TDOT contract CNZ219 bid tabulation

The ada curb ramp upgrades on various state routes. Let by Tennessee DOT on August 15, 2025, Counties Carroll, Gibson, Henderson, And Madison. 3 bids received; low bid $329,286 by MarCor Construction, Inc..

Owner
Tennessee DOT
Letting
15 AUG 2025
Pay items
13
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1MarCor Construction, Inc.$329,286Low
2Martin Paving Company, Inc.$373,017+13%
3Ford Construction Company$538,271+63%
TDOT contract CNZ219: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. MarCor Construction, Inc.2. Martin Paving Company, Inc.3. Ford Construction Company
1Construction stakes, lines and grades (105-01)LS1$1,500.00$3,500.00$15,000
2Removal of trash and debris (202-01.03)LS1$2,500.00$5,000.00$9,000.00
3Removal of rigid pavement, sidewalk, etc. (202-03)SY190$120.00$100.00$100.00
4Removal of curb and gutter (description) (202-08.15)LF841$40.00$25.00$11.00
5Furnishing & spreading topsoil (203-07)CY40$150.00$325.00$30.00
6Concrete sidewalk (4 ") (701-01.01)SF1,704$19.00$26.00$30.00
7Concrete curb ramp (retrofit) (701-02.01)SF3,426$45.00$43.00$65.00
8Detectable warning surface (rehabilitation) (701-02.06)SF407$50.00$50.00$80.00
9Concrete curb (702-01)CY14$950.00$2,600.00$1,400.00
10Concrete combined curb & gutter (702-03)CY21$650.00$2,000.00$1,100.00
11Traffic control (712-01)LS1$10,000$7,870.00$35,000
12Mobilization (717-01)LS1$16,000$12,000$100,000
13Seeding (with mulch) (801-01)UNIT5$600.00$250.00$150.00
TDOT contract CNZ219: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of August 15, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy