| 1 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 |
| 2 | Partial depth pavement repair (442), as per plan (251E01021) | SY | 1,500 | $80.00 | $68.00 |
| 3 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 161,723 | $2.50 | $3.05 |
| 4 | Pavement planing, asphalt concrete, as per plan, 1 (254E01001) | SY | 778 | $5.00 | $3.30 |
| 5 | Patching planed surface (254E01600) | SY | 8,086 | $2.50 | $4.25 |
| 6 | Full depth pavement removal and rigid replacement, type 2, class QC MS, as per plan (255E16001) | SY | 480 | $550.00 | $515.00 |
| 7 | Full depth pavement sawing (255E20000) | FT | 1,980 | $4.80 | $6.15 |
| 8 | Tack coat (407E10000) | GAL | 14,668 | $4.00 | $4.30 |
| 9 | Asphalt concrete intermediate course, type 1, (449), (under guardrail), as per plan (441E70801) | CY | 20 | $650.00 | $860.00 |
| 10 | Asphalt concrete surface course, 12.5 MM, type A (447), as per plan (442E10301) | CY | 6,770 | $245.00 | $303.00 |
| 11 | Compacted aggregate (617E10100) | CY | 150 | $168.11 | $171.00 |
| 13 | RPM (621E00100) | EACH | 839 | $29.86 | $30.00 |
| 14 | Raised pavement marker removed (621E54000) | EACH | 731 | $10.00 | $22.25 |
| 15 | Edge line, 6" (644E00104) | MI | 0.20 | $6,380.00 | $8,450.00 |
| 16 | Center line (644E00300) | MI | 0.08 | $7,990.00 | $14,250 |
| 17 | Channelizing line, 12" (644E00404) | FT | 405 | $1.50 | $3.50 |
| 18 | Stop line (644E00500) | FT | 184 | $5.50 | $9.00 |
| 19 | Lane arrow (644E01300) | EACH | 8 | $125.00 | $115.00 |
| 20 | Dotted line, 6" (644E01510) | FT | 2,115 | $1.40 | $1.10 |
| 21 | Speed measurement marking (644E40000) | EACH | 12 | $250.00 | $350.00 |
| 22 | Wet reflective epoxy pavement marking, edge line, 6" (807E12010) | MI | 0.14 | $45,715 | $27,500 |
| 23 | Wet reflective epoxy pavement marking, lane line, 6" (807E12110) | MI | 0.07 | $16,275 | $15,000 |
| 24 | Wet reflective thermoplastic pavement marking, edge line, 6" (807E14010) | MI | 20.33 | $4,325.00 | $4,590.00 |
| 25 | Wet reflective thermoplastic pavement marking, lane line, 6" (807E14110) | MI | 10.17 | $1,925.00 | $2,100.00 |
| 26 | Wet reflective thermoplastic pavement marking, channelizing line, 12" (807E14310) | FT | 3,317 | $2.25 | $3.50 |
| 27 | Wet reflective thermoplastic pavement marking, dotted line, 6" (807E14410) | FT | 3,271 | $2.15 | $1.10 |
| 28 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 30.50 | $1,425.00 | $1,240.00 |
| 29 | Grooving for 6" recessed pavement marking, (asphalt) (850E10110) | FT | 3,271 | $1.90 | $1.25 |
| 30 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 3,317 | $2.00 | $2.00 |
| 31 | Grooving for 6" recessed pavement marking, (concrete) (850E20010) | MI | 0.21 | $2,750.00 | $7,500.00 |
| 32 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $90.00 | $120.00 |
| 33 | Work zone marking sign (614E12460) | EACH | 12 | $98.00 | $98.00 |
| 34 | Work zone increased penalties sign (614E12484) | EACH | 18 | $98.00 | $98.00 |
| 35 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 20.48 | $230.00 | $625.00 |
| 36 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.16 | $835.00 | $5,250.00 |
| 37 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.80 | $1,050.00 | $10,750 |
| 38 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 41.34 | $525.00 | $825.00 |
| 39 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 7,444 | $0.75 | $0.80 |
| 40 | Work zone dotted line, class I, 6", 740.06, type I (614E24402) | FT | 4,224 | $0.55 | $0.60 |
| 41 | Work zone stop line, class III, 642 paint (614E26610) | FT | 368 | $3.65 | $5.00 |
| 42 | Water (616E10000) | MGAL | 16 | $1.00 | $8.00 |
| 43 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 56 | $600.00 | $600.00 |
| 44 | Pavement planing, asphalt concrete, 2" (254E01000) | SY | 800 | $12.00 | $14.50 |
| 45 | Pavement planing, portland cement concrete, 2" (254E01010) | SY | 324 | $30.00 | $18.00 |
| 46 | Tack coat (407E10000) | GAL | 130 | $4.00 | $4.30 |
| 47 | Tack coat, 702.13 (407E13900) | GAL | 23 | $4.00 | $5.00 |
| 48 | Sawing and sealing asphalt concrete pavement joints (409E30000) | FT | 80 | $27.00 | $27.00 |
| 49 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 28 | $500.00 | $355.00 |
| 50 | Bridge deck waterproofing asphalt concrete (856E10000) | CY | 63 | $600.00 | $390.00 |
| 51 | Pavement planing, asphalt concrete, 2" (254E01000) | SY | 800 | $12.00 | $14.50 |
| 52 | Pavement planing, portland cement concrete 2" (254E01010) | SY | 324 | $30.00 | $18.00 |
| 53 | Tack coat (407E10000) | GAL | 130 | $4.00 | $4.30 |
| 54 | Tack coat, 702.13 (407E13900) | GAL | 23 | $4.00 | $5.00 |
| 55 | Sawing and sealing asphalt concrete pavement joints (409E30000) | FT | 80 | $27.00 | $27.00 |
| 56 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 28 | $500.00 | $355.00 |
| 57 | Bridge deck waterproofing asphalt concrete (856E10000) | CY | 63 | $600.00 | $390.00 |
| 58 | Sealing concrete bridge decks with HMWM resin (512E10300) | SY | 100 | $20.50 | $20.50 |
| 59 | Treating of concrete bridge deck with SRS (512E10400) | SY | 900 | $12.00 | $12.00 |
| 60 | Sealing concrete bridge decks with HMWM resin (512E10300) | SY | 100 | $20.50 | $20.50 |
| 61 | Treating of concrete bridge deck with SRS (512E10400) | SY | 900 | $12.00 | $12.00 |
| 62 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $12,090 | $12,000 |
| 63 | Maintaining traffic (614E11000) | LS | 1 | $125,000 | $247,000 |
| 64 | Construction layout stakes and surveying (623E10000) | LS | 1 | $12,500 | $10,000 |
| 65 | Mobilization (624E10000) | LS | 1 | $105,000 | $125,000 |