ODOT contract 15654 bid tabulation
Highway barrier upgrades (coos/curry). Let by Oregon DOT on April 2, 2026, Region 3. 4 bids received.
- Owner
- Oregon DOT
- Letting
- 02 APR 2026
- Pay items
- 38
- Data through
- 13 AUG 2026
Bidders
| Rank | Total bid | Against the low bid |
|---|---|---|
| 1 | Low | |
| 2 | ||
| 3 | ||
| 4 |
Bid tabulation
| Line | Pay item | Unit | Quantity | Rank 1 | Rank 2 | Rank 3 | Rank 4 |
|---|---|---|---|---|---|---|---|
| 1 | Removal of guardrail (0310-0113000A) | LF | 21,216 | $3.54 | $2.38 | $5.00 | $3.21 |
| 2 | Midwest guardrail system, type 4 (0810-0146100F) | LF | 137.50 | $185.00 | $60.00 | $70.00 | $37.00 |
| 3 | Temporary barricades, type II (0224-0104000E) | EACH | 2 | $80.00 | $75.00 | $70.00 | $100.00 |
| 4 | Extra for hand dug guardrail post holes (0810-0145000E) | EACH | 100 | $175.00 | $200.00 | $100.00 | $210.00 |
| 5 | Guardrail terminals, non-flared, test level 2 (0810-0131000E) | EACH | 1 | $3,600.00 | $3,000.00 | $3,275.00 | $3,400.00 |
| 6 | Milepost marker posts (0840-0106000E) | EACH | 6 | $260.00 | $450.00 | $200.00 | $210.00 |
| 7 | Guardrail anchors, type 1 (0810-0119000E) | EACH | 19 | $1,175.00 | $1,310.00 | $1,450.00 | $1,700.00 |
| 8 | Guardrail terminals, buried in backslope (0810-0132100E) | EACH | 6 | $11,250 | $8,130.00 | $9,000.00 | $6,800.00 |
| 9 | Automated flagger assistance device (0223-0200000E) | EACH | 2 | $7,500.00 | $16,667 | $4,553.00 | $8,000.00 |
| 10 | Bridge removal work (0501-0100000A) | SF | 125 | $28.00 | $26.00 | $16.00 | $144.00 |
| 11 | Extra for 11 foot posts (0810-0134000E) | EACH | 1,502 | $115.00 | $114.00 | $125.00 | $210.00 |
| 12 | Clearing and grubbing (0320-0100000A) | ACRE | 0.25 | $60,000 | $92,800 | $20,000 | $672,000 |
| 13 | Temporary work access and containment (0253-0106000A) | LS | 1 | $5,000.00 | $7,000.00 | $500.00 | $19,000 |
| 14 | Aggregate shoulders (0640-0101000M) | TON | 1,367 | $70.00 | $128.00 | $150.00 | $43.00 |
| 15 | Midwest guardrail system, type 3 (0810-0146100F) | LF | 125 | $56.00 | $70.00 | $80.00 | $52.00 |
| 16 | Work containment plan (0290-0102000A) | LS | 1 | $3,000.00 | $2,975.00 | $1,000.00 | $3,400.00 |
| 17 | Repair temporary impact attenuator, truck mounted (0226-0141400E) | EACH | 1 | $1,500.00 | $1.00 | $1.00 | $600.00 |
| 18 | Reconditioning existing roadway (0610-0103000A) | LS | 1 | $29,000 | $105,000 | $40,000 | $68,000 |
| 19 | Construct grading at guardrail terminals (0810-0142100E) | EACH | 67 | $650.00 | $2,630.00 | $1,500.00 | $3,670.00 |
| 20 | Sediment fence (0280-0113000F) | LF | 100 | $12.00 | $17.00 | $10.00 | $6.00 |
| 21 | Guardrail end pieces, type C (0810-0123000E) | EACH | 19 | $145.00 | $150.00 | $155.00 | $380.00 |
| 22 | Wood sign posts (0910-0100000K) | FBM | 1,398 | $15.00 | $26.00 | $13.00 | $16.00 |
| 23 | Guardrail terminals, non-flared (0810-0129000E) | EACH | 66 | $3,850.00 | $3,125.00 | $3,675.00 | $3,200.00 |
| 24 | Delineators, type 1 (0840-0100000E) | EACH | 300 | $85.00 | $63.00 | $65.00 | $75.00 |
| 25 | Remove and reinstall existing signs (0905-0101000A) | LS | 1 | $3,500.00 | $3,800.00 | $10,500 | $24,600 |
| 26 | Temporary impact attenuator, truck mounted (0226-0138000E) | EACH | 1 | $6,000.00 | $17,144 | $5,000.00 | $36,000 |
| 27 | Guardrail anchors, type 1 modified (0810-0120000E) | EACH | 12 | $825.00 | $1,120.00 | $845.00 | $1,440.00 |
| 28 | Flaggers (0223-0168000T) | HR | 1,550 | $82.00 | $97.67 | $70.00 | $81.00 |
| 29 | Guardrail transition (0810-0126000E) | EACH | 12 | $4,100.00 | $4,585.00 | $6,250.00 | $4,100.00 |
| 30 | Asphalt pavement sawcutting, 6 to 14 inches deep (0310-0119120F) | LF | 2,100 | $7.00 | $10.00 | $10.00 | $8.00 |
| 31 | Temporary plastic drums (0224-0145000E) | EACH | 112 | $5.00 | $60.00 | $20.00 | $85.00 |
| 32 | 3 tube side mount rail, modified (0587-0102000A) | LF | 125 | $516.00 | $376.80 | $296.00 | $533.60 |
| 33 | Temporary signs (0222-0102000J) | SF | 315 | $10.00 | $24.20 | $12.00 | $50.00 |
| 34 | Sediment barrier, type 3 (0280-0115030F) | LF | 50 | $20.00 | $40.00 | $7.00 | $8.00 |
| 35 | Adjusting guardrail (0812-0101000F) | LF | 3,404 | $4.25 | $4.25 | $6.00 | $4.00 |
| 36 | Obliterating surfacings (0370-0101000A) | SF | 4,028 | $5.71 | $8.86 | $5.96 | $9.43 |
| 37 | Midwest guardrail system, type 2A (0810-0146100F) | LF | 19,200 | $28.00 | $27.70 | $30.00 | $30.00 |
| 38 | Pollution control plan (0290-0100000A) | LS | 1 | $3,000.00 | $500.00 | $1,000.00 | $1,200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.
Every contract let that day: ODOT letting of April 2, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.