| 0010 | Mobilization (1031000) | LS | 1 | $440,000 | $240,000 | $635,000 | $675,000 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $218,000 | $66,605 | $46,000 | $405,000 |
| 0030 | Removal & disposal of existing pavement (2023000) | SY | 1,273 | $20.25 | $40.00 | $52.50 | $55.00 |
| 0040 | Removal of exist. guardrail (2027801) | LF | 850 | $1.00 | $1.10 | $1.05 | $1.05 |
| 0050 | Borrow excavation (2033000) | CY | 1,630 | $59.30 | $90.00 | $105.00 | $130.00 |
| 0060 | Excavation for shoulder paving (2036000) | STA | 362.74 | $48.15 | $190.00 | $80.00 | $150.00 |
| 0070 | Hauling of excavated shoulder material (2072000) | STA | 362.74 | $123.50 | $115.00 | $120.00 | $110.00 |
| 0080 | Maintenance stone (3059900) | TON | 416.50 | $95.00 | $110.00 | $75.00 | $165.00 |
| 0090 | Cement modified recycled base (12" unif)-curing method B (3063242) | SY | 16,474 | $8.65 | $9.75 | $11.00 | $13.25 |
| 0100 | Portland cement for cement modified recycled base course (3064000) | TON | 659 | $255.00 | $265.00 | $250.00 | $285.00 |
| 0110 | HMA shoulder widening course (3104000) | TON | 2,418.24 | $89.20 | $86.25 | $90.00 | $107.00 |
| 0120 | Liquid asphalt binder PG64-22 (4011004) | TON | 2,353.41 | $640.00 | $675.00 | $735.00 | $700.00 |
| 0130 | Full depth asph. pav. patching 8" unif (4012080) | SY | 21,650 | $78.85 | $78.00 | $100.00 | $84.25 |
| 0140 | Milling existing asphalt pavement 1.75" (4013117) | SY | 51,281 | $2.55 | $2.10 | $4.00 | $3.40 |
| 0150 | Milling existing asphalt pavement 2.0" (4013120) | SY | 240,094 | $2.55 | $2.40 | $3.00 | $3.55 |
| 0160 | Milling existing asphalt pavement (variable) (4013990) | SY | 12,612 | $6.65 | $13.75 | $12.00 | $12.60 |
| 0170 | Asphalt intermediate course type B (4030320) | TON | 1,586.35 | $84.20 | $73.00 | $100.00 | $82.00 |
| 0180 | Asphalt surface course type B (4040320) | TON | 29,407.12 | $92.15 | $103.00 | $100.00 | $97.35 |
| 0190 | Asphalt surface course type C (4040340) | TON | 7,209.31 | $101.75 | $129.00 | $105.00 | $135.00 |
| 0200 | Driveway paving-surface type C (4047220) | TON | 1,194.50 | $205.00 | $235.00 | $225.00 | $240.00 |
| 0210 | Traffic control (6011000) | LS | 1 | $625,000 | $1,100,000 | $908,750 | $1,190,000 |
| 0220 | Permanent construction signs (ground mounted) (6051120) | SF | 5,484 | $5.40 | $6.30 | $6.50 | $6.00 |
| 0230 | 4" white broken lines -(gaps excluded)-fast dry paint (6240005) | LF | 54,460 | $0.14 | $0.15 | $0.15 | $0.15 |
| 0240 | 4" white solid lines (PVT. edge lines)-fast dry paint (6240010) | LF | 191,379 | $0.14 | $0.15 | $0.15 | $0.15 |
| 0250 | 8"white solid lines (crosswalk& channelization)fast dry paint (6240015) | LF | 18,420 | $0.15 | $0.16 | $0.16 | $0.16 |
| 0260 | 24" white solid lines (stop/diagonal lines)-fast dry paint (6240025) | LF | 4,449 | $0.50 | $0.55 | $0.55 | $0.55 |
| 0270 | White single arrow (left, straight, right)-fast dry paint (6240030) | EACH | 80 | $15.00 | $16.75 | $15.80 | $15.50 |
| 0280 | White word message "only"- fast dry paint (6240035) | EACH | 50 | $20.00 | $22.25 | $21.05 | $21.00 |
| 0290 | White combination arrow(STR.& RT.or STR.& LT.)fast dry paint (6240040) | EACH | 12 | $20.00 | $22.25 | $21.05 | $21.00 |
| 0300 | Railroad crossing symbols - fast dry paint (6240045) | EACH | 3 | $80.00 | $89.00 | $84.20 | $85.00 |
| 0310 | 4" yellow broken lines(gaps exc) - fast dry paint (6240105) | LF | 34,160 | $0.14 | $0.15 | $0.15 | $0.15 |
| 0320 | 4"yellow solid line(PVT.edge&no passing zone)-fast dry paint (6240110) | LF | 616,598 | $0.14 | $0.15 | $0.15 | $0.15 |
| 0330 | 6" yellow solid line on curb/median - fast dry paint (6240112) | LF | 960 | $0.15 | $0.16 | $0.16 | $0.16 |
| 0340 | 4" white solid lines (PVT. edge lines) epoxy paint slow cure (6261010) | LF | 680 | $3.00 | $3.30 | $3.15 | $3.25 |
| 0350 | 4" yellow broken lines(gaps exc) epoxy paint slow cure (6261105) | LF | 20 | $3.00 | $3.30 | $3.15 | $3.25 |
| 0360 | 4"yellow solid lines- PVT.edge&no passing zone - epoxy paint slow cure (6261110) | LF | 580 | $3.00 | $3.30 | $3.15 | $3.25 |
| 0370 | 4" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271005) | LF | 13,690 | $0.48 | $0.53 | $0.50 | $0.55 |
| 0380 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 85,868 | $0.48 | $0.53 | $0.50 | $0.55 |
| 0390 | 8" white solid lines thermoplastic - 125 mil. (6271015) | LF | 9,050 | $3.00 | $3.35 | $3.15 | $3.25 |
| 0400 | 24" white solid lines (stop/diag lines)-thermo.-125 mil (6271025) | LF | 2,146 | $6.50 | $7.25 | $6.85 | $7.00 |
| 0410 | White single arrows (LT, STRGHT, RT) thermo.-125 mil. (6271030) | EACH | 40 | $100.00 | $112.00 | $105.25 | $110.00 |
| 0420 | White word message "only" - thermoplastic - 125 mil. (6271035) | EACH | 25 | $125.00 | $140.00 | $131.50 | $135.00 |
| 0430 | White combination arrows(STR&RT.or STR& LT)thermo-125MIL (6271040) | EACH | 6 | $125.00 | $140.00 | $131.50 | $135.00 |
| 0440 | Railroad crossing symbols - thermoplastic - 125 mil. (6271045) | EACH | 1 | $220.00 | $246.75 | $230.00 | $250.00 |
| 0450 | 4" yellow broken lines(gaps exc)thermoplastic - 90 mil. (6271064) | LF | 8,540 | $0.48 | $0.53 | $0.50 | $0.55 |
| 0460 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 142,628 | $0.48 | $0.53 | $0.50 | $0.55 |
| 0470 | Permanent clear pavement markers- mono-dir.- 4"X4" (6300005) | EACH | 751 | $6.50 | $7.25 | $6.85 | $7.00 |
| 0480 | Permanent yellow pavement markers mono-dir.- 4"X 4" perm. yel. (6301005) | EACH | 790 | $6.50 | $7.25 | $6.85 | $7.00 |
| 0490 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 1,817 | $6.50 | $7.25 | $6.85 | $7.00 |
| 0500 | Milled-in rumble strip (6321000) | MI | 6.16 | $500.00 | $560.75 | $525.00 | $2,500.00 |
| 0510 | Furnish & install 1.0" schedule 80 PVC conduit (6750275) | LF | 3,360 | $24.75 | $27.75 | $26.00 | $27.50 |
| 0520 | Furnish & instl no. 14 copper wire,1-conductor for loop wire (6770413) | LF | 60,320 | $0.56 | $0.60 | $0.60 | $0.60 |
| 0530 | Sawcut for loop detector (6780495) | LF | 21,920 | $9.00 | $10.00 | $9.50 | $10.00 |
| 0540 | F&I-13"X24"X18"D.elec.flush undgrd.enclos- (STR.poly.conc.)HD (6800518) | EACH | 48 | $703.00 | $785.00 | $740.00 | $750.00 |
| 0550 | Temporary adjustment of traffic signal equipment (6885993) | EACH | 16 | $6,000.00 | $6,725.00 | $6,315.00 | $8,750.00 |
| 0560 | Concrete sidewalk(4" uniform) (7204100) | SY | 900 | $76.00 | $110.00 | $79.00 | $82.50 |
| 0570 | Detectable warning material (7204900) | SF | 175 | $48.70 | $44.75 | $58.00 | $60.00 |
| 0580 | Pedestrian ramp construction (7209000) | SY | 350 | $140.50 | $179.25 | $205.00 | $215.00 |
| 0590 | Surface applied detectable warning (7209100) | SF | 340 | $58.50 | $76.25 | $63.00 | $65.00 |
| 0600 | Premash reset W-beam strong post system (8051900) | LF | 1,965 | $16.00 | $17.75 | $16.85 | $16.00 |
| 0610 | Premash type T TL3 leading 50' (8057100) | EACH | 16 | $3,100.00 | $3,475.00 | $3,265.00 | $4,200.00 |
| 0620 | Permanent grassing for non-permitted resurfacing projects (8100102) | ACRE | 6.61 | $3,300.00 | $3,475.00 | $4,600.00 | $3,400.00 |