ODOT contract 15672 bid tabulation
Eastern oregon 2024-2027 ada curb ramps, phase 3. Let by Oregon DOT on June 11, 2026, Region 5. 6 bids received.
- Owner
- Oregon DOT
- Letting
- 11 JUN 2026
- Pay items
- 104
- Data through
- 13 AUG 2026
Bidders
| Rank | Total bid | Against the low bid |
|---|---|---|
| 1 | Low | |
| 2 | ||
| 3 | ||
| 4 | ||
| 5 | ||
| 6 |
Bid tabulation
| Line | Pay item | Unit | Quantity | Rank 1 | Rank 2 | Rank 3 | Rank 4 | Rank 5 | Rank 6 |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Temporary removable tape (0225-0150000F) | LF | 2,250 | $9.58 | $2.00 | $1.50 | $3.00 | $9.50 | $5.00 |
| 2 | Sign support footings (0920-0100000A) | CY | 7.83 | $2,298.85 | $4,469.99 | $1,915.71 | $1,945.08 | $3,192.85 | $2,043.42 |
| 3 | Salvage, stockpile and reinstall pavers (0760-0100000J) | SF | 192 | $28.33 | $25.00 | $55.00 | $52.00 | $35.00 | $21.00 |
| 4 | Aggregate base (0640-0100000M) | TON | 3,051 | $17.00 | $36.00 | $22.00 | $87.00 | $22.00 | $80.00 |
| 5 | Trench drain, type 3 (0446-0102000F) | LF | 97 | $365.65 | $280.00 | $225.00 | $430.00 | $350.00 | $600.00 |
| 6 | Temporary plastic drums (0224-0145000E) | EACH | 171 | $45.00 | $30.00 | $80.00 | $42.00 | $30.00 | $65.00 |
| 7 | Sequential arrow signs (0222-0162000E) | EACH | 1 | $3,000.00 | $3,400.00 | $6,000.00 | $4,770.00 | $4,000.00 | $4,000.00 |
| 8 | 12 inch tapping sleeve and 6 inch valve assembly (1150-0700000E) | EACH | 1 | $4,962.54 | $7,000.00 | $7,000.00 | $2,350.00 | $8,000.00 | $6,050.00 |
| 9 | Flashing beacon installation, OR7 at leo adler pathway (0990-0106000A) | EACH | 1 | $37,086 | $35,000 | $34,000 | $33,500 | $45,000 | $32,000 |
| 10 | Refurbishing and reinstalling existing illumination systems (0970-0106000A) | LS | 1 | $35,063 | $10,000 | $10,000 | $31,250 | $25,000 | $8,500.00 |
| 11 | Longitudinal pavement markings - paint (0860-0200000F) | LF | 39 | $72.10 | $95.00 | $70.00 | $70.00 | $100.00 | $30.00 |
| 12 | Historical marker installation (0759-0158000E) | EACH | 1 | $2,500.00 | $600.00 | $500.00 | $1,240.00 | $2,500.00 | $300.00 |
| 13 | Adjusting boxes (0490-0100000E) | EACH | 40 | $120.00 | $900.00 | $100.00 | $570.00 | $500.00 | $260.00 |
| 14 | Bar removal (0225-0156000J) | SF | 3,188 | $4.12 | $6.00 | $3.00 | $4.50 | $4.00 | $18.00 |
| 15 | Temporary barricades, type III (0224-0105000E) | EACH | 51 | $75.00 | $50.00 | $25.00 | $77.00 | $60.00 | $210.00 |
| 16 | Inlet protection, type 10 (0280-0114100E) | EACH | 1 | $185.00 | $140.00 | $50.00 | $181.00 | $150.00 | $110.00 |
| 17 | 12 inch storm sewer pipe, 5 FT depth (0445-035012AF) | LF | 684 | $123.60 | $150.00 | $200.00 | $230.00 | $250.00 | $185.00 |
| 18 | Cold plane pavement removal, 0 - 2 1/2 inches deep (0620-0105000J) | SY | 599 | $40.42 | $45.00 | $30.00 | $59.00 | $50.00 | $60.00 |
| 19 | Remove and reinstall existing signs (0905-0101000A) | LS | 1 | $12,000 | $8,300.00 | $5,000.00 | $4,040.00 | $5,000.00 | $4,100.00 |
| 20 | 6 inch gate valve (1150-0100000E) | EACH | 1 | $3,069.40 | $3,500.00 | $3,000.00 | $3,430.00 | $4,000.00 | $3,960.00 |
| 21 | Topsoil (1040-0101000K) | CY | 15 | $95.00 | $230.00 | $400.00 | $400.00 | $300.00 | $450.00 |
| 22 | Concrete curbs, standard curb (0759-0110000F) | LF | 204 | $53.56 | $78.00 | $60.00 | $66.00 | $55.00 | $75.00 |
| 23 | Segregate and stockpile contaminated soil (0294-0600000A) | LS | 1 | $0.01 | $15,000 | $2,000.00 | $18,760 | $2,500.00 | $10,000 |
| 24 | Lead compliance plan (0294-0500000A) | LS | 1 | $5,000.00 | $1,500.00 | $0.01 | $1,790.00 | $500.00 | $750.00 |
| 25 | 12 inch storm sewer pipe, 10 FT depth (0445-035012BF) | LF | 8 | $458.35 | $400.00 | $310.00 | $350.00 | $900.00 | $290.00 |
| 26 | Connection to existing structures (0490-0104000E) | EACH | 38 | $1,283.20 | $900.00 | $100.00 | $800.00 | $600.00 | $660.00 |
| 27 | Rock mulch (1040-0192000K) | CY | 87 | $125.00 | $195.00 | $200.00 | $240.00 | $300.00 | $270.00 |
| 28 | Perforated steel square tube slip base sign supports (0930-0114000A) | LB | 2,583.22 | $8.52 | $13.55 | $13.94 | $12.54 | $15.48 | $14.71 |
| 29 | Truncated domes on new surfaces, curb ramp (0765-0100000J) | SF | 1,878 | $32.96 | $42.00 | $45.00 | $39.44 | $32.00 | $80.00 |
| 30 | Patterned concrete surfacing (0759-0147000J) | SF | 733 | $24.72 | $35.00 | $30.00 | $52.00 | $24.00 | $29.00 |
| 31 | Minor adjustment of manholes (0490-0120000E) | EACH | 5 | $721.00 | $850.00 | $2,000.00 | $1,320.00 | $1,600.00 | $460.00 |
| 32 | Portable changeable message signs (0222-0164000E) | EACH | 4 | $6,500.00 | $6,000.00 | $11,000 | $5,360.00 | $5,000.00 | $14,000 |
| 33 | Concrete storm sewer manholes (0470-0101000E) | EACH | 1 | $10,751 | $5,500.00 | $11,000 | $6,120.00 | $10,000 | $8,000.00 |
| 34 | Clearing and grubbing (0320-0100000A) | ACRE | 1 | $9,500.00 | $10,000 | $0.01 | $6,210.00 | $15,000 | $5,000.00 |
| 35 | Asphalt pavement sawcutting, 6 to 14 inches deep (0310-0119120F) | LF | 5,160 | $5.50 | $6.00 | $5.00 | $8.00 | $7.00 | $7.00 |
| 36 | Inlet protection, type 3 (0280-0114030E) | EACH | 43 | $90.00 | $80.00 | $50.00 | $118.00 | $150.00 | $120.00 |
| 37 | Temporary pavement bars (0225-0153200J) | SF | 3,000 | $7.21 | $4.00 | $3.00 | $4.25 | $7.00 | $4.00 |
| 38 | Commercial asphalt concrete pavement (0740-0100000M) | TON | 312 | $300.00 | $275.00 | $600.00 | $350.00 | $335.00 | $400.00 |
| 39 | Joint repair (0759-0100000F) | LF | 90 | $10.30 | $75.00 | $25.00 | $89.00 | $10.00 | $51.00 |
| 40 | Concrete walk repair (0759-0128000J) | SF | 4 | $195.70 | $480.00 | $500.00 | $560.00 | $500.00 | $100.00 |
| 41 | Traffic signal modification, US30 at depot street (0990-0102000A) | EACH | 1 | $20,685 | $40,000 | $47,000 | $15,225 | $60,000 | $44,000 |
| 42 | Traffic signal modification, US30 at second street (0990-0102000A) | EACH | 1 | $30,574 | $40,000 | $41,000 | $26,250 | $60,000 | $46,000 |
| 43 | Temporary non-reflective tape (0225-0152000F) | LF | 250 | $9.58 | $3.00 | $1.50 | $3.00 | $9.50 | $6.00 |
| 44 | Contaminated soil disposal (0294-0200010M) | TON | 230 | $55.00 | $115.00 | $150.00 | $76.00 | $80.00 | $180.00 |
| 45 | Stripe removal (0225-0154000F) | LF | 380 | $10.82 | $12.00 | $5.00 | $12.00 | $10.50 | $9.00 |
| 46 | Temporary curb ramp, parallel (0228-0167670E) | EACH | 120 | $95.00 | $400.00 | $100.00 | $1.25 | $100.00 | $880.00 |
| 47 | Pavement legend, type B-HS: arrows (0867-0103100E) | EACH | 2 | $813.70 | $950.00 | $800.00 | $790.00 | $850.00 | $423.00 |
| 48 | Pole foundations (0970-0100000A) | EACH | 16 | $2,359.38 | $4,375.00 | $1,875.00 | $1,875.00 | $5,937.50 | $1,812.50 |
| 49 | Concrete inlets, type G-2 (0470-0315000E) | EACH | 17 | $3,697.70 | $4,000.00 | $6,000.00 | $4,260.00 | $5,500.00 | $2,100.00 |
| 50 | Major adjustment of manholes (0490-0121000E) | EACH | 1 | $3,500.00 | $4,000.00 | $4,000.00 | $3,210.00 | $5,000.00 | $1,200.00 |
| 51 | Concrete driveways (0759-0126000J) | SF | 1,461 | $18.54 | $15.00 | $25.00 | $24.00 | $18.00 | $24.00 |
| 52 | Temporary signs (0222-0102000J) | SF | 3,580 | $10.00 | $5.00 | $17.00 | $7.00 | $1.00 | $18.80 |
| 53 | Temporary striping (0225-0153000F) | LF | 250 | $9.58 | $4.00 | $5.00 | $6.00 | $9.50 | $5.00 |
| 54 | Mainline video inspection (0415-0100000F) | LF | 1,650 | $19.00 | $10.00 | $5.00 | $20.00 | $5.00 | $19.00 |
| 55 | 6 inch PVC pipe, 5 FT depth (0445-052006AF) | LF | 24 | $257.50 | $250.00 | $150.00 | $270.00 | $500.00 | $180.00 |
| 56 | Concrete curbs, curb and gutter (0759-0103000F) | LF | 3,336 | $55.62 | $66.00 | $62.00 | $80.00 | $57.00 | $95.00 |
| 57 | Remove existing signs (0905-0100000A) | LS | 1 | $10,000 | $7,000.00 | $4,000.00 | $4,940.00 | $15,000 | $3,100.00 |
| 58 | Switching, conduit, and wiring (0970-0105000A) | LF | 283 | $246.31 | $212.01 | $219.08 | $234.63 | $123.67 | $212.01 |
| 59 | Pavement bar, type B-HS (0867-0145100J) | SF | 4,599 | $8.76 | $11.00 | $8.50 | $10.00 | $8.50 | $25.00 |
| 60 | Truncated domes on existing surfaces, curb ramp (0765-0200000J) | SF | 5 | $154.50 | $800.00 | $100.00 | $240.00 | $150.00 | $108.00 |
| 61 | 8 inch PVC pipe, 5 FT depth (0445-052008AF) | LF | 36 | $293.55 | $200.00 | $155.00 | $260.00 | $475.00 | $190.00 |
| 62 | Concrete sawcutting, 6 to 14 inches deep (0310-0119220F) | LF | 3,624 | $7.50 | $7.00 | $5.00 | $8.00 | $10.50 | $12.00 |
| 63 | Sod lawn (1040-0189000J) | SY | 547 | $14.00 | $33.00 | $50.00 | $90.00 | $80.00 | $95.00 |
| 64 | Traffic signal modification, US30 at willow street (0990-0102000A) | EACH | 1 | $36,815 | $40,000 | $41,000 | $33,200 | $60,000 | $39,000 |
| 65 | Signs, standard sheeting, sheet aluminum (0940-0202000J) | SF | 281 | $45.00 | $30.00 | $25.00 | $25.00 | $25.00 | $29.00 |
| 66 | Permanent surface mounted tubular markers (0856-0101000E) | EACH | 17 | $247.20 | $300.00 | $250.00 | $240.00 | $250.00 | $265.00 |
| 67 | Concrete walks, reinforced (0759-0128000J) | SF | 11,152 | $17.92 | $18.00 | $25.00 | $24.00 | $18.00 | $14.60 |
| 68 | Removal of surfacings for curb ramp construction (0310-0106101J) | SY | 6,401 | $44.00 | $44.00 | $5.00 | $46.00 | $45.00 | $57.00 |
| 69 | Temporary barricades, type II (0224-0104000E) | EACH | 100 | $55.00 | $40.00 | $225.00 | $60.00 | $40.00 | $70.00 |
| 70 | Signs, standard sheeting, plywood (0940-0203000J) | SF | 139.54 | $35.00 | $50.00 | $25.00 | $25.00 | $25.00 | $29.00 |
| 71 | Concrete walks (0759-0128000J) | SF | 27,886 | $14.42 | $16.00 | $20.00 | $19.00 | $14.00 | $18.00 |
| 72 | 6 inch ductile iron pipe with class B backfill (1140-0400000F) | LF | 30 | $475.86 | $300.00 | $180.00 | $189.00 | $350.00 | $230.00 |
| 73 | Concrete manholes, with inlet (0470-0103000E) | EACH | 7 | $13,243 | $9,000.00 | $12,000 | $7,310.00 | $12,000 | $9,800.00 |
| 74 | Soil conditioner (1040-0107000K) | CY | 6 | $140.00 | $100.00 | $400.00 | $400.00 | $300.00 | $450.00 |
| 75 | Flaggers (0223-0168000T) | HR | 400 | $85.00 | $97.00 | $75.00 | $104.00 | $75.00 | $90.00 |
| 76 | Temporary pavement legends (0225-0153100E) | EACH | 15 | $206.00 | $100.00 | $150.00 | $600.00 | $200.00 | $230.00 |
| 77 | Inlet protection, type 4 (0280-0114040E) | EACH | 3 | $170.00 | $140.00 | $50.00 | $200.00 | $150.00 | $85.00 |
| 78 | Pollution control plan (0290-0100000A) | LS | 1 | $2,000.00 | $2,500.00 | $0.01 | $1,790.00 | $500.00 | $2,000.00 |
| 79 | 12 inch ductile iron pipe, 5 FT depth (0445-060012AF) | LF | 64 | $633.45 | $423.00 | $215.00 | $450.00 | $550.00 | $265.00 |
| 80 | Adjusting inlets (0490-0105000E) | EACH | 47 | $650.00 | $500.00 | $500.00 | $640.00 | $900.00 | $450.00 |
| 81 | Crosswalk closure supports (0902-0101000E) | EACH | 8 | $1,100.00 | $2,000.00 | $2,000.00 | $1,440.00 | $1,500.00 | $1,320.00 |
| 82 | Bollards (0815-0100000E) | EACH | 5 | $1,100.00 | $1,250.00 | $1,500.00 | $760.00 | $1,500.00 | $850.00 |
| 83 | Traffic signal modification, US30 at fir street (0990-0102000A) | EACH | 1 | $12,353 | $8,000.00 | $13,000 | $6,000.00 | $20,000 | $14,000 |
| 84 | Hydrant extensions (1160-0105000E) | EACH | 1 | $2,946.83 | $3,000.00 | $3,000.00 | $1,360.00 | $7,300.00 | $2,200.00 |
| 85 | Irrigation system (1120-0100000A) | LS | 1 | $5,000.00 | $1.00 | $5,000.00 | $14,010 | $2,500.00 | $20,000 |
| 86 | Moving existing hydrants (1160-0102000E) | EACH | 1 | $2,575.00 | $6,000.00 | $4,000.00 | $2,280.00 | $4,500.00 | $4,200.00 |
| 87 | Flagger station lighting (0223-0168100T) | HR | 400 | $20.00 | $10.00 | $5.00 | $12.00 | $15.00 | $12.00 |
| 88 | Legend removal (0225-0155100J) | SF | 64 | $11.85 | $13.00 | $6.00 | $13.00 | $12.00 | $18.00 |
| 89 | Wood sign posts (0910-0100000K) | FBM | 960 | $8.50 | $25.00 | $16.00 | $18.00 | $16.00 | $18.80 |
| 90 | Multiple mailbox supports (1070-0101000E) | EACH | 1 | $1,850.00 | $2,500.00 | $1,500.00 | $1,500.00 | $1,000.00 | $1,500.00 |
| 91 | Inlet protection, type 11 (0280-0114110E) | EACH | 72 | $110.00 | $85.00 | $50.00 | $142.00 | $150.00 | $140.00 |
| 92 | Pedestrian channelizing devices (0228-0141600F) | LF | 2,000 | $12.00 | $15.00 | $15.00 | $18.00 | $3.00 | $45.00 |
| 93 | Concrete islands (0759-0122000J) | SF | 278 | $18.54 | $40.00 | $25.00 | $87.00 | $18.00 | $21.00 |
| 94 | Trench drain, type 1 (0446-0100000F) | LF | 60 | $360.50 | $265.00 | $225.00 | $670.00 | $65.00 | $400.00 |
| 95 | Concrete curbs, curb and gutter, reinforced (0759-0103000F) | LF | 1,270 | $80.34 | $71.00 | $90.00 | $97.00 | $80.00 | $100.00 |
| 96 | Traffic signal modification, US30 at greenwood street (0990-0102000A) | EACH | 1 | $15,779 | $11,000 | $13,000 | $9,775.00 | $20,000 | $14,000 |
| 97 | Concrete curbs, modified (0759-0102000F) | LF | 590 | $49.44 | $49.00 | $55.00 | $69.00 | $50.00 | $66.00 |
| 98 | Aggregate cover material (0705-0102000K) | CY | 5 | $95.00 | $500.00 | $300.00 | $60.00 | $250.00 | $80.00 |
| 99 | Traffic signal modification, US30 at fourth street (0990-0102000A) | EACH | 1 | $20,435 | $18,000 | $25,000 | $15,000 | $35,000 | $27,000 |
| 100 | Plain concrete pavement, doweled, 9 inches thick (0756-0115000J) | SY | 630 | $216.30 | $288.00 | $250.00 | $340.00 | $275.00 | $150.00 |
| 101 | Removal of structures and obstructions (0310-0106000A) | LS | 1 | $25,000 | $45,000 | $310,000 | $29,740 | $75,000 | $93,500 |
| 102 | Emulsified asphalt in fog coat (0705-0101000M) | TON | 0.30 | $1,800.00 | $800.00 | $2,000.00 | $1,010.00 | $600.00 | $1,000.00 |
| 103 | Concrete inlets, type CG-2 (0470-0307000E) | EACH | 6 | $3,843.19 | $6,000.00 | $6,000.00 | $5,420.00 | $6,500.00 | $2,300.00 |
| 104 | Soil sample collection and analytical testing (0294-0700000E) | EACH | 1 | $1,000.00 | $3,000.00 | $4,000.00 | $2,610.00 | $6,500.00 | $2,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Bid Data Program yearly workbooks. ODOT publishes rank and unit price only: no bidder names and no bid totals, so these bids cannot be checked against a total and Oregon is left out of the competitor views.
Every contract let that day: ODOT letting of June 11, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.