TxDOT contract A00059276 bid tabulation
Resurface Roadway, US 380 (W. of Lake Bridgeport Bridge to SH 101/SH 114). Let by Texas DOT on February 5, 2026, Wise, Fort Worth District. 6 bids received; low bid $6,714,726 by Jagoe-Public Company, -18% against the engineer's estimate of $8,171,003.
- Owner
- Texas DOT
- Letting
- 05 FEB 2026
- Pay items
- 69
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Jagoe-Public Company | $6,714,726 | Low | -18% |
| 2 | CDM Holdings | $6,881,717 | +2.0% | -16% |
| 3 | A. L. Helmcamp, Inc. | $6,952,496 | +4.0% | -15% |
| 4 | Austin Bridge & Road Services, LP | $6,963,761 | +4.0% | -15% |
| 5 | Grey Sky Construction LLC | $8,067,598 | +20% | -1.0% |
| 6 | Eurovia Atlantic Coast LLC | $9,793,701 | +46% | +20% |
Engineer's estimate: $8,171,003.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Jagoe-Public Company | 2. CDM Holdings | 3. A. L. Helmcamp, Inc. | 4. Austin Bridge & Road Services, LP | 5. Grey Sky Construction LLC | 6. Eurovia Atlantic Coast LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Backfill (type A or B) (134-7004) | STA | 406 | $330.00 | $150.00 | $300.00 | $200.00 | $145.33 | $250.00 | $280.00 |
| 2 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 24,669 | $1.00 | $0.30 | $0.25 | $0.22 | $1.89 | $0.50 | $0.25 |
| 3 | Broadcast seed (temporary_warm) (164-7005) | SY | 12,340 | $0.50 | $0.10 | $0.25 | $0.20 | $1.88 | $0.50 | $0.18 |
| 4 | Broadcast seed (temporary_cool) (164-7006) | SY | 12,329 | $0.50 | $0.10 | $0.25 | $0.20 | $1.88 | $0.50 | $0.18 |
| 5 | Vegetative watering (168-7001) | TGL | 1,727 | $10.00 | $5.00 | $25.00 | $25.00 | $0.25 | $5.00 | $60.00 |
| 6 | Asphalt binder (PG 64-22) (291-7003) | TON | 502 | $600.00 | $500.00 | $475.00 | $480.00 | $475.00 | $500.00 | $480.00 |
| 7 | Salvage, haul & stockpile reclaimed asphalt PV (0 to 2") (305-7002) | SY | 215,124 | $2.00 | $1.75 | $4.00 | $2.00 | $1.00 | $2.50 | $1.92 |
| 8 | Fog seal (CSS-1H) (315-7004) | GAL | 16,047 | $5.90 | $2.00 | $1.75 | $4.75 | $1.75 | $2.00 | $1.75 |
| 9 | Asphalt (AC-20-5TR or AC-20XP) (316-7067) | GAL | 74,881 | $4.00 | $6.00 | $5.00 | $4.50 | $5.00 | $5.00 | $4.00 |
| 10 | Aggregate (type-PB, GR-4)(sac-B) (316-7211) | CY | 989 | $180.00 | $175.00 | $150.00 | $190.00 | $150.00 | $200.00 | $323.00 |
| 11 | SP mixes SP-C sac-A PG70-28 (344-7024) | TON | 24,740 | $160.00 | $111.00 | $109.00 | $145.00 | $136.00 | $145.00 | $173.00 |
| 12 | Tack coat (344-7077) | GAL | 43,026 | $0.70 | $0.50 | $0.15 | $3.50 | $0.05 | $4.00 | $3.00 |
| 13 | Mobilization (500-7001) | LS | 1 | $721,000 | $745,000 | $900,000 | $475,000 | $766,014 | $800,000 | $930,000 |
| 14 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $20,000 | $25,000 | $5,000.00 | $12,800 | $37,600 | $12,500 | $90,000 |
| 15 | Portable changeable message sign (503-7002) | EACH | 2 | $17,000 | $14,000 | $17,500 | $15,000 | $5,250.00 | $20,000 | $17,000 |
| 16 | TMA (stationary) (505-7001) | DAY | 198 | $250.00 | $220.00 | $200.00 | $150.00 | $2.00 | $250.00 | $350.00 |
| 17 | TMA (mobile operation) (505-7003) | DAY | 31 | $330.00 | $270.00 | $200.00 | $50.00 | $3.00 | $550.00 | $725.00 |
| 18 | Rock filter dams (install) (type 2) (506-7002) | LF | 460 | $50.00 | $48.00 | $50.00 | $43.00 | $41.00 | $30.00 | $44.15 |
| 19 | Rock filter dams (install) (type 3) (506-7003) | LF | 315 | $100.00 | $80.00 | $80.00 | $72.00 | $69.00 | $40.00 | $115.12 |
| 20 | Rock filter dams (remove) (506-7011) | LF | 775 | $25.00 | $14.00 | $15.00 | $13.00 | $12.00 | $20.00 | $12.61 |
| 21 | Temporary sediment control fence (install) (506-7039) | LF | 4,650 | $3.50 | $5.00 | $6.00 | $4.60 | $4.40 | $4.00 | $3.88 |
| 22 | Temporary sediment control fence (remove) (506-7041) | LF | 4,650 | $2.00 | $1.25 | $1.50 | $1.00 | $1.00 | $2.00 | $0.97 |
| 23 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 1,840 | $6.50 | $6.00 | $6.00 | $5.00 | $4.70 | $12.00 | $5.50 |
| 24 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,840 | $3.00 | $1.25 | $1.50 | $1.10 | $1.00 | $9.00 | $0.97 |
| 25 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 42,750 | $0.20 | $0.15 | $0.25 | $0.15 | $0.20 | $0.30 | $0.20 |
| 26 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 34,623 | $0.20 | $0.15 | $0.25 | $0.18 | $0.20 | $0.30 | $0.20 |
| 27 | Install delineator assembly (D-SW)SZ 1(WFLX)GND (658-7003) | EACH | 12 | $49.04 | $70.00 | $200.00 | $100.00 | $60.00 | $100.00 | $100.00 |
| 28 | Install object marker assembly (OM-3L)(TWT)GNDHH (658-7271) | EACH | 2 | $395.00 | $24.00 | $750.00 | $530.00 | $800.00 | $100.00 | $1,200.00 |
| 29 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 400 | $0.70 | $0.40 | $0.40 | $0.32 | $0.40 | $1.00 | $0.30 |
| 30 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 81,068 | $0.90 | $0.30 | $0.35 | $0.21 | $0.35 | $0.50 | $0.30 |
| 31 | Work zone pavement marking non-removing (W)8"(DOT) (662-7010) | LF | 231 | $0.70 | $0.70 | $0.55 | $0.53 | $0.55 | $5.00 | $1.55 |
| 32 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 2,683 | $1.00 | $0.50 | $0.60 | $0.42 | $0.60 | $5.00 | $0.60 |
| 33 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 6,480 | $0.70 | $0.30 | $0.40 | $0.23 | $0.40 | $0.50 | $0.30 |
| 34 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 45,474 | $0.90 | $0.30 | $0.35 | $0.21 | $0.35 | $0.50 | $0.30 |
| 35 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 2,088 | $2.20 | $2.25 | $2.50 | $0.75 | $0.50 | $4.00 | $1.85 |
| 36 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 20,080 | $1.00 | $2.25 | $2.50 | $0.75 | $0.50 | $4.00 | $2.00 |
| 37 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 2,682 | $1.18 | $1.00 | $0.80 | $0.83 | $0.80 | $5.00 | $0.85 |
| 38 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 450 | $0.91 | $0.70 | $0.49 | $0.58 | $0.49 | $5.00 | $0.58 |
| 39 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 82,904 | $0.86 | $0.70 | $0.47 | $0.53 | $0.47 | $0.50 | $0.56 |
| 40 | Type I high perf PM (Y)6"(broken)(100MIL) (666-7302) | LF | 6,475 | $1.00 | $0.70 | $0.49 | $0.54 | $0.49 | $0.50 | $0.58 |
| 41 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 45,476 | $0.90 | $0.70 | $0.47 | $0.53 | $0.47 | $0.50 | $0.56 |
| 42 | Pavement sler 6" (666-7347) | LF | 430 | $0.07 | $0.30 | $0.17 | $0.21 | $0.17 | $1.00 | $0.17 |
| 43 | Pavement sler 8" (666-7348) | LF | 96 | $0.59 | $0.40 | $0.30 | $0.32 | $0.30 | $3.00 | $0.26 |
| 44 | Pavement sler 24" (666-7352) | LF | 257 | $1.92 | $1.25 | $1.00 | $1.05 | $1.00 | $9.00 | $1.35 |
| 45 | Pavement sler (arrow) (666-7353) | EACH | 1 | $51.53 | $13.00 | $20.00 | $10.50 | $20.00 | $250.00 | $25.00 |
| 46 | Pavement sler (word) (666-7354) | EACH | 1 | $57.08 | $13.00 | $25.00 | $10.50 | $25.00 | $250.00 | $30.00 |
| 47 | Prefabricated PM type C (W)(8")(DOT) (668-7082) | LF | 228 | $6.94 | $5.00 | $3.00 | $4.20 | $3.00 | $10.00 | $4.50 |
| 48 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 2,069 | $18.99 | $15.00 | $11.00 | $12.00 | $11.00 | $20.00 | $13.50 |
| 49 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 13 | $324.81 | $240.00 | $240.00 | $190.00 | $240.00 | $250.00 | $225.00 |
| 50 | Prefabricated PM type C (W)(LN reduct arrow) (668-7100) | EACH | 2 | $730.00 | $470.00 | $320.00 | $370.00 | $320.00 | $250.00 | $500.00 |
| 51 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 13 | $388.60 | $330.00 | $260.00 | $270.00 | $260.00 | $250.00 | $300.00 |
| 52 | Prefabricated PM type C (W)(36")(yld tri) (668-7111) | EACH | 16 | $72.92 | $50.00 | $55.00 | $45.00 | $55.00 | $150.00 | $60.00 |
| 53 | Reflectorized pavement marker type I-C (672-7002) | EACH | 164 | $4.62 | $5.00 | $4.00 | $4.00 | $4.00 | $6.00 | $4.00 |
| 54 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,546 | $4.48 | $4.75 | $4.00 | $4.00 | $4.00 | $6.00 | $4.00 |
| 55 | Eliminating existing PM & markers (6") (677-7002) | LF | 421 | $1.02 | $1.25 | $0.35 | $1.10 | $0.35 | $1.00 | $0.60 |
| 56 | Eliminating existing PM & markers (8") (677-7004) | LF | 95 | $1.00 | $2.75 | $0.75 | $2.10 | $0.75 | $5.00 | $0.69 |
| 57 | Eliminating existing PM & markers (24") (677-7008) | LF | 236 | $5.08 | $2.75 | $2.75 | $2.10 | $2.75 | $10.00 | $2.65 |
| 58 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 1 | $67.41 | $50.00 | $50.00 | $41.00 | $50.00 | $250.00 | $39.00 |
| 59 | Eliminating existing PM & markers (word) (677-7015) | EACH | 1 | $64.36 | $50.00 | $60.00 | $41.00 | $60.00 | $250.00 | $44.00 |
| 60 | Pavement surface preparation for marking (6") (678-7002) | LF | 430 | $0.09 | $0.30 | $0.05 | $0.21 | $0.05 | $1.00 | $0.01 |
| 61 | Pavement surface preparation for marking (8") (678-7004) | LF | 96 | $0.20 | $0.30 | $0.10 | $0.26 | $0.10 | $5.00 | $0.05 |
| 62 | Pavement surface preparation for marking (24") (678-7008) | LF | 257 | $1.20 | $1.25 | $0.75 | $1.10 | $0.75 | $20.00 | $0.46 |
| 63 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 1 | $35.53 | $13.00 | $10.00 | $11.00 | $10.00 | $250.00 | $12.00 |
| 64 | Pavement surface preparation for marking (word) (678-7016) | EACH | 1 | $39.76 | $13.00 | $10.00 | $11.00 | $10.00 | $250.00 | $12.00 |
| 65 | Pavement surface preparation for marking (RPM) (678-7033) | EACH | 7 | $4.77 | $0.30 | $1.00 | $0.25 | $1.00 | $5.00 | $0.60 |
| 66 | Removal of pedestrian push buttons (690-7030) | EACH | 4 | $160.00 | $60.00 | $2,000.00 | $600.00 | $100.00 | $1,000.00 | $500.00 |
| 67 | Removing pedestrian signal LED traffic signal lamp unit (690-7094) | EACH | 4 | $80.00 | $12.00 | $5,000.00 | $1,600.00 | $400.00 | $2,500.00 | $1,000.00 |
| 68 | Lime (hydrated lime (dry)) (3023-7001) | TON | 209 | $340.00 | $350.00 | $330.00 | $320.00 | $330.00 | $400.00 | $346.00 |
| 69 | Cold-in-place recycle (4") (3023-7002) | SY | 129,183 | $8.50 | $8.00 | $6.75 | $6.00 | $6.75 | $9.00 | $10.15 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 5, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.