| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $20,000 | $18,000 | $50,000 |
| 2 | Pavement planing, asphalt concrete (1.5" depth) (254E01000) | SY | 200 | $50.00 | $30.00 | $85.00 |
| 3 | Non-tracking tack coat (407E20000) | GAL | 18 | $10.00 | $2.00 | $5.00 |
| 4 | Asphalt concrete surface course, type 1, (449), as per plan (441E70101) | CY | 9 | $325.00 | $2,800.00 | $1,800.00 |
| 5 | Rumble strips, shoulder (asphalt concrete) (618E40100) | FT | 720 | $20.00 | $14.00 | $30.00 |
| 6 | Lane line, 6" (644E00204) | MI | 0.01 | $386,065 | $390,000 | $386,065 |
| 7 | Lane line, 6" (646E10110) | MI | 0.16 | $28,940 | $30,000 | $28,940 |
| 8 | Wet reflective epoxy pavement marking, edge line, 6" (807E12010) | MI | 0.13 | $35,865 | $36,000 | $35,865 |
| 9 | Wet reflective epoxy pavement marking, lane line, 6" (807E12110) | MI | 0.39 | $12,195 | $13,000 | $12,195 |
| 10 | Wet reflective thermoplastic pavement marking, edge line, 6" (807E14010) | MI | 0.57 | $9,995.00 | $10,000 | $9,995.00 |
| 11 | Wet reflective thermoplastic pavement marking, lane line, 6" (807E14110) | MI | 1.20 | $5,240.00 | $6,000.00 | $5,240.00 |
| 12 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $150.00 | $140.00 | $100.00 |
| 13 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 3 | $2,920.00 | $2,700.00 | $2,134.05 |
| 14 | Detour signing (614E12420) | LS | 1 | $6,829.84 | $8,000.00 | $6,829.84 |
| 15 | Work zone raised pavement marker, as per plan (614E12801) | EACH | 685 | $44.00 | $40.00 | $37.80 |
| 16 | Barrier reflector, type 1, one way (614E13310) | EACH | 36 | $11.22 | $12.00 | $11.22 |
| 17 | Object marker, one way (614E13350) | EACH | 36 | $19.66 | $22.00 | $19.66 |
| 18 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 1.23 | $11,899 | $12,000 | $11,899 |
| 19 | Work zone channelizing line, class I, 12", 740.06, type I (614E23410) | FT | 8,175 | $4.66 | $5.00 | $4.66 |
| 20 | Work zone dotted line, class I, 6", 740.06, type I (614E24402) | FT | 294 | $1.09 | $4.00 | $1.09 |
| 21 | Portable barrier, unanchored (622E41100) | FT | 1,672 | $28.36 | $32.00 | $30.00 |
| 22 | Structural steel members, level UF, as per plan (513E10201) | LB | 500 | $100.00 | $120.00 | $60.50 |
| 23 | Surface preparation of existing structural steel (514E00050) | SF | 7,400 | $25.00 | $35.00 | $50.00 |
| 24 | Field painting of existing structural steel, prime coat (514E00056) | SF | 7,400 | $4.00 | $7.00 | $15.00 |
| 25 | Field painting structural steel, intermediate coat (514E00060) | SF | 7,400 | $4.00 | $7.00 | $15.00 |
| 26 | Field painting structural steel, finish coat (514E00066) | SF | 7,400 | $4.00 | $7.00 | $15.00 |
| 27 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 11 | $150.00 | $200.00 | $150.00 |
| 28 | Final inspection repair (514E10000) | EACH | 4 | $150.00 | $300.00 | $200.00 |
| 29 | Structural steel members, level UF, as per plan (513E10201) | LB | 1,000 | $100.00 | $120.00 | $55.00 |
| 30 | Structural steel for rehabilitation (513E21550) | LB | 660 | $107.50 | $140.00 | $91.62 |
| 31 | Surface preparation of existing structural steel (514E00050) | SF | 104,000 | $16.00 | $12.00 | $24.00 |
| 32 | Field painting of existing structural steel, prime coat (514E00056) | SF | 104,000 | $3.00 | $5.00 | $10.00 |
| 33 | Field painting structural steel, intermediate coat (514E00060) | SF | 104,000 | $3.00 | $5.50 | $4.00 |
| 34 | Field painting structural steel, finish coat (514E00066) | SF | 104,000 | $3.00 | $5.50 | $4.00 |
| 35 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 104 | $150.00 | $200.00 | $150.00 |
| 36 | Final inspection repair (514E10000) | EACH | 30 | $150.00 | $300.00 | $200.00 |
| 37 | Structural steel members, level UF, as per plan (513E10201) | LB | 500 | $100.00 | $120.00 | $60.50 |
| 38 | Surface preparation of existing structural steel (514E00050) | SF | 89,000 | $16.00 | $11.00 | $16.00 |
| 39 | Field painting of existing structural steel, prime coat (514E00056) | SF | 89,000 | $3.00 | $4.00 | $7.00 |
| 40 | Field painting structural steel, intermediate coat (514E00060) | SF | 89,000 | $3.00 | $5.00 | $5.00 |
| 41 | Field painting structural steel, finish coat (514E00066) | SF | 89,000 | $3.00 | $5.00 | $4.00 |
| 42 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 91 | $150.00 | $200.00 | $150.00 |
| 43 | Final inspection repair (514E10000) | EACH | 28 | $150.00 | $300.00 | $200.00 |
| 44 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $40,000 | $30,000 | $75,000 |
| 45 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $100,000 | $110,000 | $150,000 |
| 46 | Maintaining traffic (614E11000) | LS | 1 | $200,000 | $200,000 | $250,000 |
| 47 | Field office, type B, as per plan (619E16011) | MNTH | 6 | $4,000.00 | $5,000.00 | $3,500.00 |
| 48 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $2,000.00 | $5,000.00 | $20,000 |
| 49 | Mobilization (624E10000) | LS | 1 | $200,000 | $300,000 | $200,000 |