ODOT contract 260385 bid tabulation

HOC-/VIN-SR 327-00.00/06.88 (TWO LANE RESURFACING). Let by Ohio DOT on August 27, 2026, HOC. 2 bids received; low bid $3,492,500 by Shelly & Sands Inc, -1.1% against the engineer's estimate of $3,533,000.

Owner
Ohio DOT
Letting
27 AUG 2026
Pay items
19
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Shelly & Sands Inc$3,492,500Low-1.0%
2Fillmore Construction$3,692,781+6.0%+5.0%
ODOT contract 260385: bids by rank

Engineer's estimate: $3,533,000.

Bid tabulation

LinePay itemUnitQuantity1. Shelly & Sands Inc2. Fillmore Construction
1Partial depth pavement repair (441) (251E01010)CY1,200$365.00$360.00
2Pavement planing, asphalt concrete, 2.25" (254E01000)SY150,864$3.15$2.00
3Non-tracking tack coat (407E20000)GAL19,612$3.50$4.00
4Asphalt concrete surface course, type 1, (448), PG70-22M (441E50100)CY5,240$220.00$249.50
5Asphalt concrete intermediate course, type 1, (448) (441E50200)CY4,190$210.00$225.40
6RPM (621E00100)EACH1,215$36.00$36.00
7Raised pavement marker removed (621E54000)EACH1,215$8.00$10.00
8Edge line, 6", type 1 (642E00104)MI22.36$825.00$825.00
9Center line, type 1 (642E00300)MI11.18$1,250.00$1,250.00
10Stop line (644E00500)FT116$14.95$15.00
11Work zone marking sign (614E12460)EACH80$92.00$150.00
12Work zone center line, class I, 642 paint (614E21100)MI33.54$1,170.00$1,170.00
13Work zone center line, class II, 642 paint (614E21500)MI33.54$300.00$1,500.00
14Work zone stop line, class I, 642 paint (614E26200)FT90$3.00$3.00
15Polymer modified asphalt expansion joint system (846E00110)CF151$600.00$675.00
16Premium for contract performance bond and for payment bond (103E05000)LS1$12,286$10,000
17Maintaining traffic (614E11000)LS1$147,500$200,000
18Construction layout stakes and surveying, as per plan (623E10001)LS1$8,000.00$15,000
19Mobilization (624E10000)LS1$75,000$110,000
ODOT contract 260385: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of August 27, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy