TDOT contract CN262062 bid tabulation

F3-010,crp-30(100),54s030-f3-006,crp-319(19),33s319-f3-007,crp- 53(66),44s053-f3-006,crp-84(21),71s084-f3-004 the traffic signal modernization improvements at various intersections along various u.s. and state routes. Let by Tennessee DOT on October 2, 2026, Counties Franklin, Hamilton, Jackson, Mcminn, Putnam, Rhea, And White. 2 bids received; low bid $498,800 by Davis H. Elliot Construction Company, Inc..

Owner
Tennessee DOT
Letting
02 OCT 2026
Pay items
36
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Davis H. Elliot Construction Company, Inc.$498,800Low
2Stansell Electric Company, Inc.$498,8700.0%
TDOT contract CN262062: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Davis H. Elliot Construction Company, Inc.2. Stansell Electric Company, Inc.
1Traffic control (712-01)LS1$11,241$40,300
2Mobilization (717-01)LS1$24,940$48,800
3Remove & relocate existing traffic signal equipment (730-01.01)EACH2$1,000.00$1,100.00
4Removal of signal equipment (730-01.02)EACH1$1,500.00$532.00
5Signal head assembly (130 A3) (730-02.02)EACH2$1,600.00$1,460.00
6Remove & relocate school signal equipment (730-01.05)LS1$8,500.00$2,125.00
7Signal head assembly (130) (730-02.07)EACH11$1,500.00$1,320.00
8Signal head assembly (130 with backplate) (730-02.09)EACH13$1,500.00$1,365.00
9Signal head assembly (140 A1) (730-02.13)EACH2$1,600.00$1,700.00
10Signal head assembly (150 A2H) (730-02.16)EACH3$1,600.00$2,155.00
11Signal head assembly (150 A2H with backplate) (730-02.17)EACH3$1,800.00$2,440.00
12Signal head assembly (pole mounted with backplate) (730-02.30)EACH1$1,500.00$1,270.00
13Modify existing electrical service connection (730-05.04)EACH3$3,000.00$3,140.00
14Signal cable - 5 conductor (730-08.02)LF305$3.75$4.40
15Signal cable - 7 conductor (730-08.03)LF2,620$4.25$5.00
16Span wire assembly (730-09.20)LF105$4.00$13.00
17Span wire assembly (location 1) (730-09.21)LF425$4.00$8.40
18Tether wire assembly - 1/4" diameter (730-10.01)LF530$4.00$8.80
19Steel conduit riser assembly (730-11.01)EACH1$500.00$964.00
20Vehicle detector (optically activated priority control) (730-13.06)EACH14$5,250.00$4,830.00
21Vehicle detector (radar - stop line) (730-13.12)EACH2$28,000$17,800
22Vehicle detector (radar-single unit multi-approach) (730-13.18)EACH5$15,500$24,350
23Modify cabinet (connect existing GPS unit) (730-15.11)EACH1$2,000.00$728.00
24Modify cabinet (verify existing GPS unit) (730-15.12)EACH15$2,000.00$728.00
25Modify cabinet (replace cabinet door lock) (730-15.13)EACH2$2,000.00$115.00
26Modify cabinet (filter) (730-15.15)EACH2$500.00$75.00
27Cabinet maintenance (filter) (730-15.16)EACH23$500.00$115.00
28Modify cabinet (controller programming) (730-15.25)EACH18$2,000.00$289.00
29Modify cabinet (radar installation) (730-15.26)EACH6$2,000.00$355.00
30Modify cabinet (emergency preemption) (730-15.28)EACH4$2,000.00$256.00
31Cabinet (flasher) (730-15.33)EACH2$2,000.00$2,095.00
32Controller (atc) (730-16.04)EACH7$5,500.00$6,535.00
33Controller (flasher) (730-16.05)EACH2$500.00$757.00
34Conflict monitor (730-16.50)EACH2$2,000.00$2,270.00
35Cabinet monitor unit (730-16.51)EACH5$2,000.00$2,285.00
36Global positioning system (GPS) unit (730-16.60)EACH1$1,500.00$1,435.00
TDOT contract CN262062: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of October 2, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy