ODOT contract 260205 bid tabulation
MAH-Sheridan Rd (Poland) (BIKEWAYS). Let by Ohio DOT on April 23, 2026, MAH. 4 bids received; low bid $350,000 by Eclipse Co LLC, +27% against the engineer's estimate of $276,000.
- Owner
- Ohio DOT
- Letting
- 23 APR 2026
- Pay items
- 51
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Eclipse Co LLC | $350,000 | Low | +27% |
| 2 | Geauga Highway Co | $380,561 | +9.0% | +38% |
| 3 | Shelly & Sands Inc | $429,297 | +23% | +56% |
| 4 | Parella-Pannunzio Inc | $496,326 | +42% | +80% |
Engineer's estimate: $276,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eclipse Co LLC | 2. Geauga Highway Co | 3. Shelly & Sands Inc | 4. Parella-Pannunzio Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,000.00 | $10,000 | $15,000 | $12,000 |
| 2 | Pavement removed (202E23000) | SY | 139 | $30.00 | $25.00 | $25.00 | $25.00 |
| 3 | Walk removed (202E30000) | SF | 106 | $17.00 | $3.75 | $5.00 | $7.00 |
| 4 | Removal misc.:bollard (202E98100) | EACH | 9 | $60.00 | $250.00 | $105.00 | $50.00 |
| 5 | Removal misc.:inspection well (202E98100) | EACH | 1 | $210.00 | $1,100.00 | $650.00 | $100.00 |
| 6 | Removal misc.:conduit (202E98200) | FT | 10 | $30.00 | $12.50 | $50.00 | $40.00 |
| 7 | Excavation (203E10000) | CY | 799 | $31.50 | $45.00 | $43.00 | $90.00 |
| 8 | Embankment (203E20000) | CY | 57 | $16.25 | $25.00 | $201.00 | $150.00 |
| 9 | Embankment, as per plan (203E20001) | CY | 50 | $22.00 | $45.00 | $20.00 | $75.00 |
| 10 | Subgrade compaction (204E10000) | SY | 1,836 | $3.00 | $2.25 | $5.00 | $3.00 |
| 11 | Excavation of subgrade (204E13000) | CY | 25 | $29.00 | $75.00 | $25.00 | $30.00 |
| 12 | Granular material, type B (204E30010) | CY | 25 | $88.25 | $100.00 | $91.00 | $110.00 |
| 13 | Proof rolling, as per plan (204E45001) | HR | 2 | $278.00 | $150.00 | $370.00 | $125.00 |
| 14 | Geotextile fabric (204E50000) | SY | 73 | $9.25 | $6.00 | $3.00 | $18.00 |
| 15 | 4" concrete walk (608E10000) | SF | 215 | $11.50 | $15.50 | $14.00 | $19.00 |
| 16 | Curb ramp, as per plan (608E52001) | SF | 864 | $11.75 | $32.00 | $38.00 | $34.00 |
| 17 | Special - as-built construction plans (690E91000) | LS | 1 | $2,403.50 | $6,500.00 | $5,000.00 | $5,000.00 |
| 18 | Special - survey control verification (690E98400) | LS | 1 | $1,540.00 | $3,500.00 | $5,000.00 | $6,750.00 |
| 19 | Topsoil (659E00300) | CY | 361 | $58.50 | $85.00 | $82.00 | $120.00 |
| 20 | Seeding and mulching (659E10000) | SY | 3,247 | $2.50 | $4.90 | $2.50 | $3.75 |
| 21 | Commercial fertilizer (659E20000) | TON | 0.50 | $1,033.00 | $12.00 | $1,010.00 | $975.00 |
| 22 | Water (659E35000) | MGAL | 20 | $1.00 | $12.00 | $1.00 | $10.00 |
| 23 | Slope erosion protection (670E00500) | SY | 1,346 | $1.75 | $5.50 | $1.50 | $3.10 |
| 24 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,860.00 | $2,600.00 | $2,800.00 | $3,500.00 |
| 25 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $2,354.00 | $2,000.00 | $7,000.00 | $8,560.00 |
| 26 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $6,515.75 | $3,000.00 | $6,670.00 | $14,500 |
| 27 | Erosion control (832E30000) | EACH | 13,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 28 | Concrete masonry (602E20000) | CY | 0.42 | $5,108.76 | $2,600.00 | $5,000.00 | $4,200.00 |
| 29 | 12" conduit, type C (611E04600) | FT | 203 | $84.00 | $85.00 | $112.00 | $110.00 |
| 30 | 12" conduit, type D (611E04900) | FT | 54 | $95.75 | $90.00 | $100.00 | $165.00 |
| 31 | 12" conduit, type D (611E04900) | FT | 36 | $127.25 | $96.00 | $200.00 | $220.00 |
| 32 | Conduit, misc.:type B for drainage discharge conti (611E97400) | FT | 5 | $65.00 | $200.00 | $98.00 | $100.00 |
| 33 | Conduit, misc.:type C for drainage discharge conti (611E97400) | FT | 5 | $65.00 | $200.00 | $98.00 | $100.00 |
| 34 | Conduit, misc.:type E for drainage discharge conti (611E97400) | FT | 5 | $65.00 | $200.00 | $98.00 | $100.00 |
| 35 | Conduit, misc.:type F for drainage discharge conti (611E97400) | FT | 5 | $65.00 | $255.00 | $98.00 | $100.00 |
| 36 | Catch basin, no. 2-2B (611E98470) | EACH | 2 | $3,900.50 | $4,600.00 | $3,000.00 | $2,900.00 |
| 37 | Inspection well (611E99720) | EACH | 1 | $2,569.75 | $3,000.00 | $1,250.00 | $1,900.00 |
| 38 | Aggregate base (304E20000) | CY | 295 | $107.25 | $150.00 | $98.00 | $160.00 |
| 39 | Non-tracking tack coat (407E20000) | GAL | 92 | $3.25 | $5.00 | $3.05 | $2.90 |
| 40 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 128 | $353.00 | $370.00 | $321.00 | $426.00 |
| 41 | 6" non-reinforced concrete pavement, class QC MS (452E10050) | SY | 71 | $95.75 | $180.00 | $110.00 | $110.00 |
| 42 | Ground mounted support, no. 3 post (630E03100) | FT | 44 | $47.50 | $35.00 | $23.00 | $20.00 |
| 43 | Sign, flat sheet (630E80100) | SF | 1.50 | $49.25 | $150.00 | $65.00 | $75.00 |
| 44 | Removal of ground mounted sign and reerection (630E85100) | EACH | 4 | $97.75 | $250.00 | $145.00 | $250.00 |
| 45 | Crosswalk line, 24" (643E00630) | FT | 176 | $43.75 | $12.00 | $40.00 | $28.00 |
| 46 | Water (616E10000) | MGAL | 5 | $49.75 | $10.00 | $300.00 | $100.00 |
| 47 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,045.75 | $4,000.00 | $5,075.00 | $12,450 |
| 48 | Maintaining traffic (614E11000) | LS | 1 | $45,258 | $20,000 | $27,855 | $6,500.00 |
| 49 | Field office, type B (619E16010) | MNTH | 6 | $1,650.00 | $500.00 | $4,000.00 | $1,500.00 |
| 50 | Construction layout stakes and surveying (623E10000) | LS | 1 | $6,419.25 | $6,600.00 | $18,874 | $18,950 |
| 51 | Mobilization (624E10000) | LS | 1 | $29,020 | $12,000 | $22,000 | $24,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 23, 2026. Compiled by Mirage Metrics.