SCDOT contract 2372150 bid tabulation
Intersection Safety Improvement US 25 / US 25 Conn. Let by South Carolina DOT on June 10, 2025, Greenville, District 3. 4 bids received; low bid $1,212,741 by Palmetto Corp. of Conway.
- Owner
- South Carolina DOT
- Letting
- 10 JUN 2025
- Pay items
- 73
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Palmetto Corp. of Conway | $1,212,741 | Low |
| 2 | Reeves Construction Company | $1,367,556 | +13% |
| 3 | Universal Civil Construction, LLC | $1,368,896 | +13% |
| 4 | S and S Construction, Inc. of Anderson | $1,507,360 | +24% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Palmetto Corp. of Conway | 2. Reeves Construction Company | 3. Universal Civil Construction, LLC | 4. S and S Construction, Inc. of Anderson |
|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $60,000 | $65,000 | $68,250 | $83,400 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $24,000 | $16,075 | $41,000 | $30,000 |
| 0030 | Construction stakes, lines & grades (1050800) | EACH | 1 | $18,000 | $7,000.00 | $25,000 | $21,350 |
| 0040 | CPM progress schedule (1080300) | LS | 1 | $5,000.00 | $8,600.00 | $3,500.00 | $6,000.00 |
| 0050 | Clearing & grubbing within right of way (2011000) | LS | 1 | $17,000 | $6,000.00 | $10,000 | $29,000 |
| 0060 | Removal & disposal of existing asphalt pavement (2025000) | SY | 325 | $42.45 | $39.50 | $36.00 | $35.00 |
| 0070 | Site excavation (2031200) | LS | 1 | $60,000 | $81,900 | $60,000 | $45,126 |
| 0080 | Fine grading (2081001) | SY | 1,700 | $7.60 | $7.00 | $13.00 | $26.00 |
| 0090 | Liquid asphalt binder PG64-22 (4011004) | TON | 79 | $635.00 | $810.00 | $662.52 | $800.00 |
| 0100 | Milling existing asphalt pavement 2.0" (4013120) | SY | 6,325 | $4.15 | $5.30 | $7.76 | $14.20 |
| 0110 | Asphalt base course - type A (4020310) | TON | 508 | $133.50 | $91.00 | $130.24 | $178.33 |
| 0120 | Asphalt intermediate course type B (4030320) | TON | 167 | $163.70 | $172.00 | $133.64 | $205.00 |
| 0130 | Asphalt surface course type B (4040320) | TON | 866 | $124.00 | $117.00 | $138.17 | $201.00 |
| 0140 | Asphalt surface course type E (4040360) | TON | 16 | $425.00 | $350.00 | $175.54 | $950.00 |
| 0150 | Traffic control (6011000) | LS | 1 | $198,345 | $290,000 | $205,000 | $98,650 |
| 0160 | Permanent construction signs (ground mounted) (6051120) | SF | 464 | $5.45 | $7.50 | $8.30 | $11.33 |
| 0170 | 4" white broken lines -(gaps excluded)-fast dry paint (6240005) | LF | 650 | $0.25 | $0.30 | $0.17 | $1.10 |
| 0180 | 4" white solid lines (PVT. edge lines)-fast dry paint (6240010) | LF | 1,730 | $0.25 | $0.30 | $0.17 | $0.90 |
| 0190 | 24" white solid lines (stop/diagonal lines)-fast dry paint (6240025) | LF | 30 | $1.00 | $1.15 | $1.12 | $3.30 |
| 0200 | White lane drop arrow (left or right)-fast dry paint (6240043) | EACH | 2 | $25.00 | $29.75 | $56.11 | $100.00 |
| 0210 | 4"yellow solid line(PVT.edge&no passing zone)-fast dry paint (6240110) | LF | 1,710 | $0.25 | $0.30 | $0.17 | $0.90 |
| 0220 | 6" yellow solid line on curb/median - fast dry paint (6240112) | LF | 1,600 | $0.75 | $0.90 | $1.12 | $0.80 |
| 0230 | 4" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271005) | LF | 650 | $1.00 | $1.15 | $0.84 | $2.20 |
| 0240 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 1,730 | $1.00 | $1.15 | $0.84 | $2.20 |
| 0250 | 24IN X 36IN white triang. yield bar (gaps exc)thermo-125MIL (6271024) | LF | 16 | $25.00 | $29.75 | $16.83 | $14.00 |
| 0260 | 24" white solid lines (stop/diag lines)-thermo.-125 mil (6271025) | LF | 30 | $15.00 | $17.75 | $11.22 | $20.00 |
| 0270 | White lane drop arrow(LT.or RT.)thermo-125MIL (6271043) | EACH | 2 | $250.00 | $290.00 | $224.44 | $300.00 |
| 0280 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 1,710 | $1.00 | $1.15 | $0.84 | $2.25 |
| 0290 | Permanent clear pavement markers- mono-dir.- 4"X4" (6300005) | EACH | 20 | $7.50 | $8.75 | $8.42 | $11.00 |
| 0300 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 80 | $7.50 | $8.75 | $8.42 | $11.00 |
| 0310 | Milled-in rumble strip (6321000) | MI | 0.33 | $2,000.00 | $2,900.00 | $2,805.47 | $25,000 |
| 0320 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 40 | $22.00 | $41.75 | $30.30 | $11.63 |
| 0330 | Flat sheet, type XI, size determined by MSG, overhead (6510108) | SF | 23 | $50.00 | $59.50 | $54.67 | $40.00 |
| 0340 | U-section post for sign supports - 3P (6531210) | LF | 85 | $16.00 | $26.25 | $16.55 | $30.00 |
| 0350 | Furnish & install 1.0" schedule 80 PVC conduit (6750275) | LF | 265 | $24.75 | $29.50 | $16.09 | $16.00 |
| 0360 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 365 | $16.25 | $19.25 | $18.39 | $17.50 |
| 0370 | Furnish & install 3.0" schedule 80 PVC conduit (675027C) | LF | 670 | $25.00 | $29.75 | $22.99 | $19.88 |
| 0380 | Furnish additional conduit within directional bore (675027Z) | LF | 65 | $12.00 | $14.25 | $20.69 | $65.00 |
| 0390 | Furnish & install 3" schedule 80 HDPE conduit (directional bored) (6760075) | LF | 65 | $50.00 | $59.50 | $48.27 | $65.00 |
| 0400 | Furnish & install no. 14 copper wire, 4 conductor - black (6770388) | LF | 275 | $5.00 | $5.75 | $4.60 | $5.50 |
| 0410 | Furnish & install no. 14 copper wire, 8 conductor (black) (6770393) | LF | 5,750 | $5.25 | $6.25 | $5.75 | $6.10 |
| 0420 | Furnish & install no. 14 copper wire, 8 conductor (gray) (6770394) | LF | 1,880 | $5.50 | $6.50 | $5.75 | $7.09 |
| 0430 | Furnish & install electrical service for traffic signal (6800499) | EACH | 1 | $870.00 | $1,000.00 | $4,500.00 | $3,500.00 |
| 0440 | F&I-13"X24"X18"D.elec.flush undgrd.enclos- (STR.poly.conc.)HD (6800518) | EACH | 7 | $703.00 | $825.00 | $861.96 | $1,100.00 |
| 0450 | F&I-17"X30"X24"D.elec.flush undgrd.enclos- (STR.poly.conc.)HD (680052C) | EACH | 1 | $869.50 | $1,000.00 | $976.89 | $1,250.00 |
| 0460 | Furnish & install 13" X 28' steel strain pole and foundation (682505B) | EACH | 3 | $7,500.00 | $8,900.00 | $13,250 | $16,900 |
| 0470 | Furnish & install 13" X 32' steel strain pole and foundation (682505D) | EACH | 1 | $13,650 | $16,000 | $14,100 | $17,900 |
| 0480 | Furnish & install 3/8" galvanized steel cable (6825092) | LF | 1,150 | $7.25 | $8.50 | $10.34 | $8.85 |
| 0490 | Furnish & install 10' break- away alum pedestal pole and base (6825484) | EACH | 3 | $1,650.00 | $1,900.00 | $2,873.21 | $3,250.00 |
| 0500 | F&I - contr 332/336 cabinet assembly - base mounted 001 (6845511) | EACH | 1 | $23,800 | $28,000 | $28,000 | $30,000 |
| 0510 | Furnish & install - 12" 5 (6865710) | EACH | 1 | $1,356.25 | $1,600.00 | $1,723.93 | $2,100.00 |
| 0520 | Furnish & install -12" 4 (6865720) | EACH | 2 | $1,150.00 | $1,300.00 | $1,264.21 | $1,965.00 |
| 0530 | Furnish & install - 12" 3 (6865723) | EACH | 12 | $800.00 | $950.00 | $861.96 | $1,496.00 |
| 0540 | F&I - countdown pedestrian signal head (6865781) | EACH | 8 | $700.00 | $835.00 | $861.96 | $1,500.00 |
| 0550 | F&I - 1-way-1SECT.hand/man countdown pedestrian signal head (6865782) | EACH | 8 | $618.00 | $735.00 | $861.96 | $1,400.00 |
| 0560 | F&I-ped push but.solid state W/ tone assem 9"X15"&sign (R- 10-3E or R10-4A) (6865797) | EACH | 8 | $352.00 | $420.00 | $517.18 | $1,350.00 |
| 0570 | Backplate W/ retrorefl.borders for traff. sig. (6865834) | EACH | 15 | $312.50 | $370.00 | $344.79 | $365.00 |
| 0580 | Removal,salvage,&disp.of existing traf. signal equipment (6885990) | LS | 1 | $4,500.00 | $5,300.00 | $4,022.50 | $6,300.00 |
| 0590 | Temporary adjustment of traffic signal equipment (6885993) | EACH | 1 | $8,500.00 | $10,100 | $8,619.63 | $6,200.00 |
| 0600 | F&I - video detection system W/ one camera, hardware & lead-in (6886040) | EACH | 1 | $6,950.00 | $8,300.00 | $22,410 | $15,200 |
| 0610 | Furnish & install video detection camera W/ hardware & lead-in (6886042) | EACH | 7 | $6,850.00 | $8,100.00 | $18,100 | $11,113 |
| 0620 | 18" smooth wall pipe (7143618) | LF | 424 | $155.65 | $220.00 | $150.00 | $189.00 |
| 0630 | Catch basin - type 1 special (7191050) | EACH | 2 | $8,200.00 | $7,750.00 | $7,850.00 | $6,000.00 |
| 0640 | Drop inlet (24" X 36") (7192020) | EACH | 1 | $8,300.00 | $10,200 | $7,550.00 | $6,000.00 |
| 0650 | Concrete median (7206000) | SY | 750 | $133.70 | $155.00 | $130.21 | $157.00 |
| 0660 | Rip-rap (class B) (8041020) | TON | 12 | $412.90 | $164.00 | $128.15 | $125.00 |
| 0670 | Geotextile for erosion control under riprap(class 1)type C (8048110) | SY | 15 | $38.50 | $83.50 | $5.89 | $5.00 |
| 0680 | Permanent grassing for small projects (8100101) | ACRE | 0.20 | $8,000.00 | $11,400 | $10,870 | $6,500.00 |
| 0690 | Hydraulic erosion control product (hecp) - type 1 (8151201) | ACRE | 0.54 | $2,000.00 | $4,200.00 | $4,019.66 | $5,800.00 |
| 0700 | Sediment tubes for ditch checks (8152007) | LF | 80 | $11.00 | $19.00 | $18.12 | $15.00 |
| 0710 | Silt fence (8153000) | LF | 500 | $3.43 | $5.25 | $5.10 | $5.00 |
| 0720 | Inlet structure filter - type B (8156210) | EACH | 120 | $250.00 | $17.50 | $1.20 | $155.00 |
| 0730 | Stabilized construction entrance (8156490) | SY | 550 | $30.55 | $35.00 | $17.13 | $18.69 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of June 10, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.