SCDOT contract 0374810 bid tabulation
2026 Allendale CTC Resurfacing. Let by South Carolina DOT on November 12, 2025, Allendale, District 7. 3 bids received; low bid $5,739,726 by C.R. Jackson, Inc..
- Owner
- South Carolina DOT
- Letting
- 12 NOV 2025
- Pay items
- 51
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | C.R. Jackson, Inc. | $5,739,726 | Low |
| 2 | Palmetto Corp. of Conway | $6,216,503 | +8.0% |
| 3 | Blythe Construction, Inc. | $6,584,180 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. C.R. Jackson, Inc. | 2. Palmetto Corp. of Conway | 3. Blythe Construction, Inc. |
|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $286,000 | $295,000 | $330,250 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $114,000 | $120,000 | $45,000 |
| 0030 | Railroad insurance and flagging CSX (1071403) | LS | 1 | $18,500 | $55,000 | $15,000 |
| 0040 | Removal of exist. guardrail (2027801) | LF | 8,450 | $0.50 | $0.50 | $0.50 |
| 0050 | Borrow excavation (2033000) | CY | 2,108 | $60.00 | $57.75 | $96.25 |
| 0060 | Excavation for shoulder paving (2036000) | STA | 947.23 | $40.00 | $40.10 | $56.00 |
| 0070 | Hauling of excavated shoulder material (2072000) | STA | 947.23 | $70.00 | $75.50 | $91.75 |
| 0080 | Maintenance stone (3059900) | TON | 43.50 | $350.00 | $145.00 | $65.00 |
| 0090 | HMA shoulder widening course (3104000) | TON | 5,661.63 | $88.00 | $106.90 | $107.50 |
| 0100 | Liquid asphalt binder PG64-22 (4011004) | TON | 1,448.08 | $635.00 | $575.00 | $650.00 |
| 0110 | Aramid fiber (4011500) | LB | 3,500 | $65.00 | $70.00 | $69.00 |
| 0120 | Full depth asph. pav. patching 4" unif. (4012040) | SY | 2,690 | $80.00 | $63.00 | $64.50 |
| 0130 | Full depth asph. pav. patching 6" unif. (4012060) | SY | 200 | $85.00 | $110.10 | $91.25 |
| 0140 | Full depth asph. pav. patching 8" unif (4012080) | SY | 1,460 | $110.00 | $104.00 | $108.50 |
| 0150 | Milling existing asphalt pavement 1.5" (4013115) | SY | 4,770 | $2.35 | $3.55 | $6.70 |
| 0160 | Milling existing asphalt pavement 1.75" (4013117) | SY | 84,630 | $2.25 | $2.90 | $4.66 |
| 0170 | Milling existing asphalt pavement (variable) (4013990) | SY | 6,100 | $11.50 | $16.15 | $17.00 |
| 0180 | Asphalt surface course type B (4040320) | TON | 8,320.02 | $88.00 | $114.90 | $113.65 |
| 0190 | Asphalt surface course type C (4040340) | TON | 8,372.10 | $88.00 | $106.85 | $107.50 |
| 0200 | Asphalt surface course type D (4040350) | TON | 2,374.70 | $115.00 | $153.90 | $145.25 |
| 0210 | Driveway paving-surface type D (4047230) | TON | 393.75 | $200.00 | $335.00 | $368.50 |
| 0220 | Traffic control (6011000) | LS | 1 | $373,000 | $230,000 | $283,800 |
| 0230 | Permanent construction signs (ground mounted) (6051120) | SF | 1,510 | $6.65 | $5.50 | $5.50 |
| 0240 | 4" white broken lines -(gaps excluded)-fast dry paint (6240005) | LF | 9,780 | $0.12 | $0.05 | $0.05 |
| 0250 | 4" white solid lines (PVT. edge lines)-fast dry paint (6240010) | LF | 265,720 | $0.12 | $0.12 | $0.12 |
| 0260 | 24" white solid lines (stop/diagonal lines)-fast dry paint (6240025) | LF | 1,090 | $0.50 | $0.50 | $0.50 |
| 0270 | White lane drop arrow (left or right)-fast dry paint (6240043) | EACH | 4 | $30.00 | $10.00 | $10.00 |
| 0280 | Railroad crossing symbols - fast dry paint (6240045) | EACH | 6 | $50.00 | $25.00 | $25.00 |
| 0290 | 4" yellow broken lines(gaps exc) - fast dry paint (6240105) | LF | 15,040 | $0.12 | $0.12 | $0.12 |
| 0300 | 4"yellow solid line(PVT.edge&no passing zone)-fast dry paint (6240110) | LF | 171,360 | $0.12 | $0.12 | $0.12 |
| 0310 | 24" yellow diagonal lines - fast dry paint (6240115) | LF | 240 | $1.00 | $0.50 | $0.50 |
| 0320 | 4" white broken lines(gaps excl.)perm.PVMT.marking (6251005) | LF | 4,890 | $0.49 | $0.65 | $0.65 |
| 0330 | 4" white solid lines (PVT. edge lines) perm.PVMT.marking (6251010) | LF | 132,860 | $0.47 | $0.45 | $0.45 |
| 0340 | 24" white solid lines (stop/diag lines)- perm.PVMT.marking (6251025) | LF | 545 | $9.00 | $7.85 | $7.85 |
| 0350 | White lane drop arrow(LT.or RT.)perm.PVMT.marking (6251043) | EACH | 2 | $150.00 | $150.00 | $150.00 |
| 0360 | Railroad crossing symbols - perm.PVMT.marking (6251045) | EACH | 3 | $400.00 | $400.00 | $400.00 |
| 0370 | 4" yellow broken lines(gaps exc)perm.PVMT.marking (6251064) | LF | 7,520 | $0.50 | $0.45 | $0.45 |
| 0380 | 4" yellow solid lines(PVT.edge lines) perm.PVMT.marking (6251074) | LF | 85,680 | $0.46 | $0.45 | $0.45 |
| 0390 | 24" yellow solid lines - perm.PVMT.marking (6251080) | LF | 120 | $10.00 | $7.85 | $7.85 |
| 0400 | 4" white solid lines (PVT. edge lines) epoxy paint slow cure (6261010) | LF | 1,500 | $5.50 | $3.00 | $3.00 |
| 0410 | 4"yellow solid lines- PVT.edge&no passing zone - epoxy paint slow cure (6261110) | LF | 1,500 | $5.50 | $3.00 | $3.00 |
| 0420 | Permanent clear pavement markers- mono-dir.- 4"X4" (6300005) | EACH | 215 | $6.00 | $6.00 | $6.00 |
| 0430 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 835 | $6.00 | $6.00 | $6.00 |
| 0440 | Milled-in rumble strip (6321000) | MI | 18.11 | $1,000.00 | $500.00 | $1,152.90 |
| 0450 | MT3 leading end treatment TL3 (8051151) | EACH | 6 | $3,100.00 | $3,100.00 | $3,100.00 |
| 0460 | MGS3CS GR compressed shoulder (8052150) | LF | 7,550 | $28.00 | $28.00 | $28.00 |
| 0470 | Premash thrie strong post guardrail (8053050) | LF | 100 | $38.50 | $38.50 | $38.50 |
| 0480 | Premash thriebeam bridge conn TBBC3 (8053250) | EACH | 4 | $2,750.00 | $2,750.00 | $2,750.00 |
| 0490 | MTBBC3 MASH thrie-beam barrier connector TL3 (8053253) | EACH | 9 | $3,200.00 | $3,200.00 | $3,200.00 |
| 0500 | Premash type T TL3 leading 50' (8057100) | EACH | 7 | $3,100.00 | $3,100.00 | $3,100.00 |
| 0510 | Permanent grassing for non-permitted resurfacing projects (8100102) | ACRE | 14.84 | $3,300.00 | $3,000.00 | $3,100.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of November 12, 2025. Compiled by Mirage Metrics.