ODOT contract 15603 bid tabulation
Or8: canyon rd pedestrian enhancements. Let by Oregon DOT on June 5, 2025, Region 1. 4 bids received.
- Owner
- Oregon DOT
- Letting
- 05 JUN 2025
- Pay items
- 88
- Data through
- 13 AUG 2026
Bidders
| Rank | Total bid | Against the low bid |
|---|---|---|
| 1 | Low | |
| 2 | ||
| 3 | ||
| 4 |
Bid tabulation
| Line | Pay item | Unit | Quantity | Rank 1 | Rank 2 | Rank 3 | Rank 4 |
|---|---|---|---|---|---|---|---|
| 1 | Shrubs, #2 container (1040-0154000E) | EACH | 210 | $22.00 | $10.00 | $10.00 | $21.00 |
| 2 | Temporary impact attenuator, truck mounted (0226-0138000E) | EACH | 1 | $12,000 | $15,000 | $12,500 | $10,980 |
| 3 | Removal of pipes (0310-0100000F) | LF | 38 | $90.00 | $30.00 | $128.50 | $69.00 |
| 4 | Removal of surfacings (0310-0103000J) | SY | 510 | $15.00 | $3.00 | $53.00 | $42.00 |
| 5 | Concrete islands (0759-0122000J) | SF | 1,400 | $28.00 | $12.00 | $25.00 | $36.00 |
| 6 | Traffic control supervisor (0223-0169000E) | EACH | 70 | $750.00 | $800.00 | $300.00 | $1,155.00 |
| 7 | Temporary walks (0228-0167680J) | SF | 60 | $30.00 | $70.00 | $24.00 | $6.10 |
| 8 | Contaminated groundwater mobilization (0294-0300000A) | LS | 1 | $1,500.00 | $500.00 | $1,200.00 | $100.00 |
| 9 | Extra for manholes over existing sewers (0490-0123000E) | EACH | 2 | $2,200.00 | $500.00 | $3,250.00 | $8,600.00 |
| 10 | Concrete curbs, curb and gutter (0759-0103000F) | LF | 180 | $85.00 | $50.00 | $86.00 | $67.00 |
| 11 | Soil testing (1040-0100000E) | EACH | 1 | $1,200.00 | $150.00 | $160.00 | $110.00 |
| 12 | Temporary pavement legends (0225-0153100E) | EACH | 1 | $300.00 | $600.00 | $270.00 | $750.00 |
| 13 | Concrete inlets, type G-2 (0470-0315000E) | EACH | 3 | $5,000.00 | $6,000.00 | $3,700.00 | $6,750.00 |
| 14 | Cold plane pavement removal, 2 inches deep (0620-0120000J) | SY | 580 | $22.00 | $20.00 | $34.00 | $23.25 |
| 15 | Pavement legend, type B-HS: railroad crossing (0867-0119200E) | EACH | 2 | $1,500.00 | $2,000.00 | $2,100.00 | $2,415.00 |
| 16 | Bulbs (1040-0176000E) | EACH | 240 | $18.00 | $4.00 | $4.50 | $13.00 |
| 17 | Contaminated groundwater removal (0294-0400000P) | GAL | 55 | $15.00 | $50.00 | $10.00 | $10.00 |
| 18 | Truncated domes on new surfaces (0759-0510000J) | SF | 130 | $45.00 | $30.00 | $39.00 | $39.00 |
| 19 | Subgrade geotextile (0350-0105000J) | SY | 130 | $8.00 | $10.00 | $1.60 | $5.50 |
| 20 | Straw bale (0280-0119000E) | EACH | 1 | $250.00 | $250.00 | $60.00 | $50.00 |
| 21 | Legend removal (0225-0155100J) | SF | 210 | $12.00 | $10.00 | $9.00 | $10.40 |
| 22 | Sequential arrow signs (0222-0162000E) | EACH | 4 | $1,100.00 | $1,200.00 | $2,000.00 | $550.00 |
| 23 | Temporary plastic drums (0224-0145000E) | EACH | 60 | $70.00 | $75.00 | $35.00 | $48.00 |
| 24 | Contaminated soil disposal (0294-0200010M) | TON | 35 | $200.00 | $125.00 | $116.00 | $115.20 |
| 25 | Capping existing concrete structures (0490-0125000E) | EACH | 1 | $1,500.00 | $3,000.00 | $1,900.00 | $8,500.00 |
| 26 | Perforated steel square tube anchor sign supports (0930-0117000A) | LB | 400 | $5.00 | $12.50 | $8.88 | $10.07 |
| 27 | Lighting poles and arms (0970-0200000A) | EACH | 6 | $10,000 | $10,833 | $9,879.17 | $11,183 |
| 28 | Deciduous trees, 3.5 inch caliper (1040-0134000E) | EACH | 12 | $680.00 | $230.00 | $242.00 | $700.00 |
| 29 | Flagger station lighting (0223-0168100E) | EACH | 4 | $1,200.00 | $1,200.00 | $1,500.00 | $732.00 |
| 30 | Root barrier (1040-0206000F) | LF | 800 | $12.00 | $14.00 | $15.00 | $8.00 |
| 31 | Portable changeable message signs (0222-0164000E) | EACH | 2 | $2,500.00 | $6,000.00 | $9,000.00 | $1,600.00 |
| 32 | Switching, conduit, and wiring (0970-0105000A) | LF | 500 | $140.00 | $170.00 | $144.40 | $163.48 |
| 33 | Mainline video inspection (0415-0100000F) | LF | 37.90 | $80.00 | $20.00 | $25.00 | $51.24 |
| 34 | Remove existing signs (0905-0100000A) | LS | 1 | $200.00 | $600.00 | $108.00 | $122.00 |
| 35 | Remove and reinstall existing signs (0905-0101000A) | LS | 1 | $200.00 | $1,500.00 | $540.00 | $610.00 |
| 36 | Signs, wide angle sheeting, extruded aluminum (0940-0204100J) | SF | 75 | $55.00 | $35.00 | $49.00 | $55.00 |
| 37 | Concrete walks (0759-0128000J) | SF | 1,700 | $17.00 | $10.00 | $16.00 | $27.00 |
| 38 | Drainage curbs (0480-0100000F) | LF | 1,100 | $30.00 | $28.00 | $38.00 | $46.00 |
| 39 | Removal of surfacings for curb ramp construction (0310-0106101J) | SY | 320 | $62.00 | $25.00 | $56.00 | $65.00 |
| 40 | Inlet protection, type 11 (0280-0114110E) | EACH | 1 | $150.00 | $150.00 | $110.00 | $100.00 |
| 41 | Extra for new curb ramps (0759-0154100E) | EACH | 10 | $1,500.00 | $100.00 | $1,000.00 | $6,140.00 |
| 42 | Sediment barrier, type 3 (0280-0115030F) | LF | 100 | $8.00 | $8.00 | $6.00 | $5.00 |
| 43 | Bar removal (0225-0156000J) | SF | 50 | $2.00 | $10.00 | $9.00 | $10.40 |
| 44 | Stripe removal (0225-0154000F) | LF | 300 | $8.00 | $2.50 | $2.70 | $3.05 |
| 45 | Pole foundations (0970-0100000A) | EACH | 8 | $4,750.00 | $1,875.00 | $4,715.63 | $5,337.50 |
| 46 | Signs, standard sheeting, sheet aluminum (0940-0202000J) | SF | 85 | $45.00 | $30.00 | $41.00 | $46.40 |
| 47 | General excavation (0330-0105000K) | CY | 520 | $42.00 | $30.00 | $67.25 | $95.00 |
| 48 | Clearing and grubbing (0320-0100000A) | ACRE | 0.10 | $85,000 | $1,000.00 | $20,000 | $203,750 |
| 49 | Inlet protection, type 3 (0280-0114030E) | EACH | 15 | $75.00 | $150.00 | $65.00 | $100.00 |
| 50 | Temporary signs (0222-0102000J) | SF | 1,700 | $15.00 | $18.50 | $22.50 | $22.50 |
| 51 | Traffic signal modification, OR8 (canyon RD) at cedar hills (0990-0102000A) | EACH | 1 | $70,000 | $125,000 | $80,835 | $91,500 |
| 52 | Perforated steel square tube slip base sign supports (0930-0114000A) | LB | 200 | $10.00 | $10.00 | $12.00 | $13.73 |
| 53 | Removal of inlets (0310-0104000E) | EACH | 3 | $1,500.00 | $1,500.00 | $700.00 | $500.00 |
| 54 | Health and safety plan (0294-0100000A) | LS | 1 | $500.00 | $100.00 | $670.00 | $610.00 |
| 55 | Flaggers (0223-0168000T) | HR | 260 | $80.00 | $75.00 | $76.00 | $81.00 |
| 56 | Repair temporary impact attenuator, truck mounted (0226-0141400E) | EACH | 2 | $1.00 | $1.00 | $250.00 | $100.00 |
| 57 | Removal of structures and obstructions (0310-0106000A) | LS | 1 | $6,000.00 | $5,000.00 | $4,100.00 | $40,900 |
| 58 | BI-directional yellow type iar markers (0855-0103100E) | EACH | 60 | $14.00 | $20.00 | $9.50 | $11.00 |
| 59 | Sign support footings (0920-0100000A) | CY | 0.90 | $4,444.44 | $3,888.89 | $9,555.56 | $10,844 |
| 60 | Temporary barricades, type III (0224-0105000E) | EACH | 16 | $225.00 | $185.00 | $115.00 | $200.00 |
| 61 | Irrigation system (1120-0100000A) | LS | 1 | $32,000 | $30,000 | $35,000 | $38,540 |
| 62 | Bark mulch (1040-0190000K) | CY | 6 | $95.00 | $100.00 | $60.00 | $51.00 |
| 63 | Luminaires, lamps, and ballasts (0970-0104000A) | EACH | 6 | $750.00 | $1,666.67 | $790.33 | $894.67 |
| 64 | Temporary barricades, type II (0224-0104000E) | EACH | 18 | $201.00 | $65.00 | $55.00 | $80.00 |
| 65 | Pedestrian channelizing devices (0228-0141600F) | LF | 120 | $40.00 | $30.00 | $14.00 | $24.40 |
| 66 | Level 3, 1/2 inch ACP (0745-0302000M) | TON | 86.93 | $238.00 | $195.00 | $300.00 | $237.00 |
| 67 | Concrete curbs (0759-0100000F) | LF | 190 | $66.00 | $50.00 | $64.00 | $60.50 |
| 68 | Thermoplastic, extruded, surface, profiled (0865-0116600F) | LF | 800 | $3.50 | $3.25 | $3.25 | $4.00 |
| 69 | Curb marking, paint (0869-0200000F) | LF | 120 | $7.00 | $10.00 | $5.50 | $6.10 |
| 70 | Topsoil (1040-0101000K) | CY | 360 | $50.00 | $45.00 | $47.00 | $42.70 |
| 71 | Compost mulch (1040-0194000K) | CY | 54.20 | $55.00 | $55.00 | $60.00 | $50.00 |
| 72 | Flashing beacon installation, OR8 (canyon RD) at rose biggi (0990-0106000A) | EACH | 1 | $66,000 | $90,000 | $69,000 | $78,080 |
| 73 | Shrubs, #1 container (1040-0153000E) | EACH | 990 | $16.00 | $6.00 | $6.50 | $13.00 |
| 74 | Concrete inlets, type CG-2 (0470-0307000E) | EACH | 1 | $5,000.00 | $6,500.00 | $3,800.00 | $7,990.00 |
| 75 | 12 inch ductile iron pipe, 5 FT depth (0445-060012AF) | LF | 38 | $225.00 | $200.00 | $400.00 | $250.00 |
| 76 | Temporary flexible pavement markers (0225-0149000E) | EACH | 60 | $30.00 | $10.00 | $4.00 | $6.10 |
| 77 | Temporary curb ramp, parallel (0228-0167670E) | EACH | 3 | $1,200.00 | $2,000.00 | $400.00 | $4,453.00 |
| 78 | Trench resurfacing (0495-0100000J) | SY | 17.20 | $275.00 | $300.00 | $400.00 | $465.00 |
| 79 | PG 70-22ER asphalt in 1/2 inch ACP (0745-0640100M) | TON | 5.22 | $500.00 | $531.00 | $575.00 | $650.00 |
| 80 | Pavement bar, type B-HS (0867-0145100J) | SF | 710 | $22.00 | $16.75 | $18.00 | $20.50 |
| 81 | Deciduous trees, 2.5 inch caliper (1040-0132000E) | EACH | 6 | $485.00 | $200.00 | $183.00 | $465.00 |
| 82 | Aggregate base (0641-0102000M) | TON | 130 | $100.00 | $45.00 | $75.00 | $70.00 |
| 83 | Asphalt pavement sawcutting, 8 inches deep (0310-0119100F) | LF | 2,200 | $3.00 | $5.00 | $3.25 | $2.44 |
| 84 | Pollution control plan (0290-0100000A) | LS | 1 | $500.00 | $100.00 | $670.00 | $305.00 |
| 85 | Connection to existing structures (0490-0104000E) | EACH | 3 | $1,500.00 | $1,000.00 | $1,290.00 | $3,220.00 |
| 86 | Crosswalk closure supports (0902-0101000E) | EACH | 5 | $1,500.00 | $1,350.00 | $1,600.00 | $1,830.00 |
| 87 | Mono-directional white type iar markers (0855-0101100E) | EACH | 20 | $22.00 | $25.00 | $9.50 | $11.00 |
| 88 | Signal pole mounts (0930-0107000A) | LB | 710 | $21.13 | $21.13 | $29.93 | $33.85 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.
Every contract let that day: ODOT letting of June 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.