TxDOT contract A00102904 bid tabulation
Surfacing/Roadway Restoration, PR 138 (In Sheldon Lake State Park to .). Let by Texas DOT on December 2, 2025, Harris, Houston District. 5 bids received; low bid $1,740,088 by Cornerstone Paving and Construction, L.L.C., -3.0% against the engineer's estimate of $1,794,658.
- Owner
- Texas DOT
- Letting
- 02 DEC 2025
- Pay items
- 44
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Cornerstone Paving and Construction, L.L.C. | $1,740,088 | Low | -3.0% |
| 2 | Environmental Allies, Inc. | $1,816,016 | +4.0% | +1.0% |
| 3 | Texas Materials Group, Inc. | $1,820,826 | +5.0% | +1.0% |
| 4 | Durwood Greene Construction Co. | $1,854,845 | +7.0% | +3.0% |
| 5 | STX Civil | $2,154,908 | +24% | +20% |
Engineer's estimate: $1,794,658.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Cornerstone Paving and Construction, L.L.C. | 2. Environmental Allies, Inc. | 3. Texas Materials Group, Inc. | 4. Durwood Greene Construction Co. | 5. STX Civil |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Remove (4") TRT/untrt base & asphalt pavement (105-7024) | SY | 16,550 | $10.00 | $6.00 | $4.50 | $5.25 | $6.00 | $3.00 |
| 2 | Excavation (channel) (110-7002) | CY | 7 | $35.00 | $500.00 | $25.00 | $700.00 | $600.00 | $50.00 |
| 3 | Backfill (type B) (134-7002) | STA | 92.50 | $205.00 | $165.00 | $35.00 | $295.00 | $100.00 | $350.00 |
| 4 | Block sodding (162-7002) | SY | 8,665 | $5.00 | $4.00 | $7.00 | $4.90 | $5.50 | $6.00 |
| 5 | Vegetative watering (168-7001) | TGL | 371 | $42.00 | $43.00 | $30.00 | $15.65 | $35.00 | $75.00 |
| 6 | Rdside amenity (wheel stop removing&reset) (194-7008) | EACH | 50 | $200.00 | $50.00 | $150.00 | $130.00 | $130.00 | $250.00 |
| 7 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 323 | $320.00 | $365.00 | $365.00 | $352.00 | $380.00 | $420.00 |
| 8 | Lime TRT (existing material)(8") (260-7007) | SY | 17,874 | $4.50 | $9.50 | $6.00 | $6.50 | $4.00 | $6.50 |
| 9 | Asphalt TRT base (GR 2)(PG 64) (292-7006) | TON | 3,642 | $125.00 | $115.00 | $135.00 | $119.30 | $132.00 | $160.00 |
| 10 | Prime coat (pce) (310-7005) | GAL | 3,310 | $4.00 | $5.00 | $9.00 | $4.75 | $2.25 | $10.00 |
| 11 | Asphalt (AC-15P or AC-10-2TR) (316-7073) | GAL | 10,994 | $5.50 | $4.70 | $6.50 | $3.00 | $5.00 | $10.00 |
| 12 | Aggregate (type-PB or PL, GR-4)(sac-B) (316-7245) | CY | 264 | $200.00 | $234.00 | $350.00 | $267.00 | $220.00 | $175.00 |
| 13 | SP mixes SP-D sac-A PG70-22 (344-7052) | TON | 2,834 | $125.00 | $138.00 | $155.00 | $156.00 | $155.00 | $150.00 |
| 14 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 2,018 | $2.50 | $6.00 | $4.00 | $4.00 | $8.00 | $3.00 |
| 15 | Cem stabil BKFL (400-7010) | CY | 74 | $65.00 | $250.00 | $75.00 | $70.55 | $90.00 | $145.00 |
| 16 | RC pipe (arch)(CL III)(des 1) (464-7040) | LF | 194 | $245.00 | $260.00 | $175.00 | $196.00 | $260.00 | $290.00 |
| 17 | Headwall (CH - PW - 0) (diameter= 18 in) (466-7099) | EACH | 2 | $10,000 | $6,500.00 | $9,500.00 | $15,400 | $9,500.00 | $12,500 |
| 18 | Set (type II) (des 1) (RCP) (4: 1) (C) (467-7416) | EACH | 2 | $5,000.00 | $5,000.00 | $5,750.00 | $7,425.00 | $3,200.00 | $3,500.00 |
| 19 | Mobilization (500-7001) | LS | 1 | $148,000 | $62,000 | $43,850 | $160,000 | $110,000 | $195,000 |
| 20 | Barricades, signs and traffic handling (502-7001) | MO | 5 | $5,000.00 | $3,800.00 | $1,850.00 | $1,187.00 | $6,000.00 | $2,300.00 |
| 21 | Portable changeable message sign (503-7001) | DAY | 64 | $135.00 | $75.00 | $120.00 | $110.00 | $300.00 | $65.00 |
| 22 | TMA (stationary) (505-7001) | DAY | 33 | $200.00 | $120.00 | $250.00 | $250.00 | $350.00 | $65.00 |
| 23 | TMA (mobile operation) (505-7003) | DAY | 10 | $220.00 | $120.00 | $500.00 | $700.00 | $350.00 | $65.00 |
| 24 | Rock filter dams (install) (type 1) (506-7001) | LF | 100 | $48.00 | $40.20 | $40.00 | $65.00 | $65.00 | $50.00 |
| 25 | Rock filter dams (remove) (506-7011) | LF | 100 | $15.00 | $12.45 | $15.00 | $22.00 | $25.00 | $15.00 |
| 26 | Temporary sediment control fence (install) (506-7039) | LF | 12,520 | $3.50 | $3.25 | $3.50 | $1.95 | $3.75 | $5.00 |
| 27 | Temporary sediment control fence (remove) (506-7041) | LF | 12,520 | $1.00 | $0.92 | $1.50 | $0.65 | $1.50 | $1.00 |
| 28 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 36 | $4.50 | $6.00 | $10.50 | $5.45 | $22.00 | $8.00 |
| 29 | Biodegradable erosion control logs (remove) (506-7046) | LF | 36 | $1.00 | $1.00 | $3.00 | $2.20 | $5.00 | $1.00 |
| 30 | One-way traffic control (port traffic signal) (510-7003) | MO | 2 | $5,000.00 | $4,500.00 | $5,000.00 | $3,120.00 | $5,400.00 | $6,200.00 |
| 31 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 35 | $600.00 | $625.00 | $575.00 | $938.75 | $600.00 | $680.00 |
| 32 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 2 | $710.00 | $790.00 | $725.00 | $993.00 | $850.00 | $880.00 |
| 33 | Remove SM RD SN sup&AM (644-7073) | EACH | 29 | $90.00 | $125.00 | $103.00 | $157.35 | $110.00 | $115.00 |
| 34 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 76 | $3.50 | $4.00 | $5.50 | $5.45 | $5.00 | $6.46 |
| 35 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 1,490 | $0.40 | $0.30 | $0.75 | $0.55 | $0.70 | $0.71 |
| 36 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 5,206 | $0.40 | $0.30 | $0.75 | $0.55 | $0.70 | $0.71 |
| 37 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 72 | $4.00 | $6.00 | $5.50 | $5.45 | $7.00 | $10.33 |
| 38 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 1,734 | $2.00 | $1.00 | $2.00 | $0.30 | $2.50 | $11.95 |
| 39 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 231 | $7.50 | $7.00 | $9.00 | $8.85 | $10.00 | $10.14 |
| 40 | All-wther PM type I (W)6"(solid)(100MIL) (666-7309) | LF | 25,447 | $1.05 | $1.00 | $1.05 | $0.90 | $1.10 | $1.61 |
| 41 | All-wther PM type I (Y)6"(solid)(100MIL) (666-7315) | LF | 3,106 | $1.00 | $1.00 | $1.10 | $0.90 | $1.10 | $1.61 |
| 42 | All-wther PM type I (Y)6"(broken)(100MIL) (666-7316) | LF | 2,490 | $1.00 | $1.00 | $1.10 | $0.90 | $1.10 | $1.61 |
| 43 | Pre PM type C(BL&WH)(acc PRK)(W/bordr)LG (668-7133) | EACH | 6 | $450.00 | $455.00 | $550.00 | $374.45 | $550.00 | $6.13 |
| 44 | Ditch cleaning and reshaping (foot) (760-7001) | LF | 1,051 | $2.00 | $12.00 | $6.00 | $11.15 | $5.00 | $10.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of December 2, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.