SCDOT contract 2614820 bid tabulation
US 17 Bus Intersection Improvements - Garden City. Let by South Carolina DOT on May 13, 2025, Horry, District 5. 3 bids received; low bid $63,322,739 by King Asphalt, Inc..
- Owner
- South Carolina DOT
- Letting
- 13 MAY 2025
- Pay items
- 276
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | King Asphalt, Inc. | $63,322,739 | Low |
| 2 | King Construction Services, Inc. | $71,077,863 | +12% |
| 3 | Palmetto Corp. of Conway | $75,440,781 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. King Asphalt, Inc. | 2. King Construction Services, Inc. | 3. Palmetto Corp. of Conway |
|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $2,660,000 | $3,458,755 | $3,770,000 |
| 0020 | Mobilization - subcontractor (1031100) | LS | 1 | $680,500 | $1,490,520 | $3,770,000 |
| 0030 | Bonds and insurance (1032010) | LS | 1 | $330,000 | $331,520 | $1,505,000 |
| 0040 | Construction stakes, lines & grades (1050800) | EACH | 2 | $261,150 | $100,000 | $80,000 |
| 0050 | Utility staking (1052001) | LS | 1 | $94,500 | $15,000 | $45,000 |
| 0060 | Large public water relocation no. ____ P031827 (1052110) | EACH | 1 | $6,250,000 | $5,733,534 | $5,699,934 |
| 0070 | Large public water relocation no. ____ P043757 (1052110) | EACH | 1 | $725,000 | $650,400 | $616,800 |
| 0080 | Large public sewer relocation no. ____ P031827 (1052210) | EACH | 1 | $3,400,000 | $3,135,760 | $3,135,760 |
| 0090 | Large public sewer relocation no. ____ P043757 (1052210) | EACH | 1 | $1,100,000 | $1,004,600 | $1,004,600 |
| 0100 | CPM progress schedule (1080300) | LS | 1 | $39,500 | $75,000 | $25,000 |
| 0110 | Clearing & grubbing within right of way (2011000) | LS | 1 | $177,625 | $3,200,000 | $4,331,900 |
| 0120 | Clearing & grubbing ditches (2013050) | ACRE | 0.51 | $88,875 | $750,000 | $75,000 |
| 0130 | Removal of structures & obstructions (2021000) | LS | 1 | $750,000 | $300,000 | $140,000 |
| 0140 | Removal & disposal item no. 01 (2022000) | LS | 1 | $2,680.00 | $145.00 | $2,500.00 |
| 0150 | Removal & disposal item no. 39 (2022000) | LS | 1 | $11,260 | $5,000.00 | $7,500.00 |
| 0160 | Removal & disposal item no. 02 (2022000) | LS | 1 | $3,225.00 | $500.00 | $3,000.00 |
| 0170 | Removal & disposal item no. 40 (2022000) | LS | 1 | $4,300.00 | $5,000.00 | $4,000.00 |
| 0180 | Removal & disposal item no. 03 (2022000) | LS | 1 | $3,225.00 | $500.00 | $3,000.00 |
| 0190 | Removal & disposal item no. 41 (2022000) | LS | 1 | $3,225.00 | $5,000.00 | $3,000.00 |
| 0200 | Removal & disposal item no. 04 (2022000) | LS | 1 | $3,225.00 | $10,000 | $3,000.00 |
| 0210 | Removal & disposal item no. 42 (2022000) | LS | 1 | $2,145.00 | $5,000.00 | $2,000.00 |
| 0220 | Removal & disposal item no. 05 (2022000) | LS | 1 | $3,225.00 | $10,000 | $3,000.00 |
| 0230 | Removal & disposal item no. 43 (2022000) | LS | 1 | $2,145.00 | $5,000.00 | $2,000.00 |
| 0240 | Removal & disposal item no. 06 (2022000) | LS | 1 | $3,225.00 | $10,000 | $3,000.00 |
| 0250 | Removal & disposal item no. 07 (2022000) | LS | 1 | $3,225.00 | $1,750.00 | $3,000.00 |
| 0260 | Removal & disposal item no. 08 (2022000) | LS | 1 | $3,225.00 | $300.00 | $3,000.00 |
| 0270 | Removal & disposal item no. 09 (2022000) | LS | 1 | $4,300.00 | $1,200.00 | $4,000.00 |
| 0280 | Removal & disposal item no. 10 (2022000) | LS | 1 | $2,145.00 | $10,000 | $2,000.00 |
| 0290 | Removal & disposal item no. 11 (2022000) | LS | 1 | $2,145.00 | $10,000 | $2,000.00 |
| 0300 | Removal & disposal item no. 12 (2022000) | LS | 1 | $3,220.00 | $700.00 | $3,000.00 |
| 0310 | Removal & disposal item no. 13 (2022000) | LS | 1 | $3,220.00 | $300.00 | $3,000.00 |
| 0320 | Removal & disposal item no. 14 (2022000) | LS | 1 | $3,220.00 | $900.00 | $3,000.00 |
| 0330 | Removal & disposal item no. 15 (2022000) | LS | 1 | $3,220.00 | $600.00 | $3,000.00 |
| 0340 | Removal & disposal item no. 16 (2022000) | LS | 1 | $3,220.00 | $1,250.00 | $3,000.00 |
| 0350 | Removal & disposal item no. 17 (2022000) | LS | 1 | $3,220.00 | $1,250.00 | $3,000.00 |
| 0360 | Removal & disposal item no. 18 (2022000) | LS | 1 | $8,045.00 | $1,250.00 | $7,500.00 |
| 0370 | Removal & disposal item no. 19 (2022000) | LS | 1 | $1,075.00 | $1,750.00 | $1,000.00 |
| 0380 | Removal & disposal item no. 20 (2022000) | LS | 1 | $1,075.00 | $10,000 | $1,000.00 |
| 0390 | Removal & disposal item no. 21 (2022000) | LS | 1 | $1,075.00 | $10,000 | $1,000.00 |
| 0400 | Removal & disposal item no. 22 (2022000) | LS | 1 | $1,075.00 | $10,000 | $1,000.00 |
| 0410 | Removal & disposal item no. 23 (2022000) | LS | 1 | $1,075.00 | $10,000 | $1,000.00 |
| 0420 | Removal & disposal item no. 24 (2022000) | LS | 1 | $3,220.00 | $250.00 | $3,000.00 |
| 0430 | Removal & disposal item no. 25 (2022000) | LS | 1 | $3,220.00 | $250.00 | $3,000.00 |
| 0440 | Removal & disposal item no. 26 (2022000) | LS | 1 | $8,045.00 | $1,750.00 | $7,500.00 |
| 0450 | Removal & disposal item no. 27 (2022000) | LS | 1 | $1,610.00 | $600.00 | $1,500.00 |
| 0460 | Removal & disposal item no. 28 (2022000) | LS | 1 | $1,610.00 | $250.00 | $1,500.00 |
| 0470 | Removal & disposal item no. 29 (2022000) | LS | 1 | $2,680.00 | $1,750.00 | $2,500.00 |
| 0480 | Removal & disposal item no. 30 (2022000) | LS | 1 | $4,290.00 | $1,200.00 | $4,000.00 |
| 0490 | Removal & disposal item no. 31 (2022000) | LS | 1 | $166,225 | $75,000 | $155,000 |
| 0500 | Removal & disposal item no. 32 (2022000) | LS | 1 | $302,500 | $80,000 | $168,300 |
| 0510 | Removal & disposal item no. 33 (2022000) | LS | 1 | $89,125 | $35,000 | $83,100 |
| 0520 | Removal & disposal item no. 34 (2022000) | LS | 1 | $3,220.00 | $600.00 | $3,000.00 |
| 0530 | Removal & disposal item no. 35 (2022000) | LS | 1 | $3,220.00 | $600.00 | $3,000.00 |
| 0540 | Removal & disposal item no. 36 (2022000) | LS | 1 | $3,220.00 | $600.00 | $3,000.00 |
| 0550 | Removal & disposal item no. 37 (2022000) | LS | 1 | $3,220.00 | $600.00 | $3,000.00 |
| 0560 | Removal & disposal item no. 38 (2022000) | LS | 1 | $3,220.00 | $4,150.00 | $3,000.00 |
| 0570 | Removal & disposal of existing pavement (2023000) | SY | 8,579 | $12.00 | $25.00 | $64.70 |
| 0580 | Removal & disposal of existing asphalt pavement (2025000) | SY | 22,560 | $12.50 | $22.00 | $33.15 |
| 0590 | Removal of exist. guardrail (2027801) | LF | 514.50 | $1.85 | $5.00 | $1.75 |
| 0600 | Unclassified excavation (2031000) | CY | 7,676 | $115.00 | $75.00 | $96.25 |
| 0610 | Borrow excavation (2033000) | CY | 25,361 | $110.00 | $80.00 | $92.05 |
| 0620 | Borrow pit set-UP (2033100) | LS | 1 | $2,500.00 | $50,000 | $43,500 |
| 0630 | 18" diameter pipe additional foundation work (2034518) | LF | 20,389 | $50.00 | $67.00 | $56.00 |
| 0640 | 24" diameter pipe additional foundation work (2034524) | LF | 4,988 | $55.00 | $89.00 | $72.25 |
| 0650 | 30" diameter pipe additional foundation work (2034530) | LF | 1,528.38 | $60.00 | $97.00 | $82.75 |
| 0660 | 36" diameter pipe additional foundation work (2034536) | LF | 1,039.68 | $70.00 | $165.00 | $102.85 |
| 0670 | 42" diameter pipe additional foundation work (2034542) | LF | 622.91 | $75.00 | $250.00 | $124.10 |
| 0680 | Fine grading (2081001) | SY | 32,910 | $5.00 | $6.50 | $6.30 |
| 0690 | Flowable fill (2103000) | CY | 200 | $700.00 | $500.00 | $495.00 |
| 0700 | Maintenance stone (3059900) | TON | 1,182 | $105.00 | $165.00 | $213.00 |
| 0710 | Liquid asphalt binder PG64-22 (4011004) | TON | 2,988.03 | $670.00 | $900.00 | $760.00 |
| 0720 | Full depth asph. pav. patching 8" unif (4012080) | SY | 617 | $160.00 | $150.00 | $179.00 |
| 0730 | Milling existing asphalt pavement (variable) (4013990) | SY | 18,677.02 | $9.50 | $9.00 | $11.25 |
| 0740 | Asphalt base course - type A (4020310) | TON | 13,607.82 | $115.00 | $145.00 | $188.50 |
| 0750 | Asphalt intermediate course type B (4030320) | TON | 39,392.83 | $125.00 | $125.00 | $174.40 |
| 0760 | Asphalt surface course type B (4040320) | TON | 15,001.60 | $130.00 | $135.00 | $184.80 |
| 0770 | Asphalt surface course type E (4040360) | TON | 1,312.96 | $150.00 | $140.00 | $228.25 |
| 0780 | Traffic control (6011000) | LS | 1 | $6,607,000 | $9,600,000 | $5,717,700 |
| 0790 | Barricade - type III (6041200) | LF | 180 | $64.00 | $55.00 | $53.00 |
| 0800 | Permanent construction signs (ground mounted) (6051120) | SF | 1,849.75 | $11.95 | $11.00 | $9.86 |
| 0810 | Permanent construction signs (barricade mounted) (6051125) | SF | 360 | $11.80 | $11.00 | $9.75 |
| 0820 | Portable terminal impact attenuator-test level 2 (6052121) | EACH | 3 | $12,875 | $15,000 | $12,250 |
| 0830 | Anchor kit - port. attenuator(test level 2) (605212A) | EACH | 3 | $3,415.00 | $4,000.00 | $3,250.00 |
| 0840 | Temporary concrete barrier - unanchored (6053110) | LF | 3,460 | $51.35 | $55.00 | $48.84 |
| 0850 | Type B - flashing light (608100B) | EACH | 12 | $189.75 | $120.00 | $157.00 |
| 0860 | Pavement markings(temp- paint) 4" white broken lines (609105A) | LF | 30,489 | $0.13 | $0.13 | $0.12 |
| 0870 | Pavement markings(temp- paint) 4" yellow broken lines (609105B) | LF | 3,903 | $0.13 | $0.13 | $0.12 |
| 0880 | Pavement markings(temporary-paint)-4" white solid lines (609115A) | LF | 88,035 | $0.13 | $0.11 | $0.12 |
| 0890 | Pavement markings(temporary-paint)-4" yellow solid lines (609115B) | LF | 96,792 | $0.13 | $0.11 | $0.12 |
| 0900 | Pavement markings(temporary-paint)- 24"white solid lines (609135A) | LF | 7,155 | $0.80 | $2.00 | $0.75 |
| 0910 | Pavement markings(temporary-paint)- white single arrow (609160A) | EACH | 159 | $15.75 | $16.80 | $15.00 |
| 0920 | Pavement markings(temp.- paint)-white combination arrows (609165A) | EACH | 8 | $15.75 | $28.00 | $15.00 |
| 0930 | Pavement markings(temporary-paint)- white word 'only (609180A) | EACH | 142 | $15.75 | $28.00 | $15.00 |
| 0940 | Temporary clear pavement markers mono-dir.- 4"X4" (6092100) | EACH | 1,025 | $5.25 | $4.00 | $5.00 |
| 0950 | Temporary yellow pavement markers mono-dir.- 4"X4" (6092150) | EACH | 233 | $5.25 | $4.00 | $5.00 |
| 0960 | Temporary yellow pavement markers BI-dir.- 4"X4" (6092155) | EACH | 1,240 | $5.25 | $4.00 | $5.00 |
| 0970 | 6" yellow solid line on curb/median - fast dry paint (6240112) | LF | 15,360 | $0.53 | $1.12 | $0.50 |
| 0980 | 4" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271005) | LF | 10,436 | $0.70 | $0.84 | $0.65 |
| 0990 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 10,430 | $0.47 | $1.00 | $0.45 |
| 1000 | 8" white solid lines thermoplastic - 125 mil. (6271015) | LF | 6,699 | $2.65 | $3.36 | $2.50 |
| 1010 | 24" white solid lines (stop/diag lines)-thermo.-125 mil (6271025) | LF | 6,022 | $6.85 | $11.20 | $6.50 |
| 1020 | White single arrows (LT, STRGHT, RT) thermo.-125 mil. (6271030) | EACH | 83 | $89.35 | $95.20 | $85.00 |
| 1030 | White word message "only" - thermoplastic - 125 mil. (6271035) | EACH | 76 | $89.35 | $140.00 | $85.00 |
| 1040 | White combination arrows(STR&RT.or STR& LT)thermo-125MIL (6271040) | EACH | 8 | $105.10 | $140.00 | $100.00 |
| 1050 | White U-turn arrow thermo- 125MIL (6271042) | EACH | 1 | $105.10 | $560.00 | $100.00 |
| 1060 | White lane drop arrow(LT.or RT.)thermo-125MIL (6271043) | EACH | 2 | $262.75 | $392.00 | $250.00 |
| 1070 | 4" yellow broken lines(gaps exc)thermoplastic - 90 mil. (6271064) | LF | 1,079 | $0.47 | $1.00 | $0.45 |
| 1080 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 25,487 | $0.47 | $1.00 | $0.45 |
| 1090 | 24" yellow solid lines - thermoplastic - 125 mil. (6271080) | LF | 182 | $6.30 | $13.44 | $6.00 |
| 1100 | Permanent clear pavement markers- mono-dir.- 4"X4" (6300005) | EACH | 374 | $5.25 | $5.60 | $5.00 |
| 1110 | Permanent yellow pavement markers mono-dir.- 4"X 4" perm. yel. (6301005) | EACH | 133 | $5.25 | $5.60 | $5.00 |
| 1120 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 1,049 | $5.25 | $5.60 | $5.00 |
| 1130 | Flat sheet, type III, fixed SZ. & MSG. sign (6510105) | SF | 410.44 | $29.35 | $27.00 | $23.79 |
| 1140 | Flat sheet, type XI, size determined by MSG, overhead (6510108) | SF | 130 | $47.30 | $36.40 | $36.40 |
| 1150 | Mounting assembly for F.S. sign erctd on span wire (6513015) | EACH | 18 | $525.50 | $484.18 | $484.18 |
| 1160 | U-section post for sign supports - 3P (6531210) | LF | 977 | $13.30 | $39.20 | $10.96 |
| 1170 | Furnish & install 1.0" schedule 80 PVC conduit (6750275) | LF | 1,480 | $19.00 | $14.80 | $14.80 |
| 1180 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 3,030 | $26.25 | $16.25 | $16.25 |
| 1190 | Furnish & install 3.0" schedule 80 PVC conduit (675027C) | LF | 480 | $34.75 | $38.10 | $38.10 |
| 1200 | Furnish & install 2" schedule 80 HDPE conduit (directional bored) (6760065) | LF | 1,535 | $47.30 | $24.00 | $24.00 |
| 1210 | Furnish & install no. 14 copper wire, 4 conductor - black (6770388) | LF | 9,220 | $5.25 | $5.62 | $5.62 |
| 1220 | Furnish & install no. 14 copper wire, 4 conductor - gray (6770389) | LF | 6,740 | $6.00 | $5.70 | $5.70 |
| 1230 | Furnish & install no. 14 copper wire, 8 conductor (black) (6770393) | LF | 12,810 | $6.30 | $6.84 | $6.84 |
| 1240 | Furnish & install no. 14 copper wire, 8 conductor (gray) (6770394) | LF | 2,890 | $6.85 | $7.12 | $7.12 |
| 1250 | Furnish & install fiber optic cable-single mode (6770470) | LF | 3,835 | $5.25 | $6.88 | $6.88 |
| 1260 | Furnish & install electrical service for traffic signal (6800499) | EACH | 6 | $4,205.00 | $2,000.00 | $2,000.00 |
| 1270 | F&I-13"X24"X18"D.elec.flush undgrd.enclos- (STR.poly.conc.)HD (6800518) | EACH | 23 | $3,675.00 | $1,288.64 | $1,288.64 |
| 1280 | F&I-17"X30"X24"D.elec.flush undgrd.enclos- (STR.poly.conc.)HD (680052C) | EACH | 17 | $4,415.00 | $1,562.40 | $1,562.40 |
| 1290 | Furnish & install 13" X 28' steel strain pole and foundation (682505B) | EACH | 4 | $18,920 | $23,626 | $23,626 |
| 1300 | Furnish & install 13" X 32' steel strain pole and foundation (682505D) | EACH | 22 | $22,070 | $25,093 | $25,093 |
| 1310 | Furnish & install 3/8" galvanized steel cable (6825092) | LF | 3,740 | $10.50 | $9.20 | $9.20 |
| 1320 | Furnish & install 10' break- away alum pedestal pole and base (6825484) | EACH | 30 | $3,995.00 | $1,866.40 | $1,866.40 |
| 1330 | F&I - contr 332/336 cabinet assembly - base mounted 003 (6845511) | EACH | 6 | $32,580 | $25,532 | $25,532 |
| 1340 | Furnish & install - 12" 5 (6865710) | EACH | 12 | $4,415.00 | $1,946.33 | $1,946.33 |
| 1350 | Furnish & install -12" 4 (6865720) | EACH | 13 | $4,205.00 | $1,645.56 | $1,645.56 |
| 1360 | Furnish & install - 12" 3 (6865723) | EACH | 52 | $3,680.00 | $1,395.70 | $1,395.70 |
| 1370 | F&I - 1-way-1SECT.(countdown hand/man emblem)ped.sig.head (6865783) | EACH | 42 | $2,100.00 | $1,680.76 | $1,860.76 |
| 1380 | F&I-ped push but.solid state W/ tone assem 9"X15"&sign (R- 10-3E or R10-4A) (6865797) | EACH | 42 | $840.00 | $1,118.53 | $1,278.53 |
| 1390 | Backplate W/ retrorefl.borders for traff. sig. (6865834) | EACH | 77 | $420.00 | $288.88 | $288.88 |
| 1400 | Removal,salvage,&disp.of existing traf. signal equipment (6885990) | LS | 1 | $57,800 | $30,000 | $30,000 |
| 1410 | Temporary adjustment of traffic signal equipment (6885993) | EACH | 5 | $22,280 | $15,000 | $15,000 |
| 1420 | Remove foundation for steel strain pole - 18" below grade (6887941) | EACH | 18 | $3,675.00 | $4,500.00 | $4,500.00 |
| 1430 | Furnish & install concrete cabinet foundation (6887951) | EACH | 6 | $1,575.00 | $3,480.00 | $3,480.00 |
| 1440 | Furnish & install radar for stop bar detection, inc 150' cable & mounting hardware (6887971) | EACH | 22 | $9,455.00 | $10,914 | $10,914 |
| 1450 | Furnish & install radar for setback detection, inc 150' cable & mounting hardware (6887973) | EACH | 12 | $10,300 | $12,654 | $12,654 |
| 1460 | Furnish & install factory terminated patch panel (6888082) | EACH | 5 | $3,995.00 | $3,185.00 | $3,185.00 |
| 1470 | Conc. for structures - class 4000(retaining wall) (7011401) | CY | 65.70 | $3,530.00 | $3,920.00 | $3,198.15 |
| 1480 | Reinf. steel for structures (retaining wall) (7031105) | LB | 6,696 | $3.15 | $35.00 | $2.84 |
| 1490 | 14"X 23" horizontal elliptical(HE) RC pipe cul.- class HE-III (7141141) | LF | 232 | $320.00 | $160.00 | $258.50 |
| 1500 | 19"X 30" horizontal elliptical(HE) RC pipe cul.- class HE-III (7141142) | LF | 620 | $390.00 | $165.00 | $266.95 |
| 1510 | 24"X 38" horizontal elliptical(HE) RC pipe cul.- class HE-III (7141144) | LF | 248 | $445.00 | $250.00 | $339.00 |
| 1520 | 15" smooth wall pipe (7143615) | LF | 76 | $320.00 | $158.00 | $281.35 |
| 1530 | 18" smooth wall pipe (7143618) | LF | 23,056 | $190.00 | $200.00 | $183.70 |
| 1540 | 24" smooth wall pipe (7143624) | LF | 5,816 | $260.00 | $228.00 | $237.05 |
| 1550 | 30" smooth wall pipe (7143630) | LF | 1,352 | $365.00 | $315.00 | $310.60 |
| 1560 | 36" smooth wall pipe (7143636) | LF | 1,148 | $425.00 | $400.00 | $348.75 |
| 1570 | 42" smooth wall pipe (7143642) | LF | 672 | $550.00 | $500.00 | $413.20 |
| 1580 | Cleaning existing pipe (7149999) | LF | 422 | $60.00 | $20.00 | $65.00 |
| 1590 | Catch basin - type 1 special (7191050) | EACH | 38 | $8,250.00 | $10,000 | $7,175.00 |
| 1600 | Catch basin -type 9 MH (7191250) | EACH | 12 | $6,250.00 | $8,500.00 | $5,825.00 |
| 1610 | Catch basin -type 16 (7191605) | EACH | 125 | $8,250.00 | $10,000 | $9,250.00 |
| 1620 | Catch basin -type 16B (6X6 box) (7191606) | EACH | 2 | $15,500 | $15,000 | $16,310 |
| 1630 | Catch basin -type 18 (7191650) | EACH | 25 | $13,000 | $17,500 | $17,500 |
| 1640 | Drop inlet (24" X 36") (7192020) | EACH | 71 | $6,500.00 | $6,000.00 | $5,165.00 |
| 1650 | Drop inlet (24" X 36") with standard 5' X 5' box (7192022) | EACH | 2 | $7,500.00 | $7,000.00 | $10,495 |
| 1660 | Closed flume inlet type-16 (7192060) | EACH | 40 | $33,500 | $3,750.00 | $28,495 |
| 1670 | Closed flume inlet type-18 (7192062) | EACH | 8 | $35,750 | $3,750.00 | $40,220 |
| 1680 | Trench drain-4" interior dimension (driveway application) (719209A) | LF | 56 | $420.00 | $15.00 | $1,365.00 |
| 1690 | Manhole (7192105) | EACH | 40 | $7,000.00 | $6,250.00 | $5,545.00 |
| 1700 | Manhole with standard 4' X 4' box (7192107) | EACH | 7 | $7,250.00 | $7,500.00 | $7,095.00 |
| 1710 | Manhole with standard 5' X 5' box (7192108) | EACH | 2 | $11,000 | $8,500.00 | $14,195 |
| 1720 | 48" X 48" junction box (7192260) | EACH | 11 | $6,750.00 | $12,500 | $6,635.00 |
| 1730 | 48" X 60" junction box (7192265) | EACH | 1 | $9,500.00 | $20,000 | $14,200 |
| 1740 | 60" X 60" junction box (7192275) | EACH | 2 | $10,250 | $50,000 | $14,200 |
| 1750 | Junction box (special) 005 (719228Z) | EACH | 2 | $34,250 | $19,282 | $78,485 |
| 1760 | Junction box (special) 01 (719228Z) | EACH | 1 | $25,750 | $25,000 | $57,840 |
| 1770 | Extra depth of box (7196000) | LF | 11.03 | $675.00 | $7,500.00 | $875.00 |
| 1780 | Catch basin - type 9 MH (top only) (7196152) | EACH | 1 | $3,000.00 | $560.00 | $4,400.00 |
| 1790 | Beveling of pipe end (7199100) | EACH | 28 | $375.00 | $1,500.00 | $1,300.00 |
| 1800 | Concrete curb and gutter(1'-6") vertical face (7203110) | LF | 403 | $31.40 | $53.00 | $153.50 |
| 1810 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 28,390 | $30.00 | $53.00 | $63.60 |
| 1820 | Concrete sidewalk(4" uniform) (7204100) | SY | 11,848 | $90.85 | $124.00 | $119.70 |
| 1830 | Detectable warning material (7204900) | SF | 1,062.50 | $59.00 | $55.00 | $50.00 |
| 1840 | Concrete driveway(6" uniform) (7205000) | SY | 4,989.53 | $98.00 | $230.00 | $230.95 |
| 1850 | Concrete median (7206000) | SY | 7,159 | $195.80 | $167.50 | $164.30 |
| 1860 | Pedestrian ramp construction (7209000) | SY | 2,125 | $112.75 | $325.00 | $250.00 |
| 1870 | Surface applied detectable warning (7209100) | SF | 170 | $59.00 | $115.00 | $60.00 |
| 1880 | Waterproofing (7282000) | SY | 47.80 | $113.75 | $250.00 | $130.00 |
| 1890 | Aggregate underdrain (aggr.no. 57) (8011400) | CY | 17.90 | $450.00 | $293.93 | $865.00 |
| 1900 | Rip-rap (class A) (8041010) | TON | 78 | $275.00 | $200.00 | $425.00 |
| 1910 | Rip-rap (class B) (8041020) | TON | 814 | $350.00 | $150.00 | $350.00 |
| 1920 | Geotextile for erosion control under riprap(class 2)type A (8048200) | SY | 988 | $8.00 | $9.00 | $8.00 |
| 1930 | Premash W-beam strong post system WSP3 (8051050) | LF | 362.50 | $24.70 | $30.00 | $23.50 |
| 1940 | MT3 leading end treatment TL3 (8051151) | EACH | 4 | $3,678.50 | $6,500.00 | $3,500.00 |
| 1950 | MB trailing end treatment (8051710) | EACH | 1 | $1,735.00 | $3,500.00 | $1,650.00 |
| 1960 | MGS2C GR behind curb (8052200) | LF | 200 | $25.25 | $50.00 | $24.00 |
| 1970 | Premash trailing W-beam type B 12.5' (8052210) | EACH | 1 | $1,525.00 | $3,200.00 | $1,450.00 |
| 1980 | MTBBC3 MASH thrie-beam barrier connector TL3 (8053253) | EACH | 1 | $3,180.00 | $6,038.76 | $3,025.00 |
| 1990 | Premash W-beam tight curved system (8055800) | LF | 87.50 | $29.95 | $42.56 | $28.50 |
| 2000 | Premash W-beam medium shop bent system (8055801) | LF | 75 | $29.95 | $42.56 | $28.50 |
| 2010 | Premash type T TL2 leading 25FT (8057050) | EACH | 1 | $3,575.00 | $3,976.00 | $3,400.00 |
| 2020 | 72" chain link fence 72" chain- link fence (8063300) | LF | 2,203 | $46.65 | $33.00 | $29.00 |
| 2030 | 20' wide- chain link fence gate (72"HT) double swing gates (8064700) | EACH | 3 | $10,135 | $10,000 | $3,500.00 |
| 2040 | Moving item no. 34 (8081000) | LS | 1 | $3,220.00 | $3,360.00 | $3,000.00 |
| 2050 | Moving item no. 01 (8081000) | LS | 1 | $10,725 | $8,500.00 | $10,000 |
| 2060 | Moving item no. 35 (8081000) | LS | 1 | $1,072.43 | $1,120.00 | $1,000.00 |
| 2070 | Moving item no. 02 (8081000) | LS | 1 | $8,045.00 | $8,500.00 | $7,500.00 |
| 2080 | Moving item no. 36 (8081000) | LS | 1 | $16,100 | $16,800 | $15,000 |
| 2090 | Moving item no. 03 (8081000) | LS | 1 | $8,045.00 | $8,500.00 | $7,500.00 |
| 2100 | Moving item no. 37 (8081000) | LS | 1 | $1,075.00 | $1,120.00 | $1,000.00 |
| 2110 | Moving item no. 04 (8081000) | LS | 1 | $8,045.00 | $8,500.00 | $7,500.00 |
| 2120 | Moving item no. 38 (8081000) | LS | 1 | $1,075.00 | $1,120.00 | $1,000.00 |
| 2130 | Moving item no. 05 (8081000) | LS | 1 | $8,045.00 | $8,500.00 | $7,500.00 |
| 2140 | Moving item no. 06 (8081000) | LS | 1 | $2,145.00 | $2,500.00 | $2,000.00 |
| 2150 | Moving item no. 07 (8081000) | LS | 1 | $2,145.00 | $2,500.00 | $2,000.00 |
| 2160 | Moving item no. 08 (8081000) | LS | 1 | $2,145.00 | $2,500.00 | $2,000.00 |
| 2170 | Moving item no. 09 (8081000) | LS | 1 | $4,205.00 | $5,000.00 | $4,000.00 |
| 2180 | Moving item no. 10 (8081000) | LS | 1 | $4,730.00 | $5,100.00 | $4,500.00 |
| 2190 | Moving item no. 11 (8081000) | LS | 1 | $4,205.00 | $5,000.00 | $4,000.00 |
| 2200 | Moving item no. 12 (8081000) | LS | 1 | $540.00 | $560.00 | $500.00 |
| 2210 | Moving item no. 13 (8081000) | LS | 1 | $2,145.00 | $2,250.00 | $2,000.00 |
| 2220 | Moving item no. 14 (8081000) | LS | 1 | $2,145.00 | $2,250.00 | $2,000.00 |
| 2230 | Moving item no. 15 (8081000) | LS | 1 | $1,075.00 | $1,250.00 | $1,000.00 |
| 2240 | Moving item no. 16 (8081000) | LS | 1 | $2,145.00 | $3,500.00 | $2,000.00 |
| 2250 | Moving item no. 17 (8081000) | LS | 1 | $1,075.00 | $1,250.00 | $1,000.00 |
| 2260 | Moving item no. 18 (8081000) | LS | 1 | $1,075.00 | $1,250.00 | $1,000.00 |
| 2270 | Moving item no. 19 (8081000) | LS | 1 | $1,075.00 | $2,250.00 | $1,000.00 |
| 2280 | Moving item no. 20 (8081000) | LS | 1 | $5,255.00 | $7,500.00 | $0.01 |
| 2290 | Moving item no. 21 (8081000) | LS | 1 | $5,255.00 | $7,500.00 | $0.01 |
| 2300 | Moving item no. 22 (8081000) | LS | 1 | $5,255.00 | $7,500.00 | $0.01 |
| 2310 | Moving item no. 23 (8081000) | LS | 1 | $5,255.00 | $7,500.00 | $250.00 |
| 2320 | Moving item no. 24 (8081000) | LS | 1 | $5,255.00 | $7,500.00 | $250.00 |
| 2330 | Moving item no. 25 (8081000) | LS | 1 | $5,255.00 | $7,500.00 | $250.00 |
| 2340 | Moving item no. 26 (8081000) | LS | 1 | $5,255.00 | $7,500.00 | $0.01 |
| 2350 | Moving item no. 27 (8081000) | LS | 1 | $5,255.00 | $7,500.00 | $0.01 |
| 2360 | Moving item no. 28 (8081000) | LS | 1 | $18,775 | $7,500.00 | $17,500 |
| 2370 | Moving item no. 29 (8081000) | LS | 1 | $13,405 | $15,000 | $12,500 |
| 2380 | Moving item no. 30 (8081000) | LS | 1 | $10,725 | $12,500 | $10,000 |
| 2390 | Moving item no. 31 (8081000) | LS | 1 | $10,725 | $12,500 | $10,000 |
| 2400 | Moving item no. 32 (8081000) | LS | 1 | $37,535 | $12,500 | $10,000 |
| 2410 | Moving item no. 33 (8081000) | LS | 1 | $15,015 | $30,000 | $10,000 |
| 2420 | Right of way marker(rebar and cap) (8091010) | EACH | 311 | $218.50 | $500.00 | $75.00 |
| 2430 | Right of way plat (8091050) | LS | 1 | $35,205 | $7,000.00 | $5,800.00 |
| 2440 | Permanent cover (8100100) | ACRE | 18.12 | $2,091.25 | $2,250.00 | $1,950.00 |
| 2450 | Temporary cover (8100200) | ACRE | 18.12 | $1,340.50 | $1,450.00 | $1,250.00 |
| 2460 | Select material (8101100) | CY | 80.60 | $270.00 | $60.00 | $165.00 |
| 2470 | Fertilizer (nitrogen) (8104005) | LB | 1,812 | $2.15 | $3.00 | $2.00 |
| 2480 | Fertilizer (phosphoric acid) (8104010) | LB | 1,812 | $2.15 | $3.00 | $2.00 |
| 2490 | Fertilizer (potash) (8104015) | LB | 1,812 | $2.15 | $3.00 | $2.00 |
| 2500 | Agricultural granular lime (8105005) | LB | 36,240 | $2.15 | $3.00 | $2.00 |
| 2510 | Selective watering (8109050) | GAL | 190,050 | $0.27 | $0.35 | $0.25 |
| 2520 | Mowing (8109901) | ACRE | 72.48 | $536.25 | $560.00 | $500.00 |
| 2530 | Sodding (8131000) | MSY | 8.77 | $10,725 | $11,199 | $10,000 |
| 2540 | Turf reinforcement matting (TRM) type 2 (8151102) | MSY | 0.09 | $5,095.00 | $4,000.00 | $4,750.00 |
| 2550 | Temporary erosion control blanket (ecb) (8151110) | MSY | 3.04 | $2,650.00 | $5,600.00 | $2,475.00 |
| 2560 | Hydraulic erosion control product (hecp) - type 1 (8151201) | ACRE | 11.22 | $1,875.00 | $200.00 | $1,750.00 |
| 2570 | Hydraulic erosion control product (hecp) - type 2 (8151202) | ACRE | 13.59 | $2,950.00 | $3,150.00 | $2,750.00 |
| 2580 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 40.78 | $4,020.00 | $4,250.00 | $3,750.00 |
| 2590 | Inlet structure filter - type F (weighted) (8152004) | LF | 245 | $11.80 | $13.50 | $11.00 |
| 2600 | Inlet structure filter- type F (non-weighted) (8152006) | LF | 245 | $11.80 | $12.50 | $11.00 |
| 2610 | Sediment tubes for ditch checks (8152007) | LF | 663 | $11.80 | $12.50 | $11.00 |
| 2620 | Silt fence (8153000) | LF | 33,107.80 | $3.75 | $4.00 | $3.50 |
| 2630 | Replace/repair silt fence (8153090) | LF | 3,310.88 | $4.30 | $6.00 | $4.00 |
| 2640 | Silt basins (8154000) | CY | 12,141.10 | $39.90 | $30.80 | $27.50 |
| 2650 | Cleaning silt basins (8154010) | CY | 4,512.08 | $61.90 | $62.00 | $55.00 |
| 2660 | Porous baffle (8154011) | LF | 320 | $10.75 | $11.50 | $10.00 |
| 2670 | Floating skimmer (8154012) | EACH | 3 | $8,700.00 | $8,750.00 | $11,975 |
| 2680 | Removal of silt retained by silt fence (8154050) | LF | 8,276.95 | $4.30 | $5.00 | $4.00 |
| 2690 | Cleaning inlet structure filters (8156200) | EACH | 574 | $101.50 | $225.00 | $200.00 |
| 2700 | Inlet structure filter - type D1 (8156205) | EACH | 60 | $805.00 | $850.00 | $750.00 |
| 2710 | Inlet structure filter - type D2 (8156215) | EACH | 7 | $1,075.00 | $1,250.00 | $1,000.00 |
| 2720 | Inlet structure filter - type A (8156219) | LF | 306 | $10.75 | $12.00 | $10.00 |
| 2730 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 100 | $200.00 | $170.00 | $270.00 |
| 2740 | Stabilized construction entrance (8156490) | SY | 1,925 | $54.00 | $45.00 | $58.80 |
| 2750 | Permanent sediment control structure (8160200) | EACH | 3 | $15,465 | $10,000 | $11,400 |
| 2751 | On-the-job trainee (roadway) (9001000) | HR | 8,320 | $0.80 | $0.80 | $0.80 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of May 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.