| Rank | Total bid | Against the low bid |
|---|---|---|
| 1 | Low | |
| 2 | ||
| 3 | ||
| 4 | ||
| 5 | ||
| 6 | ||
| 7 |
Bid tabulation
| Line | Pay item | Unit | Quantity | Rank 1 | Rank 2 | Rank 3 | Rank 4 | Rank 5 | Rank 6 |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Remove and reinstall existing signs (0905-0101000A) | LS | 1 | $500.00 | $3,900.00 | $3,210.00 | $3,000.00 | $49,680 | $4,500.00 |
| 2 | Cinder mulch (1040-0192000K) | CY | 2.30 | $1,000.00 | $280.00 | $940.00 | $900.00 | $307.80 | $800.00 |
| 3 | Concrete inlets, type G-2 (0470-0315000E) | EACH | 9 | $3,400.00 | $2,700.00 | $4,590.00 | $5,500.00 | $3,780.00 | $4,500.00 |
| 4 | 6 inch ductile iron pipe with class A backfill (1140-0400000F) | LF | 36 | $369.00 | $160.00 | $290.00 | $200.00 | $534.60 | $600.00 |
| 5 | Legend removal (0225-0155100J) | SF | 1,056 | $5.00 | $3.50 | $3.25 | $1.50 | $8.10 | $2.75 |
| 6 | Asphalt pavement sawcutting (0310-0119000F) | LF | 3,600 | $5.00 | $3.00 | $8.00 | $12.00 | $7.02 | $13.00 |
| 7 | Rock mulch (1040-0196000M) | TON | 109 | $200.00 | $220.00 | $165.00 | $160.00 | $162.00 | $140.00 |
| 8 | Signs, standard sheeting, plywood (0940-0203000J) | SF | 559 | $52.00 | $51.00 | $43.00 | $26.00 | $48.06 | $26.50 |
| 9 | Concrete curbs, curb and gutter (0759-0103000F) | LF | 3,123 | $70.00 | $47.00 | $56.00 | $75.00 | $48.00 | $58.10 |
| 10 | Aggregate base (0640-0100000M) | TON | 1,484 | $81.00 | $55.00 | $92.00 | $25.00 | $51.84 | $20.00 |
| 11 | Concrete curbs, standard curb, modified (0759-0112000F) | LF | 222 | $131.00 | $44.00 | $59.00 | $75.00 | $46.41 | $58.10 |
| 12 | Moving existing hydrants (1160-0102000E) | EACH | 4 | $6,800.00 | $3,400.00 | $2,980.00 | $3,000.00 | $11,340 | $3,000.00 |
| 13 | Concrete driveways (0759-0126000J) | SF | 698 | $20.00 | $18.00 | $19.00 | $30.00 | $24.84 | $16.10 |
| 14 | Pole foundations (0970-0100000A) | EACH | 1 | $65,000 | $95,000 | $68,960 | $12,000 | $99,360 | $10,000 |
| 15 | Temporary plastic drums (0224-0145000E) | EACH | 90 | $40.00 | $45.00 | $55.00 | $80.00 | $54.00 | $38.00 |
| 16 | Concrete walks (0759-0128000J) | SF | 22,784 | $14.00 | $10.80 | $15.00 | $20.00 | $11.82 | $11.15 |
| 17 | Flashing beacon, OR207 at W hartley (0990-0106000A) | EACH | 1 | $62,000 | $79,000 | $57,830 | $65,000 | $64,828 | $80,000 |
| 18 | Chain link fence, type CL- 6R (1050-0135000F) | LF | 20 | $420.00 | $480.00 | $410.00 | $100.00 | $383.40 | $180.00 |
| 19 | Concrete curbs, standard curb (0759-0110000F) | LF | 21 | $151.00 | $44.00 | $86.00 | $90.00 | $84.60 | $58.10 |
| 20 | Extra for asphalt approaches (0749-0100000E) | EACH | 1 | $1,000.00 | $1,000.00 | $3,760.00 | $3,000.00 | $2,727.00 | $1,800.00 |
| 21 | Inlet protection, type 3 (0280-0114030E) | EACH | 20 | $77.00 | $75.00 | $137.00 | $50.00 | $135.00 | $130.00 |
| 22 | Soil sample collection and analytical testing (0294-0700000E) | EACH | 5 | $2,000.00 | $1,200.00 | $2,060.00 | $2,500.00 | $945.00 | $1,800.00 |
| 23 | Commercial asphalt concrete pavement (0740-0100000M) | TON | 311 | $369.00 | $375.00 | $350.00 | $450.00 | $361.80 | $275.00 |
| 24 | Sod lawn (1040-0189000J) | SY | 273 | $36.00 | $120.00 | $26.00 | $25.00 | $48.60 | $22.00 |
| 25 | Flashing beacon, US730 at S first ST (0990-0106000A) | EACH | 1 | $16,000 | $24,000 | $14,445 | $20,000 | $17,977 | $25,000 |
| 26 | Perforated steel square tube slip base sign supports (0930-0114000A) | LB | 1,985.30 | $10.07 | $17.63 | $14.39 | $15.11 | $28.08 | $15.11 |
| 27 | Removal of inlets (0310-0104000E) | EACH | 9 | $1,200.00 | $1,500.00 | $970.00 | $1,700.00 | $1,701.00 | $1,175.00 |
| 28 | Bar removal (0225-0156000J) | SF | 3,473 | $7.00 | $6.00 | $6.00 | $2.00 | $9.94 | $4.85 |
| 29 | Sequential arrow signs (0222-0162000E) | EACH | 3 | $700.00 | $3,200.00 | $4,290.00 | $500.00 | $1,620.00 | $4,500.00 |
| 30 | Stripe removal (0225-0154000F) | LF | 252 | $5.00 | $2.00 | $1.75 | $0.75 | $5.24 | $1.50 |
| 31 | Temporary walks (0228-0167680J) | SF | 1,000 | $9.00 | $9.00 | $15.00 | $13.00 | $7.56 | $10.00 |
| 32 | Segregate and stockpile contaminated soil (0294-0600000A) | LS | 1 | $18,000 | $9,700.00 | $4,290.00 | $1,000.00 | $1.08 | $15,000 |
| 33 | Removal of pipes (0310-0100000F) | LF | 23 | $110.00 | $300.00 | $104.00 | $50.00 | $378.00 | $60.00 |
| 34 | Sign support footings (0920-0100000A) | CY | 2.88 | $5,208.33 | $16,667 | $13,536 | $4,861.11 | $9,396.00 | $6,250.00 |
| 35 | Ductile iron pipe bend, 6 inch (1140-0650000E) | EACH | 4 | $900.00 | $1,000.00 | $670.00 | $300.00 | $1,296.00 | $1,100.00 |
| 36 | 6 inch gate valve (1150-0100000E) | EACH | 1 | $2,100.00 | $3,500.00 | $4,570.00 | $3,000.00 | $2,592.00 | $4,800.00 |
| 37 | Adjusting inlets (0490-0105000E) | EACH | 2 | $1,200.00 | $430.00 | $890.00 | $1,500.00 | $1,706.40 | $1,200.00 |
| 38 | Temporary signs (0222-0102000J) | SF | 1,686 | $12.00 | $28.00 | $11.00 | $22.00 | $19.44 | $25.00 |
| 39 | 12 inch storm sewer pipe, 5 FT depth (0445-035012AF) | LF | 59 | $284.00 | $190.00 | $280.00 | $125.00 | $540.00 | $325.00 |
| 40 | Valley gutter concrete surfacing (0759-0135000J) | SF | 149 | $38.00 | $15.00 | $41.00 | $50.00 | $47.69 | $36.10 |
| 41 | Pavement bar, type B (0867-0145000J) | SF | 3,637 | $26.00 | $16.00 | $12.70 | $12.70 | $13.18 | $12.70 |
| 42 | Flashing beacon, OR207 at W joseph ave (0990-0106000A) | EACH | 1 | $70,000 | $83,000 | $60,440 | $67,000 | $67,650 | $80,000 |
| 43 | Inlet protection, type 11 (0280-0114110E) | EACH | 1 | $110.00 | $105.00 | $270.00 | $50.00 | $216.00 | $200.00 |
| 44 | Contaminated soil disposal (0294-0200010M) | TON | 292 | $85.00 | $88.00 | $106.00 | $25.00 | $118.80 | $90.00 |
| 45 | Adjusting boxes (0490-0100000E) | EACH | 34 | $350.00 | $110.00 | $520.00 | $150.00 | $648.00 | $450.00 |
| 46 | Traffic signal modification, US395 at E highland ave (0990-0106000A) | EACH | 1 | $24,000 | $26,000 | $20,580 | $25,000 | $24,598 | $70,000 |
| 47 | Topsoil (1040-0101000K) | CY | 50 | $133.00 | $220.00 | $350.00 | $150.00 | $270.00 | $200.00 |
| 48 | Extra for new curb ramps (0759-0154100E) | EACH | 86 | $900.00 | $760.00 | $1,060.00 | $2,000.00 | $1,188.00 | $1,200.00 |
| 49 | Truncated domes on new surfaces (0759-0510000J) | SF | 1,217 | $44.00 | $36.00 | $38.00 | $38.00 | $32.63 | $38.10 |
| 50 | Removal of surfacings for curb ramp construction (0310-0106101J) | SY | 5,549 | $31.00 | $54.00 | $61.00 | $65.00 | $44.28 | $65.00 |
| 51 | 6 inch storm sewer pipe, 5 FT depth (0445-035006AF) | LF | 16 | $266.00 | $170.00 | $310.00 | $100.00 | $1,026.00 | $480.00 |
| 52 | Concrete inlets, type G-1 (0470-0313000E) | EACH | 2 | $3,500.00 | $2,500.00 | $2,770.00 | $5,500.00 | $4,536.00 | $4,500.00 |
| 53 | Minor adjustment of manholes (0490-0120000E) | EACH | 6 | $500.00 | $650.00 | $1,220.00 | $2,000.00 | $1,458.00 | $650.00 |
| 54 | Pavement legend, type B: arrows (0867-0103000E) | EACH | 18 | $450.00 | $350.00 | $350.00 | $350.00 | $270.00 | $350.00 |
| 55 | Longitudinal pavement markings - paint (0860-0200000F) | LF | 111 | $14.00 | $6.00 | $5.00 | $5.00 | $10.80 | $5.00 |
| 56 | Pollution control plan (0290-0100000A) | LS | 1 | $500.00 | $1,800.00 | $1,500.00 | $2,000.00 | $324.00 | $500.00 |
| 57 | Inlet protection, type 10 (0280-0114100E) | EACH | 5 | $80.00 | $92.00 | $144.00 | $50.00 | $167.40 | $180.00 |
| 58 | Traffic signal modification, US395 at E theater LN (0990-0106000A) | EACH | 1 | $15,000 | $17,000 | $13,505 | $20,000 | $16,959 | $65,000 |
| 59 | Lead compliance plan (0294-0500000A) | LS | 1 | $2,500.00 | $4,000.00 | $1,500.00 | $1,000.00 | $2,160.00 | $1,500.00 |
| 60 | Connection to existing structures (0490-0104000E) | EACH | 16 | $1,000.00 | $320.00 | $1,620.00 | $1,500.00 | $1,614.60 | $1,000.00 |
| 61 | Crosswalk closure supports (0902-0101000E) | EACH | 4 | $1,500.00 | $1,800.00 | $1,505.00 | $1,500.00 | $1,566.00 | $1,000.00 |
| 62 | Pedestrian channelizing devices (0228-0141600F) | LF | 900 | $23.00 | $24.00 | $18.00 | $20.00 | $16.20 | $6.25 |
| 63 | Cold plane pavement removal, 0 - 1 inches deep (0620-0103000J) | SY | 15 | $62.00 | $108.00 | $250.00 | $65.00 | $97.20 | $100.00 |
| 64 | Cold plane pavement removal, 2 inches deep (0620-0120000J) | SY | 63 | $69.00 | $108.00 | $250.00 | $65.00 | $129.60 | $40.00 |
| 65 | Flashing beacon, OR207 at M.P. 7.92 (DR wendell ford ave) (0990-0106000A) | EACH | 1 | $21,000 | $30,000 | $19,065 | $25,000 | $22,963 | $30,000 |
| 66 | Inlet protection, type 7 (0280-0114070E) | EACH | 16 | $80.00 | $110.00 | $140.00 | $50.00 | $243.00 | $150.00 |
| 67 | Traffic signal modification, US395 at OR207 (elm ave) (0990-0106000A) | EACH | 1 | $15,000 | $15,000 | $11,965 | $20,000 | $15,294 | $60,000 |
| 68 | Temporary curb ramp, parallel (0228-0167670E) | EACH | 4 | $1,800.00 | $1,800.00 | $1,100.00 | $2,500.00 | $1,350.00 | $1,800.00 |
| 69 | Level 3, 1/2 inch ACP mixture (0744-0302000M) | TON | 31 | $369.00 | $375.00 | $430.00 | $500.00 | $486.00 | $295.00 |
| 70 | Temporary barricades, type II (0224-0104000E) | EACH | 30 | $90.00 | $110.00 | $43.00 | $75.00 | $70.20 | $65.00 |
| 71 | Traffic signal modification, US395 at W hermiston ave - E gladys ave (0990-0106000A) | EACH | 1 | $8,500.00 | $9,000.00 | $7,230.00 | $10,000 | $10,180 | $40,000 |
| 72 | Bollards (0815-0100000E) | EACH | 3 | $1,500.00 | $1,000.00 | $410.00 | $1,200.00 | $1,620.00 | $1,050.00 |
| 73 | Lighting poles and arms (0970-0200000A) | EACH | 1 | $7,000.00 | $8,000.00 | $6,445.00 | $9,000.00 | $9,335.52 | $11,000 |
| 74 | Truncated domes on existing surfaces (0759-0520000J) | SF | 20 | $95.00 | $36.00 | $84.00 | $60.00 | $107.69 | $60.10 |
| 75 | Hydrant assemblies (1160-0100000E) | EACH | 4 | $8,000.00 | $8,800.00 | $10,680 | $5,000.00 | $9,180.00 | $10,550 |
| 76 | Remove existing signs (0905-0100000A) | LS | 1 | $2,500.00 | $730.00 | $605.00 | $5,000.00 | $24,408 | $4,500.00 |
| 77 | Luminaires, lamps, and ballasts (0970-0104000A) | EACH | 1 | $1,500.00 | $1,500.00 | $1,120.00 | $2,000.00 | $1,205.28 | $5,000.00 |
| 78 | Switching, conduit, and wiring (0970-0105000A) | LF | 1 | $50,000 | $30,000 | $16,680 | $22,000 | $18,011 | $10,000 |
| 79 | Mainline video inspection (0415-0100000F) | LF | 75 | $30.00 | $48.00 | $49.00 | $20.00 | $45.36 | $20.00 |
| 80 | Flaggers (0223-0168000T) | HR | 490 | $92.00 | $74.00 | $92.00 | $82.00 | $89.64 | $69.00 |
| 81 | Reinforced concrete pavement repair (0758-0202000J) | SY | 15 | $511.00 | $1,025.00 | $610.00 | $450.00 | $186.84 | $750.00 |
| 82 | Traffic signal modification, US395 at SE 4TH ST (0990-0106000A) | EACH | 1 | $11,000 | $12,000 | $9,675.00 | $12,000 | $12,823 | $50,000 |
| 83 | Temporary barricades, type III (0224-0105000E) | EACH | 16 | $100.00 | $190.00 | $74.00 | $75.00 | $81.00 | $195.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.
Every contract let that day: ODOT letting of February 6, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.