
| 77 | Work zone crosswalk line, class I, 12", 642 paint (614E27050) | FT | 1,587 | $2.15 | $3.50 | $2.15 | $2.15 |
| 78 | Work zone crosswalk line, class III, 12", 642 paint (614E27250) | FT | 1,587 | $1.95 | $3.50 | $1.95 | $1.95 |
| 79 | Work zone arrow, class I, 642 paint (614E30200) | EACH | 47 | $50.00 | $70.00 | $50.00 | $50.00 |
| 80 | Work zone arrow, class III, 642 paint (614E30650) | EACH | 47 | $45.00 | $70.00 | $45.00 | $45.00 |
| 81 | Signing, misc.:additional signs, ground mounted, A (630E97800) | SF | 1,400 | $10.00 | $17.50 | $17.50 | $17.50 |
| 82 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 12 | $675.00 | $675.00 | $675.00 | $675.00 |
| 83 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $25,000 | $25,000 | $17,700 | $14,500 |
| 84 | Maintaining traffic (614E11000) | LS | 1 | $300,000 | $742,000 | $250,000 | $523,279 |
| 85 | Construction layout stakes and surveying (623E10000) | LS | 1 | $10,000 | $1,000.00 | $7,500.00 | $6,594.29 |
| 86 | Mobilization (624E10000) | LS | 1 | $150,000 | $35,000 | $190,000 | $182,000 |
| 100 | Pavement planing, portland cement concrete(1.5") (254E01010) | SY | 6,937 | $10.00 | $5.50 | $15.00 | $8.40 |
| 101 | Tack coat, 702.13 (407E13900) | GAL | 555 | $2.50 | $6.00 | $10.00 | $3.50 |
| 102 | Edge line, 6", type 1 (642E00104) | MI | 0.95 | $2,655.00 | $3,250.00 | $2,655.00 | $2,655.00 |
| 103 | Lane line, 6", type 1 (642E00204) | MI | 0.95 | $1,175.00 | $2,500.00 | $1,175.00 | $1,175.00 |
| 104 | Channelizing line, 12", type 1 (642E00404) | FT | 620 | $2.55 | $2.50 | $2.55 | $2.55 |
| 105 | Work zone lane line, class I, 6", 642 paint (614E20110) | MI | 0.95 | $900.00 | $1,250.00 | $900.00 | $900.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 15, 2026. Compiled by Mirage Metrics.