TDOT contract CN262062 bid tabulation
F3-010,crp-30(100),54s030-f3-006,crp-319(19),33s319-f3-007,crp- 53(66),44s053-f3-006,crp-84(21),71s084-f3-004 the traffic signal modernization improvements at various intersections along various u.s. and state routes. Let by Tennessee DOT on October 2, 2026, Counties Franklin, Hamilton, Jackson, Mcminn, Putnam, Rhea, And White. 2 bids received; low bid $498,800 by Davis H. Elliot Construction Company, Inc..
- Owner
- Tennessee DOT
- Letting
- 02 OCT 2026
- Pay items
- 36
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Davis H. Elliot Construction Company, Inc. | $498,800 | Low |
| 2 | Stansell Electric Company, Inc. | $498,870 | 0.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Davis H. Elliot Construction Company, Inc. | 2. Stansell Electric Company, Inc. |
|---|---|---|---|---|---|
| 1 | Traffic control (712-01) | LS | 1 | $11,241 | $40,300 |
| 2 | Mobilization (717-01) | LS | 1 | $24,940 | $48,800 |
| 3 | Remove & relocate existing traffic signal equipment (730-01.01) | EACH | 2 | $1,000.00 | $1,100.00 |
| 4 | Removal of signal equipment (730-01.02) | EACH | 1 | $1,500.00 | $532.00 |
| 5 | Signal head assembly (130 A3) (730-02.02) | EACH | 2 | $1,600.00 | $1,460.00 |
| 6 | Remove & relocate school signal equipment (730-01.05) | LS | 1 | $8,500.00 | $2,125.00 |
| 7 | Signal head assembly (130) (730-02.07) | EACH | 11 | $1,500.00 | $1,320.00 |
| 8 | Signal head assembly (130 with backplate) (730-02.09) | EACH | 13 | $1,500.00 | $1,365.00 |
| 9 | Signal head assembly (140 A1) (730-02.13) | EACH | 2 | $1,600.00 | $1,700.00 |
| 10 | Signal head assembly (150 A2H) (730-02.16) | EACH | 3 | $1,600.00 | $2,155.00 |
| 11 | Signal head assembly (150 A2H with backplate) (730-02.17) | EACH | 3 | $1,800.00 | $2,440.00 |
| 12 | Signal head assembly (pole mounted with backplate) (730-02.30) | EACH | 1 | $1,500.00 | $1,270.00 |
| 13 | Modify existing electrical service connection (730-05.04) | EACH | 3 | $3,000.00 | $3,140.00 |
| 14 | Signal cable - 5 conductor (730-08.02) | LF | 305 | $3.75 | $4.40 |
| 15 | Signal cable - 7 conductor (730-08.03) | LF | 2,620 | $4.25 | $5.00 |
| 16 | Span wire assembly (730-09.20) | LF | 105 | $4.00 | $13.00 |
| 17 | Span wire assembly (location 1) (730-09.21) | LF | 425 | $4.00 | $8.40 |
| 18 | Tether wire assembly - 1/4" diameter (730-10.01) | LF | 530 | $4.00 | $8.80 |
| 19 | Steel conduit riser assembly (730-11.01) | EACH | 1 | $500.00 | $964.00 |
| 20 | Vehicle detector (optically activated priority control) (730-13.06) | EACH | 14 | $5,250.00 | $4,830.00 |
| 21 | Vehicle detector (radar - stop line) (730-13.12) | EACH | 2 | $28,000 | $17,800 |
| 22 | Vehicle detector (radar-single unit multi-approach) (730-13.18) | EACH | 5 | $15,500 | $24,350 |
| 23 | Modify cabinet (connect existing GPS unit) (730-15.11) | EACH | 1 | $2,000.00 | $728.00 |
| 24 | Modify cabinet (verify existing GPS unit) (730-15.12) | EACH | 15 | $2,000.00 | $728.00 |
| 25 | Modify cabinet (replace cabinet door lock) (730-15.13) | EACH | 2 | $2,000.00 | $115.00 |
| 26 | Modify cabinet (filter) (730-15.15) | EACH | 2 | $500.00 | $75.00 |
| 27 | Cabinet maintenance (filter) (730-15.16) | EACH | 23 | $500.00 | $115.00 |
| 28 | Modify cabinet (controller programming) (730-15.25) | EACH | 18 | $2,000.00 | $289.00 |
| 29 | Modify cabinet (radar installation) (730-15.26) | EACH | 6 | $2,000.00 | $355.00 |
| 30 | Modify cabinet (emergency preemption) (730-15.28) | EACH | 4 | $2,000.00 | $256.00 |
| 31 | Cabinet (flasher) (730-15.33) | EACH | 2 | $2,000.00 | $2,095.00 |
| 32 | Controller (atc) (730-16.04) | EACH | 7 | $5,500.00 | $6,535.00 |
| 33 | Controller (flasher) (730-16.05) | EACH | 2 | $500.00 | $757.00 |
| 34 | Conflict monitor (730-16.50) | EACH | 2 | $2,000.00 | $2,270.00 |
| 35 | Cabinet monitor unit (730-16.51) | EACH | 5 | $2,000.00 | $2,285.00 |
| 36 | Global positioning system (GPS) unit (730-16.60) | EACH | 1 | $1,500.00 | $1,435.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of October 2, 2026. Compiled by Mirage Metrics.