ODOT contract 15585 bid tabulation
Jackson county curb ramps, phase 2. Let by Oregon DOT on February 20, 2025, Region 3. 4 bids received.
- Owner
- Oregon DOT
- Letting
- 20 FEB 2025
- Pay items
- 109
- Data through
- 13 AUG 2026
Bidders
| Rank | Total bid | Against the low bid |
|---|---|---|
| 1 | Low | |
| 2 | ||
| 3 | ||
| 4 |
Bid tabulation
| Line | Pay item | Unit | Quantity | Rank 1 | Rank 2 | Rank 3 | Rank 4 |
|---|---|---|---|---|---|---|---|
| 1 | BI-directional yellow type iar markers (0855-0103100E) | EACH | 15 | $35.00 | $35.00 | $41.00 | $75.00 |
| 2 | Sediment barrier, type 8 (0280-0115080F) | LF | 60 | $10.00 | $20.00 | $50.00 | $20.00 |
| 3 | Soil sample collection and analytical testing (0294-0700000E) | EACH | 2 | $4,000.00 | $3,000.00 | $1,170.00 | $5,000.00 |
| 4 | Thermoplastic, sprayed, surface, non-profiled (0865-0119600F) | LF | 5,218 | $5.75 | $5.75 | $6.80 | $6.00 |
| 5 | Mainline video inspection (0415-0100000F) | LF | 216 | $40.00 | $27.00 | $60.00 | $40.00 |
| 6 | Signs, standard sheeting, sheet aluminum (0940-0202000J) | SF | 38 | $28.00 | $28.00 | $65.00 | $50.00 |
| 7 | Crosswalk closure supports (0902-0101000E) | EACH | 8 | $1,250.00 | $1,250.00 | $1,790.00 | $1,500.00 |
| 8 | Minor correction of preexisting ramps (1999-9Z90000J) | SF | 22.60 | $100.00 | $270.00 | $140.00 | $600.00 |
| 9 | Remove existing signs (0905-0100000A) | LS | 1 | $450.00 | $450.00 | $600.00 | $500.00 |
| 10 | Traffic signal modification, crater lake hwy at biddle RD MP 0.81 (0990-0102000A) | EACH | 1 | $55,000 | $50,000 | $84,380 | $55,000 |
| 11 | Inlet protection, type 10 (0280-0114100E) | EACH | 6 | $200.00 | $130.00 | $140.00 | $120.00 |
| 12 | Concrete inlets, type CG-3 (0470-0309000E) | EACH | 2 | $5,000.00 | $5,000.00 | $2,600.00 | $5,000.00 |
| 13 | Temporary curb ramp, parallel (0228-0167670E) | EACH | 8 | $500.00 | $350.00 | $4,900.00 | $2,600.00 |
| 14 | General structural concrete, class 3300 (0540-0301000A) | CY | 115 | $782.61 | $695.65 | $1,078.26 | $852.17 |
| 15 | Temporary plastic drums (0224-0145000E) | EACH | 362 | $40.00 | $50.00 | $75.00 | $40.00 |
| 16 | Concrete walks (0759-0128000J) | SF | 27,504 | $12.00 | $12.50 | $12.00 | $17.00 |
| 17 | Loose riprap, class 50 (0390-0105000K) | CY | 3 | $500.00 | $500.00 | $480.00 | $450.00 |
| 18 | Concrete curbs, retaining curb (0759-0108000F) | LF | 71 | $85.00 | $58.00 | $46.00 | $200.00 |
| 19 | Sign support footings (0920-0100000A) | CY | 1.17 | $3,632.48 | $4,273.50 | $6,666.67 | $12,821 |
| 20 | Truncated domes on new surfaces (0759-0510000J) | SF | 1,525 | $40.00 | $57.00 | $35.00 | $48.00 |
| 21 | 12 inch storm sewer pipe, 5 FT depth (0445-035012AF) | LF | 177 | $225.00 | $120.00 | $160.00 | $280.00 |
| 22 | Temporary removable tape (0225-0150000F) | LF | 5,520 | $3.00 | $3.00 | $3.50 | $3.00 |
| 23 | Concrete curbs, low profile mountable curb (0759-0106000F) | LF | 57 | $46.00 | $44.00 | $38.00 | $115.00 |
| 24 | Traffic signal modification, rogue valley hwy at W jackson RD/S valley view RD (0990-0102000A) | EACH | 1 | $20,000 | $20,000 | $33,480 | $20,000 |
| 25 | Monitoring report (0290-0300000A) | LS | 1 | $1,000.00 | $26,000 | $5,500.00 | $6,000.00 |
| 26 | Contaminated soil disposal (0294-0200010M) | TON | 863.50 | $55.00 | $90.00 | $70.00 | $90.00 |
| 27 | Adjusting boxes (0490-0100000E) | EACH | 12 | $650.00 | $250.00 | $115.00 | $900.00 |
| 28 | Traffic signal modification, lake of the woods hwy at antelope RD (0990-0102000A) | EACH | 1 | $165,000 | $150,000 | $134,460 | $145,000 |
| 29 | CL-6R chain link fence (1050-0135000F) | LF | 124 | $105.00 | $145.00 | $170.00 | $185.00 |
| 30 | Concrete stairs (0759-0150000K) | CY | 1 | $1,900.00 | $6,000.00 | $5,000.00 | $2,500.00 |
| 31 | Pavement legend, type B-HS: bicycle lane stencil (0867-0131000E) | EACH | 6 | $415.00 | $410.00 | $490.00 | $450.00 |
| 32 | Traffic signal modification, crater lake hwy at biddle RD MP 0.44 (0990-0102000A) | EACH | 1 | $80,000 | $70,000 | $91,000 | $75,000 |
| 33 | Clearing and grubbing (0320-0100000A) | ACRE | 1 | $2,500.00 | $20,000 | $75,000 | $15,000 |
| 34 | Wood sign posts (0910-0100000K) | FBM | 228 | $18.00 | $18.00 | $42.00 | $30.00 |
| 35 | Inlet protection, type 3 (0280-0114030E) | EACH | 39 | $150.00 | $120.00 | $90.00 | $110.00 |
| 36 | Remove and reinstall unit masonry landscape walls (1999-9Z90000A) | LS | 1 | $6,500.00 | $5,000.00 | $9,500.00 | $3,341.00 |
| 37 | Switching, conduit, and wiring (0970-0105000A) | LF | 490 | $3.06 | $10.20 | $9.18 | $12.24 |
| 38 | Temporary barricades, type II (0224-0104000E) | EACH | 40 | $60.00 | $60.00 | $80.00 | $90.00 |
| 39 | Lead compliance plan (0294-0500000A) | LS | 1 | $500.00 | $2,000.00 | $2,000.00 | $6,000.00 |
| 40 | Concrete inlets, type G-2 (0470-0315000E) | EACH | 3 | $6,000.00 | $5,000.00 | $2,300.00 | $4,800.00 |
| 41 | Pollution control plan (0290-0100000A) | LS | 1 | $500.00 | $5,000.00 | $3,000.00 | $6,000.00 |
| 42 | Temporary signs (0222-0102000J) | SF | 3,598 | $23.00 | $23.00 | $40.00 | $11.00 |
| 43 | Pavement bar, type B-HS (0867-0145100J) | SF | 6,183 | $14.50 | $14.60 | $17.40 | $16.00 |
| 44 | Temporary barricades, type III (0224-0105000E) | EACH | 47 | $150.00 | $185.00 | $250.00 | $90.00 |
| 45 | Asphalt pavement sawcutting (0310-0119000F) | LF | 5,074 | $4.00 | $3.50 | $4.00 | $8.00 |
| 46 | Removal of surfacings for curb ramp construction (0310-0106101J) | SY | 6,153 | $8.50 | $30.00 | $48.00 | $45.00 |
| 47 | Sediment fence (0280-0113000F) | LF | 251 | $7.00 | $5.00 | $40.00 | $8.00 |
| 48 | Traffic signal modification, rogue valley hwy at helman ST (0990-0102000A) | EACH | 1 | $40,000 | $40,000 | $56,770 | $45,000 |
| 49 | Pole foundations (0970-0100000A) | EACH | 2 | $2,500.00 | $2,500.00 | $1,400.00 | $2,250.00 |
| 50 | Perforated steel square tube anchor sign supports (0930-0117000A) | LB | 291 | $9.62 | $10.31 | $12.37 | $10.31 |
| 51 | Temporary pavement legends (0225-0153100E) | EACH | 2 | $140.00 | $140.00 | $200.00 | $250.00 |
| 52 | Bark mulch (1040-0190000K) | CY | 15 | $400.00 | $155.00 | $180.00 | $250.00 |
| 53 | Pedestrian channelizing devices (0228-0141600F) | LF | 1,620 | $7.50 | $25.00 | $29.00 | $25.00 |
| 54 | Permanent surface mounted tubular markers (0856-0101000E) | EACH | 10 | $250.00 | $191.00 | $290.00 | $320.00 |
| 55 | Aggregate base (0640-0100000M) | TON | 2,486 | $25.00 | $65.00 | $68.00 | $78.00 |
| 56 | Extra for new curb ramps (0759-0154100E) | EACH | 113 | $850.00 | $1,500.00 | $940.00 | $1,200.00 |
| 57 | Inlet protection, type 11 (0280-0114110E) | EACH | 16 | $150.00 | $150.00 | $90.00 | $125.00 |
| 58 | Concrete inlets, type CG-2 (0470-0307000E) | EACH | 1 | $6,000.00 | $6,000.00 | $2,600.00 | $4,800.00 |
| 59 | Level 3, 1/2 inch ACP mixture (0744-0302000M) | TON | 822 | $240.00 | $250.00 | $380.00 | $295.00 |
| 60 | Bar removal (0225-0156000J) | SF | 5,863 | $5.30 | $5.30 | $6.20 | $10.00 |
| 61 | Temporary walks (0228-0167680J) | SF | 4,685 | $1.85 | $9.00 | $11.00 | $7.00 |
| 62 | Inlet protection, type 7 (0280-0114070E) | EACH | 20 | $160.00 | $260.00 | $90.00 | $100.00 |
| 63 | Adjusting inlets (0490-0105000E) | EACH | 24 | $1,800.00 | $1,300.00 | $470.00 | $1,300.00 |
| 64 | Flagger station lighting (0223-0168100E) | EACH | 5 | $250.00 | $60.00 | $2,100.00 | $3,000.00 |
| 65 | Remove and reinstall existing signs (0905-0101000A) | LS | 1 | $1,500.00 | $1,500.00 | $9,300.00 | $6,000.00 |
| 66 | Refurbishing and reinstalling existing illumination systems (0970-0106000A) | LS | 1 | $5,000.00 | $5,000.00 | $4,288.00 | $5,000.00 |
| 67 | Perforated steel square tube slip base sign supports (0930-0114000A) | LB | 317 | $17.35 | $18.93 | $31.55 | $15.77 |
| 68 | Traffic signal modification, pacific hwy SB ramps at E pine ST (0990-0102000A) | EACH | 1 | $27,500 | $30,000 | $42,000 | $33,000 |
| 69 | Traffic signal modification, pacific hwy ramps at garfield ST/highland DR (0990-0102000A) | EACH | 1 | $35,000 | $30,000 | $87,110 | $45,000 |
| 70 | Pavement legend, type B-HS: arrows (0867-0103100E) | EACH | 34 | $400.00 | $395.00 | $470.00 | $425.00 |
| 71 | Concrete driveways (0759-0126000J) | SF | 187 | $26.00 | $33.00 | $20.00 | $32.00 |
| 72 | 17 inch asphalt concrete pavement repair (0748-0110000J) | SY | 132 | $150.00 | $70.00 | $55.00 | $323.00 |
| 73 | Portable changeable message signs (0222-0164000E) | EACH | 2 | $10,000 | $9,500.00 | $21,000 | $4,500.00 |
| 74 | Removal of structures and obstructions (0310-0106000A) | LS | 1 | $100,000 | $15,000 | $85,000 | $100,000 |
| 75 | Concrete storm sewer manholes (0470-0101000E) | EACH | 2 | $8,000.00 | $10,000 | $8,500.00 | $9,888.00 |
| 76 | Concrete inlets, type G-1 (0470-0313000E) | EACH | 1 | $5,500.00 | $6,000.00 | $2,200.00 | $4,800.00 |
| 77 | Concrete curbs, curb and gutter, modified (0759-0105000F) | LF | 3,414 | $40.00 | $43.00 | $53.00 | $82.00 |
| 78 | Drainage geotextile, type 1 (0350-0100000J) | SY | 220 | $6.00 | $2.50 | $30.00 | $9.00 |
| 79 | Traffic signal modification, rogue valley hwy at pioneer ST (0990-0102000A) | EACH | 1 | $52,500 | $50,000 | $65,510 | $48,000 |
| 80 | Removal of curbs (0310-0101000F) | LF | 16 | $300.00 | $80.00 | $80.00 | $70.00 |
| 81 | Segregate and stockpile contaminated soil (0294-0600000A) | LS | 1 | $5,000.00 | $15,000 | $20,000 | $30,000 |
| 82 | Traffic signal modification, rogue valley hwy at maple ST (0990-0102000A) | EACH | 1 | $72,500 | $70,000 | $86,670 | $70,000 |
| 83 | Rock mulch (1040-0196000M) | TON | 19 | $400.00 | $155.00 | $180.00 | $250.00 |
| 84 | 8 inch storm sewer pipe, 5 FT depth (0445-035008AF) | LF | 39 | $350.00 | $140.00 | $180.00 | $240.00 |
| 85 | Traffic signal modification, rogue valley hwy at garfield ST (0990-0102000A) | EACH | 1 | $72,500 | $70,000 | $101,870 | $66,000 |
| 86 | Retaining wall, cast-in-place concrete rigid gravity (0596-C002000A) | SF | 271 | $221.40 | $110.70 | $137.27 | $184.30 |
| 87 | Concrete curbs, standard curb (0759-0110000F) | LF | 1,789 | $35.00 | $35.00 | $37.00 | $79.00 |
| 88 | Flaggers (0223-0168000T) | HR | 2,600 | $53.00 | $77.00 | $77.00 | $87.00 |
| 89 | Traffic signal modification, garfield ST at center DR (0990-0102000A) | EACH | 1 | $45,000 | $50,000 | $84,980 | $55,000 |
| 90 | Contrast pavement bar, type B-HS (1999-9Z90000J) | SF | 117.50 | $21.00 | $21.00 | $25.00 | $26.00 |
| 91 | Lawn seeding (1030-0138000J) | SY | 105 | $50.00 | $38.00 | $40.00 | $68.00 |
| 92 | Concrete islands (0759-0122000J) | SF | 1,822 | $23.00 | $17.00 | $20.00 | $30.00 |
| 93 | Connection to existing structures (0490-0104000E) | EACH | 5 | $1,500.00 | $1,200.00 | $350.00 | $2,800.00 |
| 94 | Health and safety plan (0294-0100000A) | LS | 1 | $500.00 | $2,000.00 | $3,000.00 | $5,000.00 |
| 95 | Stripe removal (0225-0154000F) | LF | 5,575 | $0.75 | $0.75 | $0.90 | $3.00 |
| 96 | Concrete washout facility (0280-0112500E) | EACH | 19 | $100.00 | $1,000.00 | $940.00 | $600.00 |
| 97 | Temporary traffic signal, ________ (0227-0158000A) | LS | 1 | $60,000 | $176,913 | $22,000 | $95,000 |
| 98 | Bridge removal work (0501-0100000A) | SF | 4,791 | $8.35 | $20.87 | $5.22 | $10.85 |
| 99 | 14 inch wide contrast striping (1999-9Z90000F) | LF | 8 | $45.00 | $45.00 | $54.00 | $95.00 |
| 100 | Coated reinforcement, grade 60 (0530-0104100A) | LB | 8,680 | $4.03 | $3.46 | $3.32 | $2.88 |
| 101 | Traffic control supervisor (0223-0169000E) | EACH | 261 | $100.00 | $600.00 | $750.00 | $550.00 |
| 102 | Traffic signal modification, rogue valley hwy at W valley view RD (0990-0102000A) | EACH | 1 | $60,000 | $60,000 | $82,620 | $77,000 |
| 103 | Temporary pavement bars (0225-0153200J) | SF | 180 | $6.75 | $6.75 | $8.00 | $11.00 |
| 104 | Legend removal (0225-0155100J) | SF | 1,280 | $3.50 | $3.50 | $4.10 | $10.00 |
| 105 | Grouted durable rock (1999-9Z90000J) | SF | 59 | $32.00 | $70.00 | $180.00 | $88.00 |
| 106 | Traffic signal modification, rogue valley hwy at 2ND ST (0990-0102000A) | EACH | 1 | $55,000 | $50,000 | $79,890 | $50,000 |
| 107 | Minor adjustment of manholes (0490-0120000E) | EACH | 7 | $1,800.00 | $1,000.00 | $640.00 | $1,888.00 |
| 108 | Asphalt slope paving (0749-0116000J) | SF | 303 | $5.00 | $15.00 | $31.00 | $40.00 |
| 109 | Sequential arrow signs (0222-0162000E) | EACH | 6 | $1,500.00 | $4,500.00 | $3,800.00 | $1,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.
Every contract let that day: ODOT letting of February 20, 2025. Compiled by Mirage Metrics.