SCDOT contract 2357390 bid tabulation
Safety Improvements/RSA SC 183 (MP 4.2 - 6.0). Let by South Carolina DOT on March 11, 2025, Greenville, District 3. 4 bids received; low bid $4,967,618 by Palmetto Corp. of Conway.
- Owner
- South Carolina DOT
- Letting
- 11 MAR 2025
- Pay items
- 95
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Palmetto Corp. of Conway | $4,967,618 | Low |
| 2 | Reeves Construction Company | $5,765,438 | +16% |
| 3 | King Asphalt, Inc. | $6,215,354 | +25% |
| 4 | Rogers Group, Inc. | $8,596,343 | +73% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Palmetto Corp. of Conway | 2. Reeves Construction Company | 3. King Asphalt, Inc. | 4. Rogers Group, Inc. |
|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $245,000 | $347,250 | $310,000 | $420,000 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $98,000 | $100,000 | $125,000 | $260,000 |
| 0030 | Construction stakes, lines & grades (1050800) | EACH | 1 | $50,000 | $28,000 | $85,000 | $425,000 |
| 0040 | CPM progress schedule (1080300) | LS | 1 | $4,500.00 | $17,500 | $18,500 | $200,000 |
| 0050 | Selected clearing (2015005) | ACRE | 1 | $11,500 | $35,000 | $80,000 | $55,000 |
| 0060 | Removal & disposal of existing pavement (2023000) | SY | 1,525 | $49.45 | $43.00 | $82.50 | $90.00 |
| 0070 | Removal & disposal of existing asphalt pavement (2025000) | SY | 2,075 | $32.00 | $12.65 | $23.50 | $75.00 |
| 0080 | Site excavation (2031200) | LS | 1 | $225,000 | $145,000 | $265,000 | $390,000 |
| 0090 | Maintenance stone (3059900) | TON | 100 | $190.00 | $180.00 | $100.00 | $145.00 |
| 0100 | Liquid asphalt binder PG64-22 (4011004) | TON | 400 | $660.00 | $700.00 | $735.00 | $700.00 |
| 0110 | Full depth asph. pav. patching 10"unif (4012100) | SY | 7,180 | $91.35 | $157.00 | $120.00 | $113.50 |
| 0120 | Milling existing asphalt pavement 2.0" (4013120) | SY | 71,800 | $3.75 | $3.50 | $4.50 | $5.00 |
| 0130 | Asphalt surface course type B (4040320) | TON | 7,230 | $101.60 | $115.00 | $135.00 | $132.00 |
| 0140 | Traffic control (6011000) | LS | 1 | $715,225 | $700,000 | $645,000 | $1,443,000 |
| 0150 | Permanent construction signs (ground mounted) (6051120) | SF | 980 | $6.00 | $7.00 | $6.20 | $8.70 |
| 0160 | Pavement markings (temporary paint) 12"X18" white triangle yield bar (609136A) | LF | 200 | $2.00 | $2.25 | $2.05 | $2.25 |
| 0170 | 4" white broken lines -(gaps excluded)-fast dry paint (6240005) | LF | 18,600 | $0.14 | $0.15 | $0.15 | $0.20 |
| 0180 | 4" white solid lines (PVT. edge lines)-fast dry paint (6240010) | LF | 7,640 | $0.14 | $0.15 | $0.15 | $0.20 |
| 0190 | 8"white solid lines (crosswalk& channelization)fast dry paint (6240015) | LF | 12,700 | $0.15 | $0.18 | $0.15 | $0.20 |
| 0200 | 24" white solid lines (stop/diagonal lines)-fast dry paint (6240025) | LF | 11,000 | $0.50 | $0.60 | $0.55 | $0.60 |
| 0210 | White single arrow (left, straight, right)-fast dry paint (6240030) | EACH | 84 | $20.00 | $23.00 | $20.50 | $23.00 |
| 0220 | White word message "only"- fast dry paint (6240035) | EACH | 74 | $20.00 | $23.00 | $20.50 | $23.00 |
| 0230 | White combination arrow(STR.& RT.or STR.& LT.)fast dry paint (6240040) | EACH | 6 | $20.00 | $23.00 | $20.50 | $23.00 |
| 0240 | 4" yellow broken lines(gaps exc) - fast dry paint (6240105) | LF | 2,200 | $0.14 | $0.15 | $0.15 | $0.50 |
| 0250 | 4"yellow solid line(PVT.edge&no passing zone)-fast dry paint (6240110) | LF | 27,240 | $0.14 | $0.15 | $0.15 | $0.25 |
| 0260 | 6" yellow solid line on curb/median - fast dry paint (6240112) | LF | 3,050 | $0.20 | $0.25 | $0.22 | $0.40 |
| 0270 | 4" white broken lines -(gaps excluded) - epoxy paint slow cure (6261005) | LF | 1,430 | $3.00 | $3.50 | $3.10 | $3.50 |
| 0280 | 4" white solid lines (PVT. edge lines) epoxy paint slow cure (6261010) | LF | 350 | $3.00 | $3.50 | $3.10 | $3.50 |
| 0290 | 24"white solid lines(stop lines/diag.lines) epoxy paint slow cure (6261025) | LF | 100 | $3.00 | $3.50 | $3.10 | $3.50 |
| 0300 | White single arrows (left, straight, right) epoxy paint slow cure (6261030) | EACH | 2 | $85.00 | $100.00 | $90.00 | $100.00 |
| 0310 | White word message "only" - epoxy paint slow cure (6261035) | EACH | 2 | $150.00 | $175.00 | $155.00 | $170.00 |
| 0320 | 4"yellow solid lines- PVT.edge&no passing zone - epoxy paint slow cure (6261110) | LF | 1,500 | $3.00 | $3.50 | $3.10 | $3.50 |
| 0330 | 4" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271005) | LF | 9,300 | $0.48 | $0.55 | $0.50 | $0.55 |
| 0340 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 3,820 | $0.48 | $0.55 | $0.50 | $0.55 |
| 0350 | 8" white solid lines thermoplastic - 125 mil. (6271015) | LF | 6,350 | $2.00 | $2.25 | $2.05 | $2.25 |
| 0360 | 12IN X 18IN white triang. yield bar (gaps exc)thermo-125MIL (6271023) | LF | 100 | $6.00 | $7.00 | $6.20 | $7.00 |
| 0370 | 24" white solid lines (stop/diag lines)-thermo.-125 mil (6271025) | LF | 5,500 | $8.00 | $9.50 | $8.25 | $8.95 |
| 0380 | White single arrows (LT, STRGHT, RT) thermo.-125 mil. (6271030) | EACH | 42 | $85.00 | $100.00 | $90.00 | $95.00 |
| 0390 | White word message "only" - thermoplastic - 125 mil. (6271035) | EACH | 37 | $100.00 | $119.00 | $105.00 | $115.00 |
| 0400 | White combination arrows(STR&RT.or STR& LT)thermo-125MIL (6271040) | EACH | 3 | $125.00 | $145.00 | $130.00 | $150.00 |
| 0410 | White U-turn arrow thermo- 125MIL (6271042) | EACH | 4 | $125.00 | $145.00 | $130.00 | $150.00 |
| 0420 | 4" yellow broken lines(gaps exc)thermoplastic - 90 mil. (6271064) | LF | 1,100 | $0.48 | $0.55 | $0.50 | $0.55 |
| 0430 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 13,620 | $0.48 | $0.55 | $0.50 | $0.55 |
| 0440 | Permanent clear pavement markers- mono-dir.- 4"X4" (6300005) | EACH | 465 | $7.00 | $8.00 | $7.25 | $8.00 |
| 0450 | Permanent yellow pavement markers mono-dir.- 4"X 4" perm. yel. (6301005) | EACH | 120 | $7.00 | $8.00 | $7.25 | $9.00 |
| 0460 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 950 | $7.00 | $8.00 | $7.25 | $8.00 |
| 0470 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 169.24 | $26.50 | $35.50 | $23.20 | $35.00 |
| 0480 | Flat sheet, type XI, size determined by MSG, overhead (6510108) | SF | 62.50 | $29.90 | $28.00 | $51.55 | $175.00 |
| 0490 | Flat sheet,type-VIII,IX, or XI, fluor fixed size & MSG. (6510109) | SF | 62.76 | $23.50 | $59.50 | $23.20 | $35.00 |
| 0500 | Mounting assembly for F.S. sign erctd on span wire (6513015) | EACH | 8 | $248.00 | $295.00 | $375.00 | $5,800.00 |
| 0510 | U-section post for sign supports - 3P (6531210) | LF | 395 | $12.00 | $14.00 | $10.30 | $8.00 |
| 0520 | Furnish & install 1.0" schedule 80 PVC conduit (6750275) | LF | 1,745 | $10.50 | $12.50 | $26.05 | $30.00 |
| 0530 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 1,805 | $11.90 | $14.00 | $17.10 | $20.00 |
| 0540 | Furnish & install 3.0" schedule 80 PVC conduit (675027C) | LF | 705 | $14.96 | $17.50 | $51.50 | $59.00 |
| 0550 | Furnish & install 2" schedule 80 HDPE conduit (directional bored) (6760065) | LF | 1,967 | $34.00 | $40.00 | $36.50 | $42.00 |
| 0560 | Furnish & install no. 14 copper wire, 4 conductor - black (6770388) | LF | 3,195 | $4.00 | $4.75 | $4.05 | $5.00 |
| 0570 | Furnish & install no. 14 copper wire, 4 conductor - gray (6770389) | LF | 4,805 | $4.00 | $4.75 | $4.20 | $5.00 |
| 0580 | Furnish & install no. 14 copper wire, 8 conductor (black) (6770393) | LF | 10,865 | $4.75 | $5.75 | $4.40 | $5.00 |
| 0590 | Furnish & install no. 14 copper wire, 8 conductor (gray) (6770394) | LF | 2,630 | $4.85 | $5.75 | $4.50 | $5.00 |
| 0600 | Furnish & instl no. 14 copper wire,1-conductor for loop wire (6770413) | LF | 10,570 | $1.20 | $1.40 | $0.60 | $1.00 |
| 0610 | Sawcut for loop detector (6780495) | LF | 4,250 | $8.30 | $9.90 | $9.50 | $11.00 |
| 0620 | Furnish & install electrical service for traffic signal (6800499) | EACH | 5 | $2,500.00 | $2,900.00 | $2,000.00 | $2,300.00 |
| 0630 | F&I-13"X24"X18"D.elec.flush undgrd.enclos- (STR.poly.conc.)HD (6800518) | EACH | 36 | $590.00 | $700.00 | $740.00 | $900.00 |
| 0640 | F&I-17"X30"X24"D.elec.flush undgrd.enclos- (STR.poly.conc.)HD (680052C) | EACH | 7 | $690.00 | $825.00 | $915.00 | $1,100.00 |
| 0650 | F&I 13"X26' steel strain pole- powder coated with foundation (6825050) | EACH | 9 | $9,850.00 | $11,500 | $15,000 | $17,000 |
| 0660 | Furnish & install 13" X 28' steel strain pole and foundation (682505B) | EACH | 4 | $13,200 | $15,500 | $15,000 | $17,000 |
| 0670 | Furnish & install 3/8" galvanized steel cable (6825092) | LF | 3,405 | $7.00 | $8.00 | $7.65 | $9.00 |
| 0680 | Furnish & install 4' break- away aluminum pedestal pole (6825480) | EACH | 7 | $1,100.00 | $1,300.00 | $1,400.00 | $1,700.00 |
| 0690 | Furnish & install 10' break- away alum pedestal pole and base (6825484) | EACH | 11 | $1,699.00 | $2,000.00 | $1,735.00 | $2,100.00 |
| 0700 | Furnish & install 20' break- away aluminum pedestal pole and base (6825485) | EACH | 4 | $2,500.00 | $2,900.00 | $2,525.00 | $3,000.00 |
| 0710 | F&I - contr 332/336 cabinet assembly - base mounted 001 (6845511) | EACH | 7 | $16,450 | $19,500 | $25,050 | $29,000 |
| 0720 | Furnish & install -12" 4 (6865720) | EACH | 10 | $1,040.00 | $1,200.00 | $1,210.00 | $1,500.00 |
| 0730 | Furnish & install - 12" 3 (6865723) | EACH | 63 | $850.00 | $1,000.00 | $845.00 | $2,500.00 |
| 0740 | F&I - 1-way-1SECT.hand/man countdown pedestrian signal head (6865782) | EACH | 44 | $745.00 | $890.00 | $650.00 | $2,500.00 |
| 0750 | F&I-ped push but.solid state W/ tone assem 9"X15"&sign (R- 10-3E or R10-4A) (6865797) | EACH | 44 | $475.00 | $565.00 | $2,400.00 | $2,800.00 |
| 0760 | Backplate W/ retrorefl.borders for traff. sig. (6865834) | EACH | 73 | $250.00 | $295.00 | $330.00 | $400.00 |
| 0770 | Removal,salvage,&disp.of existing traf. signal equipment (6885991) | EACH | 5 | $9,500.00 | $11,000 | $1,580.00 | $10,000 |
| 0780 | Remove foundation for steel strain pole - 18" below grade (6887941) | EACH | 1 | $3,300.00 | $3,900.00 | $1,840.00 | $2,200.00 |
| 0790 | Furnish & install concrete cabinet foundation (6887951) | EACH | 5 | $1,000.00 | $1,195.00 | $1,345.00 | $1,600.00 |
| 0800 | Furnish & install radar for stop bar detection, inc 150' cable & mounting hardware (6887971) | EACH | 8 | $8,740.00 | $10,000 | $15,000 | $21,500 |
| 0810 | Furnish & install radar for setback detection, inc 150' cable & mounting hardware (6887973) | EACH | 4 | $8,430.00 | $10,000 | $14,000 | $20,500 |
| 0820 | 18" smooth wall pipe (7143618) | LF | 33 | $370.40 | $225.00 | $415.00 | $750.00 |
| 0830 | Catch basin - type 1 special (7191050) | EACH | 1 | $10,500 | $12,750 | $15,000 | $27,000 |
| 0840 | Catch basin -type 16 (7191605) | EACH | 2 | $11,500 | $14,000 | $12,900 | $19,000 |
| 0850 | Concrete curb (9" X 15") (7201000) | LF | 75 | $72.20 | $98.00 | $85.00 | $225.00 |
| 0860 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 475 | $44.65 | $62.00 | $41.25 | $70.00 |
| 0870 | Concrete sidewalk(4" uniform) (7204100) | SY | 320 | $91.40 | $115.00 | $105.00 | $145.00 |
| 0880 | Detectable warning material (7204900) | SF | 390 | $45.00 | $47.00 | $70.00 | $75.00 |
| 0890 | Concrete median (7206000) | SY | 2,250 | $114.00 | $115.00 | $155.00 | $170.00 |
| 0900 | Pedestrian ramp construction (7209000) | SY | 565 | $116.45 | $205.00 | $260.00 | $285.00 |
| 0910 | Permanent grassing for small projects (8100101) | ACRE | 0.26 | $12,800 | $10,000 | $10,500 | $10,000 |
| 0920 | Temporary erosion control blanket (ecb) (8151110) | MSY | 2.38 | $1,180.00 | $1,900.00 | $2,550.00 | $2,000.00 |
| 0930 | Inlet structure filter - type F (weighted) (8152004) | LF | 120 | $16.25 | $19.00 | $15.50 | $20.00 |
| 0940 | Silt fence (8153000) | LF | 430 | $2.32 | $6.00 | $5.45 | $7.00 |
| 0950 | Stabilized construction entrance (8156490) | SY | 1,100 | $28.20 | $25.00 | $30.00 | $16.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of March 11, 2025. Compiled by Mirage Metrics.