ODOT contract 260012 bid tabulation
D01-BP FY26 (BRIDGE PAINTING). Let by Ohio DOT on January 15, 2026, District 1. 7 bids received; low bid $1,893,660 by Elite Contractors Inc, -10% against the engineer's estimate of $2,110,000.
- Owner
- Ohio DOT
- Letting
- 15 JAN 2026
- Pay items
- 38
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Elite Contractors Inc | $1,893,660 | Low | -10% |
| 2 | Apbn Inc | $2,137,152 | +13% | +1.0% |
| 3 | Corrosion Resistance LTD | $2,185,202 | +15% | +4.0% |
| 4 | Vimas Painting Company Inc | $2,223,370 | +17% | +5.0% |
| 5 | Spartan Contracting LLC | $2,232,000 | +18% | +6.0% |
| 6 | 360 Construction Company Inc | $2,293,688 | +21% | +9.0% |
| 7 | Legend Painting Inc | $3,261,432 | +72% | +55% |
Engineer's estimate: $2,110,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Elite Contractors Inc | 2. Apbn Inc | 3. Corrosion Resistance LTD | 4. Vimas Painting Company Inc | 5. Spartan Contracting LLC | 6. 360 Construction Company Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,000.00 | $3,000.00 | $4,500.00 | $12,000 | $1,000.00 | $5,000.00 |
| 2 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 3 | Pavement repair (253E02000) | CY | 20 | $200.00 | $100.00 | $1,100.00 | $400.00 | $400.00 | $350.00 |
| 4 | Non-tracking tack coat (407E20000) | GAL | 20 | $3.00 | $3.00 | $2.75 | $200.00 | $10.00 | $3.00 |
| 5 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 10 | $250.00 | $100.00 | $975.00 | $800.00 | $400.00 | $360.00 |
| 6 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 800 | $100.00 | $20.00 | $100.00 | $70.00 | $75.00 | $95.00 |
| 7 | Detour signing (614E12420) | LS | 1 | $8,666.93 | $4,000.00 | $8,700.00 | $15,000 | $9,000.00 | $8,700.00 |
| 8 | Replacement sign (614E12500) | EACH | 10 | $239.36 | $250.00 | $239.36 | $250.00 | $240.00 | $240.00 |
| 9 | Replacement drum (614E12600) | EACH | 30 | $55.24 | $50.00 | $55.24 | $60.00 | $56.00 | $56.00 |
| 10 | Portable changeable message sign, as per plan (614E18601) | SNMT | 10 | $779.02 | $1,000.00 | $780.00 | $900.00 | $780.00 | $780.00 |
| 11 | Compacted aggregate (617E10100) | CY | 50 | $80.00 | $50.00 | $150.00 | $40.00 | $100.00 | $75.00 |
| 12 | Railroad flagging services (900E00100) | EACH | 243,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 13 | Surface preparation of existing structural steel (514E00050) | SF | 17,225 | $9.00 | $10.00 | $15.00 | $16.00 | $14.00 | $12.00 |
| 14 | Field painting of existing structural steel, prime coat (514E00056) | SF | 17,225 | $3.00 | $4.00 | $4.00 | $3.00 | $3.00 | $9.00 |
| 15 | Field painting structural steel, intermediate coat (514E00060) | SF | 17,225 | $3.00 | $4.00 | $3.65 | $3.00 | $3.00 | $3.00 |
| 16 | Field painting structural steel, finish coat (514E00066) | SF | 17,225 | $3.00 | $4.00 | $3.75 | $3.00 | $3.00 | $2.00 |
| 17 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 24 | $100.00 | $100.00 | $50.00 | $200.00 | $100.00 | $150.00 |
| 18 | Final inspection repair (514E10000) | EACH | 22 | $150.00 | $100.00 | $350.00 | $350.00 | $200.00 | $250.00 |
| 19 | Scupper, lengthening, as per plan (518E12901) | EACH | 20 | $742.50 | $500.00 | $742.50 | $850.00 | $500.00 | $350.00 |
| 20 | Surface preparation of existing structural steel (514E00050) | SF | 38,954 | $9.00 | $10.00 | $11.40 | $10.00 | $14.00 | $10.00 |
| 21 | Field painting of existing structural steel, prime coat (514E00056) | SF | 38,954 | $2.50 | $4.00 | $2.90 | $3.00 | $3.00 | $8.00 |
| 22 | Field painting structural steel, intermediate coat (514E00060) | SF | 38,954 | $2.50 | $4.00 | $2.90 | $3.50 | $3.00 | $3.00 |
| 23 | Field painting structural steel, finish coat (514E00066) | SF | 38,954 | $2.50 | $4.00 | $3.05 | $3.50 | $3.00 | $2.00 |
| 24 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 31 | $100.00 | $100.00 | $50.00 | $200.00 | $100.00 | $150.00 |
| 25 | Final inspection repair (514E10000) | EACH | 24 | $150.00 | $100.00 | $350.00 | $350.00 | $200.00 | $250.00 |
| 26 | Scupper, lengthening, as per plan (518E12901) | EACH | 25 | $742.50 | $500.00 | $742.50 | $850.00 | $500.00 | $350.00 |
| 27 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 426 | $35.00 | $40.00 | $59.00 | $50.00 | $45.00 | $55.00 |
| 28 | Surface preparation of existing structural steel (514E00050) | SF | 8,339 | $19.00 | $11.00 | $16.25 | $21.00 | $15.00 | $15.00 |
| 29 | Field painting of existing structural steel, prime coat (514E00056) | SF | 8,339 | $4.00 | $5.00 | $3.20 | $5.00 | $3.00 | $10.00 |
| 30 | Field painting structural steel, intermediate coat (514E00060) | SF | 8,339 | $4.00 | $5.00 | $5.25 | $5.00 | $3.00 | $5.00 |
| 31 | Field painting structural steel, finish coat (514E00066) | SF | 8,339 | $4.00 | $5.00 | $5.45 | $4.00 | $3.00 | $4.00 |
| 32 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 12 | $100.00 | $100.00 | $50.00 | $200.00 | $100.00 | $150.00 |
| 33 | Final inspection repair (514E10000) | EACH | 15 | $150.00 | $100.00 | $350.00 | $350.00 | $200.00 | $250.00 |
| 34 | Scupper, lengthening, as per plan (518E12901) | EACH | 34 | $680.00 | $500.00 | $680.00 | $800.00 | $500.00 | $350.00 |
| 35 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $15,000 | $10,000 | $5,000.00 | $8,000.00 | $14,097 | $5,000.00 |
| 36 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $20,000 | $22,000 | $20,500 | $30,000 | $45,000 | $25,000 |
| 37 | Maintaining traffic (614E11000) | LS | 1 | $100,000 | $148,000 | $85,000 | $100,000 | $150,000 | $100,000 |
| 38 | Mobilization (624E10000) | LS | 1 | $100,000 | $148,500 | $85,000 | $100,000 | $110,000 | $100,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 15, 2026. Compiled by Mirage Metrics.