ODOT contract 260007 bid tabulation
ATH-SR 682-04.70 (SIDEWALK). Let by Ohio DOT on January 15, 2026, ATH. 5 bids received; low bid $951,988 by Shelly & Sands Inc, -8.6% against the engineer's estimate of $1,042,000.
- Owner
- Ohio DOT
- Letting
- 15 JAN 2026
- Pay items
- 25
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $951,988 | Low | -9.0% |
| 2 | Oglesby Construction Inc | $966,583 | +2.0% | -7.0% |
| 3 | Axis Civil Construction LLC | $988,467 | +4.0% | -5.0% |
| 4 | MC Kee Paving & Sealing LLC | $1,152,374 | +21% | +11% |
| 5 | Alan Stone Co Inc | $1,173,081 | +23% | +13% |
Engineer's estimate: $1,042,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Oglesby Construction Inc | 3. Axis Civil Construction LLC | 4. MC Kee Paving & Sealing LLC | 5. Alan Stone Co Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Walk removed (202E30000) | SF | 40,496 | $2.70 | $2.70 | $3.90 | $4.00 | $1.75 |
| 2 | Curb and gutter removed (202E32500) | FT | 1,492 | $16.00 | $10.00 | $10.00 | $10.00 | $6.00 |
| 3 | 4" concrete walk, as per plan (608E10001) | SF | 34,186 | $7.50 | $6.25 | $9.20 | $12.00 | $14.00 |
| 4 | 6" concrete walk, as per plan (608E13001) | SF | 125 | $24.00 | $8.00 | $28.00 | $17.00 | $25.00 |
| 5 | Curb ramp, as per plan (608E52001) | SF | 8,601 | $23.00 | $17.00 | $23.50 | $26.00 | $15.00 |
| 6 | Seeding and mulching, as per plan (659E10001) | SY | 100 | $22.00 | $20.00 | $28.00 | $7.50 | $30.00 |
| 7 | Catch basin reconstructed to grade (611E98634) | EACH | 3 | $1,500.00 | $3,000.00 | $3,800.00 | $1,500.00 | $3,400.00 |
| 8 | Manhole adjusted to grade (611E99654) | EACH | 10 | $1,000.00 | $1,500.00 | $880.00 | $750.00 | $1,200.00 |
| 9 | Special - gas valve box adjusted to grade (611E99700) | EACH | 1 | $600.00 | $750.00 | $650.00 | $525.00 | $55.00 |
| 10 | Aggregate base (304E20000) | CY | 529 | $200.00 | $180.00 | $185.00 | $130.00 | $160.00 |
| 11 | Combination curb and gutter, type 2 (609E12000) | FT | 383 | $95.00 | $45.00 | $50.00 | $50.00 | $95.00 |
| 12 | Curb, type 4-C, as per plan (609E24511) | FT | 16 | $160.00 | $30.00 | $50.00 | $53.00 | $120.00 |
| 13 | Valve box adjusted to grade (638E10800) | EACH | 2 | $595.00 | $750.00 | $750.00 | $400.00 | $360.00 |
| 14 | Ground mounted support, no. 3 post (630E03100) | FT | 84 | $22.00 | $48.00 | $25.31 | $18.00 | $25.00 |
| 15 | Sign, flat sheet (630E80100) | SF | 77 | $26.00 | $58.00 | $29.52 | $20.00 | $25.00 |
| 16 | Signing, misc.:solar-powered rectangular rapid fla (630E97700) | EACH | 6 | $10,810 | $13,250 | $8,732.54 | $11,500 | $11,000 |
| 17 | Stop line (644E00500) | FT | 92 | $11.00 | $11.00 | $9.80 | $19.00 | $10.00 |
| 18 | Crosswalk line, 12" (644E00620) | FT | 280 | $5.00 | $8.00 | $4.75 | $11.00 | $5.50 |
| 19 | Crosswalk line, 24" (644E00630) | FT | 378 | $11.00 | $11.00 | $9.80 | $15.00 | $10.00 |
| 20 | Removal of pavement marking (644E30000) | FT | 1,051 | $4.00 | $1.00 | $3.75 | $6.75 | $6.50 |
| 21 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,340.00 | $100,000 | $9,840.87 | $17,000 | $7,000.00 |
| 22 | Maintaining traffic (614E11000) | LS | 1 | $55,000 | $70,800 | $45,000 | $55,000 | $188,000 |
| 23 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $7,500.00 | $30,000 | $5,000.00 | $24,000 | $18,500 |
| 24 | Mobilization (624E10000) | LS | 1 | $50,000 | $42,000 | $25,000 | $50,000 | $36,000 |
| 100 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 15, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.