| 0010 | Mobilization (1031000) | LS | 1 | $342,000 | $225,000 | $340,000 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $136,500 | $140,000 | $82,500 |
| 0030 | Railroad insurance and flagging PD RR (1071403) | LS | 1 | $38,500 | $18,000 | $105,000 |
| 0040 | Removal & disposal of existing pavement (2023000) | SY | 3,195 | $40.00 | $19.50 | $35.00 |
| 0050 | Removal & disposal of existing curb (2024100) | LF | 1,000 | $18.00 | $12.75 | $16.00 |
| 0060 | Borrow excavation (2033000) | CY | 2,426 | $71.50 | $61.15 | $87.50 |
| 0070 | Excavation for shoulder paving (2036000) | STA | 600.86 | $45.00 | $26.00 | $28.40 |
| 0080 | Hauling of excavated shoulder material (2072000) | STA | 600.86 | $22.00 | $66.50 | $62.20 |
| 0090 | Maintenance stone (3059900) | TON | 73 | $97.00 | $175.00 | $85.35 |
| 0100 | HMA shoulder widening course (3104000) | TON | 2,803.68 | $72.50 | $79.65 | $83.70 |
| 0110 | Liquid asphalt binder PG64-22 (4011004) | TON | 1,954.32 | $569.00 | $580.00 | $610.00 |
| 0120 | Full depth asph. pav. patching 8" unif (4012080) | SY | 7,300 | $73.00 | $81.75 | $85.50 |
| 0130 | Milling existing asphalt pavement 2.0" (4013120) | SY | 184,197 | $1.80 | $2.55 | $2.25 |
| 0140 | Milling existing asphalt pavement (variable) (4013990) | SY | 1,450 | $9.00 | $22.00 | $10.45 |
| 0150 | Asphalt surface course type B (4040320) | TON | 24,033.93 | $73.50 | $91.60 | $86.45 |
| 0160 | Asphalt surface course type C (4040340) | TON | 7,106.33 | $65.50 | $90.75 | $81.35 |
| 0170 | Asphalt surface course type D (4040350) | TON | 297 | $92.00 | $136.30 | $105.55 |
| 0180 | Driveway paving-surface type D (4047230) | TON | 388.75 | $177.50 | $245.00 | $200.00 |
| 0190 | Traffic control (6011000) | LS | 1 | $328,500 | $335,000 | $475,000 |
| 0200 | Permanent construction signs (ground mounted) (6051120) | SF | 1,924 | $6.00 | $5.60 | $6.25 |
| 0210 | 4" white broken lines -(gaps excluded)-fast dry paint (6240005) | LF | 32,100 | $0.12 | $0.12 | $0.12 |
| 0220 | 4" white solid lines (PVT. edge lines)-fast dry paint (6240010) | LF | 435,051 | $0.12 | $0.12 | $0.12 |
| 0230 | 8"white solid lines (crosswalk& channelization)fast dry paint (6240015) | LF | 8,235 | $0.05 | $0.05 | $0.05 |
| 0240 | 24" white solid lines (stop/diagonal lines)-fast dry paint (6240025) | LF | 1,680 | $0.12 | $0.12 | $0.12 |
| 0250 | White single arrow (left, straight, right)-fast dry paint (6240030) | EACH | 30 | $5.00 | $5.00 | $5.00 |
| 0260 | White single bike lane arrow (LT, straight, RT)-fast dry paint (6240031) | EACH | 12 | $5.00 | $5.00 | $5.00 |
| 0270 | White word message "only"- fast dry paint (6240035) | EACH | 18 | $5.00 | $5.00 | $5.00 |
| 0280 | White combination arrow(STR.& RT.or STR.& LT.)fast dry paint (6240040) | EACH | 6 | $5.00 | $5.00 | $5.00 |
| 0290 | Railroad crossing symbols - fast dry paint (6240045) | EACH | 18 | $10.00 | $10.00 | $10.00 |
| 0300 | Bike lane symbol - fast dry paint (6240055) | EACH | 12 | $10.00 | $10.00 | $10.00 |
| 0310 | 4" yellow broken lines(gaps exc) - fast dry paint (6240105) | LF | 40,815 | $0.12 | $0.12 | $0.12 |
| 0320 | 4"yellow solid line(PVT.edge&no passing zone)-fast dry paint (6240110) | LF | 310,557 | $0.12 | $0.12 | $0.12 |
| 0330 | 6" yellow solid line on curb/median - fast dry paint (6240112) | LF | 555 | $1.00 | $1.00 | $1.00 |
| 0340 | 4" white broken lines -(gaps excluded) - epoxy paint slow cure (6261005) | LF | 100 | $0.75 | $0.75 | $0.75 |
| 0350 | 4" white solid lines (PVT. edge lines) epoxy paint slow cure (6261010) | LF | 6,440 | $0.75 | $0.75 | $0.75 |
| 0360 | 6" white solid lines (PVT. edge lines) epoxy paint slow cure (6261012) | LF | 400 | $1.00 | $1.00 | $1.00 |
| 0370 | 4" yellow broken lines(gaps exc) epoxy paint slow cure (6261105) | LF | 920 | $0.75 | $0.75 | $0.75 |
| 0380 | 4"yellow solid lines- PVT.edge&no passing zone - epoxy paint slow cure (6261110) | LF | 1,120 | $0.75 | $0.75 | $0.75 |
| 0390 | 4" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271005) | LF | 10,700 | $0.65 | $0.65 | $0.65 |
| 0400 | 6" white broken lines(gaps excl.)thermoplastic- 90 mil. (6271007) | LF | 450 | $0.85 | $0.85 | $0.85 |
| 0410 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 125,692 | $0.40 | $0.40 | $0.40 |
| 0420 | 6" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271012) | LF | 19,325 | $0.60 | $0.60 | $0.60 |
| 0430 | 8" white solid lines thermoplastic - 125 mil. (6271015) | LF | 2,745 | $2.15 | $2.15 | $2.15 |
| 0440 | 12IN X 18IN white triang. yield bar (gaps exc)thermo-125MIL (6271023) | LF | 400 | $15.00 | $15.00 | $15.00 |
| 0450 | 24" white solid lines (stop/diag lines)-thermo.-125 mil (6271025) | LF | 875 | $6.50 | $6.50 | $6.50 |
| 0460 | White single arrows (LT, STRGHT, RT) thermo.-125 mil. (6271030) | EACH | 10 | $100.00 | $100.00 | $100.00 |
| 0470 | White word message "only" - thermoplastic - 125 mil. (6271035) | EACH | 6 | $100.00 | $100.00 | $100.00 |
| 0480 | White combination arrows(STR&RT.or STR& LT)thermo-125MIL (6271040) | EACH | 2 | $100.00 | $100.00 | $100.00 |
| 0490 | Railroad crossing symbols - thermoplastic - 125 mil. (6271045) | EACH | 6 | $350.00 | $350.00 | $350.00 |
| 0500 | 4" yellow broken lines(gaps exc)thermoplastic - 90 mil. (6271064) | LF | 13,605 | $0.40 | $0.40 | $0.40 |
| 0510 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 103,519 | $0.40 | $0.40 | $0.40 |
| 0520 | Bike lane symbol -preformed thermo - 60MIL (6280055) | EACH | 4 | $100.00 | $100.00 | $100.00 |
| 0530 | Bike lane arrow - preformed thermo - 60MIL (6280056) | EACH | 4 | $50.00 | $50.00 | $50.00 |
| 0540 | Permanent clear pavement markers- mono-dir.- 4"X4" (6300005) | EACH | 592 | $5.00 | $5.00 | $5.00 |
| 0550 | Permanent yellow pavement markers mono-dir.- 4"X 4" perm. yel. (6301005) | EACH | 450 | $5.00 | $5.00 | $5.00 |
| 0560 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 1,733 | $5.00 | $5.00 | $5.00 |
| 0570 | Milled-in rumble strip (6321000) | MI | 27.27 | $885.00 | $500.00 | $500.00 |
| 0580 | Furnish & install 1.0" schedule 80 PVC conduit (6750275) | LF | 590 | $20.00 | $17.50 | $17.50 |
| 0590 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 150 | $20.00 | $18.00 | $18.00 |
| 0600 | Furnish & install no. 14 copper wire, 8 conductor (gray) (6770394) | LF | 1,500 | $7.00 | $5.70 | $5.70 |
| 0610 | Furnish & instl no. 14 copper wire,1-conductor for loop wire (6770413) | LF | 16,576 | $3.00 | $1.15 | $1.15 |
| 0620 | Sawcut for loop detector (6780495) | LF | 6,188 | $12.50 | $9.61 | $9.61 |
| 0630 | F&I-13"X24"X18"D.elec.flush undgrd.enclos- (STR.poly.conc.)HD (6800518) | EACH | 31 | $1,800.00 | $831.17 | $831.17 |
| 0640 | Temporary adjustment of traffic signal equipment (6885993) | EACH | 5 | $28,500 | $10,500 | $10,500 |
| 0650 | Concrete curb and gutter(1'-6") vertical face (7203110) | LF | 500 | $56.00 | $62.10 | $32.00 |
| 0660 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 500 | $63.00 | $66.25 | $35.00 |
| 0670 | Concrete sidewalk(4" uniform) (7204100) | SY | 1,435 | $65.00 | $80.75 | $86.00 |
| 0680 | Detectable warning material (7204900) | SF | 562.50 | $55.00 | $36.00 | $68.00 |
| 0690 | Concrete driveway(6" uniform) (7205000) | SY | 635 | $75.00 | $101.75 | $103.00 |
| 0700 | Pedestrian ramp construction (7209000) | SY | 1,125 | $145.00 | $157.25 | $130.00 |
| 0710 | Premash reset W-beam strong post system (8051900) | LF | 2,840 | $18.00 | $16.50 | $16.50 |
| 0720 | Premash reset type T TL3 leading 50' (8052420) | EACH | 4 | $710.00 | $75.00 | $75.00 |
| 0730 | Permanent grassing for non-permitted resurfacing projects (8100102) | ACRE | 6.20 | $3,300.00 | $3,235.00 | $4,235.00 |