TDOT contract CNZ219 bid tabulation
The ada curb ramp upgrades on various state routes. Let by Tennessee DOT on August 15, 2025, Counties Carroll, Gibson, Henderson, And Madison. 3 bids received; low bid $329,286 by MarCor Construction, Inc..
- Owner
- Tennessee DOT
- Letting
- 15 AUG 2025
- Pay items
- 13
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | MarCor Construction, Inc. | $329,286 | Low |
| 2 | Martin Paving Company, Inc. | $373,017 | +13% |
| 3 | Ford Construction Company | $538,271 | +63% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. MarCor Construction, Inc. | 2. Martin Paving Company, Inc. | 3. Ford Construction Company |
|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $1,500.00 | $3,500.00 | $15,000 |
| 2 | Removal of trash and debris (202-01.03) | LS | 1 | $2,500.00 | $5,000.00 | $9,000.00 |
| 3 | Removal of rigid pavement, sidewalk, etc. (202-03) | SY | 190 | $120.00 | $100.00 | $100.00 |
| 4 | Removal of curb and gutter (description) (202-08.15) | LF | 841 | $40.00 | $25.00 | $11.00 |
| 5 | Furnishing & spreading topsoil (203-07) | CY | 40 | $150.00 | $325.00 | $30.00 |
| 6 | Concrete sidewalk (4 ") (701-01.01) | SF | 1,704 | $19.00 | $26.00 | $30.00 |
| 7 | Concrete curb ramp (retrofit) (701-02.01) | SF | 3,426 | $45.00 | $43.00 | $65.00 |
| 8 | Detectable warning surface (rehabilitation) (701-02.06) | SF | 407 | $50.00 | $50.00 | $80.00 |
| 9 | Concrete curb (702-01) | CY | 14 | $950.00 | $2,600.00 | $1,400.00 |
| 10 | Concrete combined curb & gutter (702-03) | CY | 21 | $650.00 | $2,000.00 | $1,100.00 |
| 11 | Traffic control (712-01) | LS | 1 | $10,000 | $7,870.00 | $35,000 |
| 12 | Mobilization (717-01) | LS | 1 | $16,000 | $12,000 | $100,000 |
| 13 | Seeding (with mulch) (801-01) | UNIT | 5 | $600.00 | $250.00 | $150.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of August 15, 2025. Compiled by Mirage Metrics.