ODOT contract 15596 bid tabulation

North powder/richland/halfway curb ramps. Let by Oregon DOT on April 17, 2025, Region 5. 6 bids received.

Owner
Oregon DOT
Letting
17 APR 2025
Pay items
76
Data through
13 AUG 2026

Bidders

RankTotal bidAgainst the low bid
1Low
2
3
4
5
6
ODOT contract 15596: bids by rank

Bid tabulation

LinePay itemUnitQuantityRank 1Rank 2Rank 3Rank 4Rank 5Rank 6
1Longitudinal pavement markings - paint (0860-0200000F)LF1,978$5.00$2.50$2.25$2.00$4.00$2.00
2Metal handrail, 3 rails (1069-0100000F)LF16$550.00$350.00$450.00$375.00$700.00$300.00
3Wood sign posts (0910-0100000K)FBM54$5.00$25.00$96.00$35.00$42.00$16.00
4Perforated steel square tube slip base sign supports (0930-0114000A)LB1,720$22.33$18.60$6.58$20.35$20.35$17.44
5Inlet protection, type 4 (0280-0114040E)EACH1$125.00$100.00$177.00$140.00$150.00$50.00
6Crosswalk closure supports (0902-0101000E)EACH3$1,800.00$1,500.00$2,260.00$1,600.00$2,000.00$2,000.00
7Concrete inlets, type G-2 (0470-0315000E)EACH36$4,500.00$2,550.00$4,400.00$5,200.00$3,500.00$7,000.00
8Temporary barricades, type III (0224-0105000E)EACH182$85.00$125.00$82.00$190.00$90.00$15.00
9Stripe removal (0225-0154000F)LF1,412$1.95$3.50$2.00$3.00$9.00$0.75
1016 foot X 48 inch chain link double gates (1050-0208000E)EACH1$6,500.00$5,700.00$5,570.00$6,000.00$6,000.00$3,000.00
11Flaggers (0223-0168000T)HR3,840$0.01$86.00$75.00$1.00$80.00$0.01
12Adjusting inlets (0490-0105000E)EACH16$525.00$2,100.00$1,200.00$1,300.00$1,000.00$500.00
1318 inch storm sewer pipe, 5 FT depth (0445-035018AF)LF26$192.00$341.00$510.00$700.00$360.00$175.00
14Lead compliance plan (0294-0500000A)LS1$5,000.00$2,500.00$2,500.00$2,000.00$1,500.00$2,000.00
15Contaminated groundwater removal (0294-0400000P)GAL2,000$1.00$11.05$13.00$1.75$10.00$0.50
1612 inch HDPE pipe, 5 FT depth (0445-055012AF)LF6$185.00$220.00$650.00$850.00$345.00$150.00
17Weed control geotextile (1040-0208000J)SF636$3.00$2.50$1.75$2.15$4.00$1.00
18Remove existing signs (0905-0100000A)LS1$24,000$10,000$5,660.00$15,000$2,500.00$4,000.00
19Minor adjustment of manholes (0490-0120000E)EACH5$700.00$500.00$1,580.00$1,500.00$1,500.00$1,500.00
20Refurbishing and reinstalling existing illumination systems (0970-0106000A)LS1$20,900$20,530$15,940$75,000$15,000$17,000
21Concrete driveways (0759-0126000J)SF425$17.43$16.60$22.00$16.60$26.00$20.00
22Pavement bar, type B-HS (0867-0145100J)SF1,693$22.00$16.50$21.00$18.85$23.00$18.85
23Concrete manholes, with inlet (0470-0103000E)EACH2$7,500.00$4,676.00$10,240$13,000$9,500.00$14,000
24Soil conditioner (1040-0107000K)CY1$3,500.00$200.00$1,640.00$1,000.00$500.00$1,000.00
25Contaminated groundwater mobilization (0294-0300000A)LS1$2,000.00$2,600.00$8,830.00$2,250.00$2,000.00$100.00
26Sediment fence (0280-0113000F)LF40$42.00$5.00$39.00$5.25$22.00$12.00
27Special ADA concrete curb (0759-0103000F)LF4,807$73.50$73.00$75.00$70.00$84.00$85.00
28Asphalt pavement sawcutting (0310-0119000F)LF5,927$45.00$5.00$8.00$10.00$6.00$10.00
29Inlet protection, type 11 (0280-0114110E)EACH34$115.00$100.00$148.00$175.00$90.00$50.00
30Temporary barricades, type II (0224-0104000E)EACH100$65.00$100.00$41.00$78.00$80.00$15.00
31Temporary plastic drums (0224-0145000E)EACH118$49.00$50.00$41.00$45.00$80.00$10.00
32Temporary pavement bars (0225-0153200J)SF1,350$5.25$3.50$6.00$5.00$7.00$1.50
33Adjusting boxes (0490-0100000E)EACH26$450.00$500.00$470.00$750.00$600.00$150.00
34Remove and reinstall existing signs (0905-0101000A)LS1$35,600$1,000.00$8,490.00$15,000$500.00$7,000.00
35Rock mulch (1040-0192000K)CY12$450.00$150.00$450.00$300.00$250.00$250.00
36Type CL-4R chain link fence (1050-0135000F)LF13$250.00$200.00$230.00$205.00$250.00$150.00
37Signs, standard sheeting, plywood (0940-0203000J)SF591$12.00$40.00$62.00$30.00$55.00$26.00
38Contaminated soil disposal (0294-0200010M)TON1,042$1.00$92.50$82.00$35.00$85.00$0.01
39Connection to existing structures (0490-0104000E)EACH37$1,100.00$500.00$780.00$1,450.00$1,500.00$100.00
40Topsoil (1040-0101000K)CY1$850.00$200.00$1,640.00$1,000.00$500.00$1,000.00
41Pedestrian channelizing devices (0228-0141600F)LF1,540$22.50$30.00$19.00$8.00$28.00$10.00
42Switching, conduit, and wiring (0970-0105000A)LF57$281.54$408.86$425.61$1,315.79$403.51$438.60
43Removing and rebuilding fence (1050-0240000F)LF43$200.00$65.00$220.00$135.00$250.00$100.00
44Truncated domes on new surfaces (0759-0510000J)SF1,794$23.10$27.00$43.00$22.00$62.00$25.00
45Temporary walks (0228-0167680J)SF30$11.50$10.00$24.00$45.00$50.00$50.00
4612 inch ductile iron pipe, 5 FT depth (0445-060012AF)LF140$185.00$276.88$400.00$450.00$385.00$170.00
47Pole foundations (0970-0100000A)EACH8$150.00$3,166.25$3,018.75$9,375.00$2,875.00$3,125.00
48Temporary curb ramp, parallel (0228-0167670E)EACH4$1,550.00$1,200.00$1,290.00$1,200.00$1,500.00$2,000.00
49Legend removal (0225-0155100J)SF3$262.50$3.00$280.00$250.00$500.00$100.00
50Portable changeable message signs (0222-0164000E)EACH3$7,500.00$6,500.00$5,290.00$7,500.00$2,300.00$15,000
51Hydrant extensions (1160-0105000E)EACH2$2,500.00$4,500.00$2,820.00$6,500.00$15,000$4,000.00
52Pollution control plan (0290-0100000A)LS1$2,200.00$1,000.00$1,500.00$1,000.00$1,500.00$3,000.00
53Soil sample collection and analytical testing (0294-0700000E)EACH3$1,500.00$1,650.00$1,870.00$3,000.00$5,000.00$2,700.00
54Health and safety plan (0294-0100000A)LS1$2,500.00$3,500.00$2,500.00$2,000.00$8,000.00$3,000.00
55Sign support footings (0920-0100000A)CY3.40$2.94$6,470.59$4,994.12$10,294$11,471$4,705.88
56Removal of surfacings for curb ramp construction (0310-0106101J)SY6,369$42.00$40.00$55.00$62.00$36.00$135.00
57Mainline video inspection (0415-0100000F)LF1,636$38.00$12.00$14.00$6.00$18.00$0.01
58Clearing and grubbing (0320-0100000A)ACRE1$4,500.00$2,500.00$7,580.00$25,000$10,000$2,000.00
59Remove and reinstall pavers (0760-0100000J)SF13$125.00$25.00$167.00$60.00$100.00$200.00
60Sod lawn (1040-0189000J)SY8$150.00$50.00$310.00$165.00$300.00$200.00
61Inlet protection, type 10 (0280-0114100E)EACH2$95.00$100.00$113.00$125.00$100.00$50.00
62Removal of structures and obstructions (0310-0106000A)LS1$25,000$350,000$15,720$55,000$75,000$310,000
6312 inch storm sewer pipe, 5 FT depth (0445-035012AF)LF192$170.00$220.00$390.00$650.00$360.00$150.00
64Aggregate base (0640-0100000M)TON3,077$0.01$41.07$98.00$34.50$90.00$20.00
65Commercial asphalt concrete pavement (0740-0100000M)TON692$350.00$237.90$400.00$385.00$465.00$460.00
66Temporary removable tape (0225-0150000F)LF2,640$5.77$2.50$2.25$5.50$6.00$1.50
67Extra for new curb ramps (0759-0154100E)EACH148$997.00$1,450.00$810.00$950.00$900.00$800.00
68Concrete storm sewer manholes (0470-0101000E)EACH1$6,500.00$3,450.00$7,710.00$12,500$9,500.00$12,000
69Concrete walks (0759-0128000J)SF33,075$16.38$17.10$14.00$15.60$17.00$22.00
70Concrete inlets, type CG-3 (0470-0309000E)EACH1$4,500.00$3,275.00$4,310.00$4,500.00$4,300.00$7,000.00
71Concrete inlets, type CG-2 (0470-0307000E)EACH2$5,200.00$2,800.00$4,590.00$5,600.00$4,000.00$7,000.00
72Segregate and stockpile contaminated soil (0294-0600000A)LS1$2,500.00$7,200.00$37,760$50,000$60,000$500.00
73Inlet protection, type 3 (0280-0114030E)EACH55$78.00$100.00$106.00$175.00$90.00$50.00
74Bar removal (0225-0156000J)SF1,676$8.92$5.00$10.00$8.50$11.00$3.00
75Concrete stairs (0759-0150000K)CY1$1,575.00$1,500.00$3,480.00$1,500.00$3,000.00$4,000.00
76Temporary signs (0222-0102000J)SF2,635$13.50$35.00$8.00$26.00$16.00$12.00
ODOT contract 15596: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.

Every contract let that day: ODOT letting of April 17, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy