SCDOT contract 2160650 bid tabulation
Intersection Improvement E Nat. Cemetery Rd and Papermill Rd. Let by South Carolina DOT on November 12, 2025, Florence, District 5. 6 bids received; low bid $2,079,099 by Universal Civil Construction, LLC.
- Owner
- South Carolina DOT
- Letting
- 12 NOV 2025
- Pay items
- 63
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Universal Civil Construction, LLC | $2,079,099 | Low |
| 2 | Cherokee, Inc. | $2,129,955 | +2.0% |
| 3 | Psi of Conway, LLC | $2,140,908 | +3.0% |
| 4 | Kershaw Builders, Inc. | $2,170,081 | +4.0% |
| 5 | R.E. Goodson Construction Co., Inc. | $2,547,882 | +23% |
| 6 | King Asphalt, Inc. | $2,558,914 | +23% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Universal Civil Construction, LLC | 2. Cherokee, Inc. | 3. Psi of Conway, LLC | 4. Kershaw Builders, Inc. | 5. R.E. Goodson Construction Co., Inc. | 6. King Asphalt, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $103,750 | $106,500 | $201,955 | $105,000 | $121,384 | $125,000 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $62,250 | $43,000 | $38,000 | $42,500 | $15,400 | $12,000 |
| 0030 | Construction stakes, lines & grades (1050800) | EACH | 1 | $38,501 | $35,000 | $20,000 | $25,000 | $220,000 | $25,000 |
| 0040 | Clearing & grubbing within right of way (2011000) | LS | 1 | $168,000 | $100,000 | $49,119 | $30,000 | $75,000 | $60,000 |
| 0050 | Removal & disposal item no. 001 (2022000) | LS | 1 | $550.00 | $1,000.00 | $1,999.73 | $1,850.00 | $2,000.00 | $6,000.00 |
| 0060 | Removal & disposal item no. 002 (2022000) | LS | 1 | $1.00 | $200.00 | $2,157.23 | $100.00 | $2,000.00 | $900.00 |
| 0070 | Removal & disposal item no. 003 (2022000) | LS | 1 | $1.00 | $200.00 | $1,999.73 | $100.00 | $2,000.00 | $900.00 |
| 0080 | Removal & disposal of existing pavement (2023000) | SY | 1,244 | $9.50 | $20.00 | $28.15 | $15.00 | $25.00 | $15.00 |
| 0090 | Unclassified excavation (2031000) | CY | 5,027 | $14.00 | $35.00 | $11.58 | $20.00 | $15.00 | $60.00 |
| 0100 | Borrow excavation (2033000) | CY | 7,051 | $32.00 | $25.00 | $47.45 | $32.50 | $15.00 | $32.00 |
| 0110 | Muck excavation (2034000) | CY | 4,200 | $25.00 | $25.00 | $16.50 | $28.50 | $15.00 | $54.00 |
| 0120 | Geotextile, separation (2036020) | SY | 900 | $7.25 | $5.00 | $2.24 | $7.50 | $5.00 | $17.75 |
| 0130 | Geogrid stabilization (2037030) | SY | 900 | $6.50 | $5.00 | $8.09 | $20.00 | $10.00 | $18.15 |
| 0140 | Fine grading (2081001) | SY | 7,078 | $6.00 | $5.00 | $4.28 | $7.50 | $3.00 | $7.00 |
| 0150 | Flowable fill (2103000) | CY | 40 | $325.00 | $400.00 | $366.81 | $350.00 | $500.00 | $785.00 |
| 0160 | Maintenance stone (3059900) | TON | 175 | $68.00 | $60.00 | $106.89 | $100.00 | $65.00 | $100.00 |
| 0170 | Liquid asphalt binder PG64-22 (4011004) | TON | 179 | $693.00 | $710.00 | $660.00 | $710.00 | $674.00 | $660.00 |
| 0180 | Full depth asph. pav. patching 8" unif (4012080) | SY | 1,100 | $105.00 | $83.00 | $99.80 | $83.00 | $80.00 | $99.80 |
| 0190 | Asphalt base course - type A (4020310) | TON | 2,084 | $124.00 | $128.00 | $118.00 | $127.50 | $121.60 | $118.00 |
| 0200 | Asphalt intermediate course type B (4030320) | TON | 769 | $110.25 | $135.00 | $105.00 | $134.25 | $125.60 | $105.00 |
| 0210 | Asphalt surface course type B (4040320) | TON | 781 | $113.50 | $161.00 | $108.00 | $160.50 | $157.40 | $108.00 |
| 0220 | Traffic control (6011000) | LS | 1 | $210,000 | $210,000 | $150,000 | $87,500 | $697,000 | $315,000 |
| 0230 | Permanent construction signs (ground mounted) (6051120) | SF | 276 | $8.00 | $9.00 | $10.00 | $12.00 | $7.00 | $7.75 |
| 0240 | Pavement markings(temp- paint) 4" white broken lines (609105A) | LF | 100 | $0.10 | $1.00 | $0.35 | $0.05 | $0.01 | $0.05 |
| 0250 | Pavement markings(temporary-paint)-4" white solid lines (609115A) | LF | 27,000 | $0.10 | $0.13 | $0.25 | $0.15 | $0.10 | $0.11 |
| 0260 | Pavement markings(temporary-paint)-4" yellow solid lines (609115B) | LF | 27,000 | $0.10 | $0.13 | $0.25 | $0.15 | $0.10 | $0.11 |
| 0270 | Pavement markings(temporary-paint)- 24"white solid lines (609135A) | LF | 264 | $0.10 | $0.13 | $2.00 | $0.15 | $0.10 | $0.11 |
| 0280 | Temporary yellow pavement markers BI-dir.- 4"X4" (6092155) | EACH | 150 | $5.00 | $6.00 | $4.00 | $5.50 | $5.00 | $5.15 |
| 0290 | 24" white solid lines (stop/diag lines)- perm.PVMT.marking (6251025) | LF | 50 | $10.00 | $13.00 | $30.00 | $11.00 | $10.00 | $10.30 |
| 0300 | 4" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271005) | LF | 30 | $1.00 | $1.30 | $50.00 | $1.10 | $1.00 | $1.05 |
| 0310 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 4,100 | $1.00 | $1.30 | $1.00 | $1.10 | $1.00 | $1.05 |
| 0320 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 4,100 | $1.00 | $1.30 | $1.00 | $1.10 | $1.00 | $1.05 |
| 0330 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 26 | $5.00 | $6.50 | $35.00 | $5.50 | $5.00 | $5.15 |
| 0340 | Milled-in rumble strip (6321000) | MI | 0.78 | $2,825.00 | $5,000.00 | $500.00 | $15,000 | $2,500.00 | $2,600.00 |
| 0350 | 18" smooth wall pipe (7143618) | LF | 272 | $135.00 | $80.00 | $198.76 | $125.50 | $203.00 | $225.00 |
| 0360 | 24" smooth wall pipe (7143624) | LF | 64 | $150.00 | $200.00 | $250.33 | $158.50 | $214.00 | $235.00 |
| 0370 | 30" smooth wall pipe (7143630) | LF | 64 | $225.00 | $225.00 | $315.10 | $175.00 | $241.00 | $250.00 |
| 0380 | 36" smooth wall pipe (7143636) | LF | 92 | $302.00 | $230.00 | $386.09 | $200.00 | $271.00 | $350.00 |
| 0390 | Beveling of pipe end (7199100) | EACH | 16 | $225.00 | $500.00 | $1,551.13 | $275.00 | $405.00 | $650.00 |
| 0400 | Rip-rap (class A) (8041010) | TON | 32 | $165.00 | $115.00 | $230.30 | $125.00 | $120.00 | $280.00 |
| 0410 | Rip-rap (class B) (8041020) | TON | 283 | $120.00 | $115.00 | $215.79 | $125.00 | $120.00 | $210.00 |
| 0420 | Geotextile for erosion control under riprap(class 2)type B (8048205) | SY | 423 | $2.00 | $5.00 | $2.24 | $7.50 | $5.00 | $11.15 |
| 0430 | Moving item no. 001 (8081000) | LS | 1 | $825.00 | $3,000.00 | $5,000.00 | $2,500.00 | $5,000.00 | $5,200.00 |
| 0440 | Moving item no. 002 (8081000) | LS | 1 | $825.00 | $3,000.00 | $5,000.00 | $2,500.00 | $5,000.00 | $5,200.00 |
| 0450 | Right of way marker(rebar and cap) (8091010) | EACH | 33 | $205.00 | $200.00 | $80.30 | $225.00 | $150.00 | $100.00 |
| 0460 | Right of way plat (8091050) | LS | 1 | $4,500.00 | $7,000.00 | $1,100.00 | $5,000.00 | $5,000.00 | $2,200.00 |
| 0470 | Permanent cover (8100100) | ACRE | 5.60 | $1,500.00 | $2,200.00 | $2,481.01 | $1,850.00 | $2,482.01 | $2,800.00 |
| 0480 | Temporary cover (8100200) | ACRE | 8.40 | $1,500.00 | $1,500.00 | $1,500.00 | $1,650.00 | $1,500.00 | $1,650.00 |
| 0490 | Compost (8101105) | CY | 2,259 | $6.00 | $15.00 | $5.00 | $75.00 | $5.00 | $5.50 |
| 0500 | Fertilizer (nitrogen) (8104005) | LB | 560 | $4.50 | $4.40 | $1.94 | $3.50 | $1.94 | $2.10 |
| 0510 | Fertilizer (phosphoric acid) (8104010) | LB | 560 | $4.50 | $4.40 | $1.94 | $3.50 | $1.94 | $2.10 |
| 0520 | Fertilizer (potash) (8104015) | LB | 560 | $4.50 | $4.40 | $1.94 | $3.50 | $1.94 | $2.10 |
| 0530 | Agricultural granular lime (8105005) | LB | 11,200 | $0.50 | $0.50 | $1.94 | $0.50 | $1.94 | $2.10 |
| 0540 | Selective watering (8109050) | GAL | 135,750 | $0.03 | $0.09 | $0.10 | $0.50 | $0.10 | $0.11 |
| 0550 | Mowing (8109901) | ACRE | 28 | $450.00 | $480.00 | $435.49 | $850.00 | $435.49 | $475.00 |
| 0560 | Turf reinforcement matting (TRM) type 1 (8151101) | MSY | 0.08 | $9,600.00 | $8,500.00 | $3,437.07 | $10,000 | $3,437.07 | $3,800.00 |
| 0570 | Hydraulic erosion control product (hecp) - type 1 (8151201) | ACRE | 14 | $1,550.00 | $1,550.00 | $1,493.60 | $1,625.00 | $1,493.60 | $1,700.00 |
| 0580 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 14 | $3,500.00 | $3,500.00 | $3,613.98 | $4,625.00 | $3,613.98 | $3,950.00 |
| 0590 | Sediment tubes for ditch checks (8152007) | LF | 1,045 | $9.00 | $14.00 | $11.00 | $15.00 | $11.00 | $12.85 |
| 0600 | Silt fence (8153000) | LF | 500 | $9.00 | $11.00 | $3.44 | $3.75 | $5.00 | $4.40 |
| 0610 | Cleaning silt basins (8154010) | CY | 132 | $34.00 | $10.00 | $100.00 | $32.50 | $25.00 | $30.00 |
| 0620 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 10 | $120.00 | $90.00 | $90.00 | $86.50 | $150.00 | $285.00 |
| 0630 | Stabilized construction entrance (8156490) | SY | 550 | $22.00 | $24.00 | $28.00 | $15.00 | $30.00 | $52.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of November 12, 2025. Compiled by Mirage Metrics.