TxDOT contract A00129824 bid tabulation
Preventive Maintenance, BU 287P (E Rosedale St. to Miller Ave). Let by Texas DOT on March 4, 2025, Tarrant, Fort Worth District. 4 bids received; low bid $11,941,325 by Foutsco Paving Company, LLC, -26% against the engineer's estimate of $16,105,101.
- Owner
- Texas DOT
- Letting
- 04 MAR 2025
- Pay items
- 104
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Foutsco Paving Company, LLC | $11,941,325 | Low | -26% |
| 2 | Jagoe-Public Company | $13,130,625 | +10% | -18% |
| 3 | Peachtree Construction, LTD. | $13,759,264 | +15% | -15% |
| 4 | Texas Materials Group, Inc. | $14,041,961 | +18% | -13% |
Engineer's estimate: $16,105,101.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Foutsco Paving Company, LLC | 2. Jagoe-Public Company | 3. Peachtree Construction, LTD. | 4. Texas Materials Group, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 277 | $150.00 | $50.00 | $100.00 | $850.00 | $662.00 |
| 2 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 1 | $5,000.00 | $2,300.00 | $1,900.00 | $2,200.00 | |
| 3 | Removing concrete (driveways) (104-7011) | SY | 433 | $40.00 | $45.00 | $44.30 | $45.00 | |
| 4 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 58 | $40.00 | $45.00 | $44.30 | $45.00 | |
| 5 | Removing concrete (curb) (104-7016) | LF | 1,882 | $20.00 | $10.00 | $11.00 | $8.75 | $9.00 |
| 6 | Removing concrete (curb or curb & gutter) (104-7018) | LF | 2,211 | $12.00 | $14.00 | $13.30 | $15.00 | |
| 7 | Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002) | SY | 147 | $50.00 | $10.00 | $25.00 | $20.00 | |
| 8 | Remove (0"-12") TRT/untrt base & asphalt pavement (105-7111) | CY | 7,897 | $40.00 | $30.00 | $10.90 | $12.00 | |
| 9 | Excavation (special) (110-7003) | CY | 900 | $50.00 | $30.00 | $49.50 | $52.00 | |
| 10 | Embankment (final)(OC)(type A) (132-7001) | CY | 1,000 | $75.00 | $35.00 | $79.00 | $85.00 | |
| 11 | Embankment (final)(OC)(type C) (132-7005) | CY | 1,500 | $65.00 | $50.00 | $70.00 | $72.00 | |
| 12 | Backfill (type B) (134-7002) | STA | 48 | $371.92 | $200.00 | $800.00 | $620.00 | $650.00 |
| 13 | Compost manuf topsoil (4") (161-7002) | SY | 7,729 | $1.00 | $8.00 | $3.50 | $2.62 | |
| 14 | Block sodding (162-7002) | SY | 7,729 | $5.00 | $6.00 | $6.44 | $6.75 | |
| 15 | Vegetative watering (168-7001) | TGL | 271 | $1.00 | $100.00 | $25.00 | $70.00 | |
| 16 | Asphalt (AC-20XP) (316-7006) | GAL | 53,643 | $5.43 | $6.00 | $6.50 | $8.60 | $5.00 |
| 17 | Aggregate (type-PB, GR-5)(sac-B) (316-7214) | CY | 1,441 | $500.00 | $325.00 | $275.00 | $500.00 | $513.37 |
| 18 | D-GR HMA type D sac-A PG64-22 (341-7044) | TON | 131 | $300.00 | $200.00 | $360.00 | $255.00 | |
| 19 | SP mixes SP-C sac-A PG70-28 (344-7024) | TON | 24,682 | $183.18 | $170.00 | $176.00 | $171.00 | $181.00 |
| 20 | Flexible pavement structure repair(5") (351-7004) | SY | 4,000 | $80.00 | $45.00 | $50.00 | $60.50 | $67.00 |
| 21 | Plane & text asphalt concrete pavement(0" to 3") (354-7003) | SY | 214,532 | $6.00 | $2.00 | $3.00 | $3.50 | $3.17 |
| 22 | Full - depth repair CRCP (6") (361-7001) | CY | 86 | $1,200.00 | $300.00 | $900.00 | $1,800.00 | $1,900.00 |
| 23 | Full - depth repair CRCP (10") (361-7005) | CY | 274 | $1,500.00 | $400.00 | $800.00 | $1,400.00 | $1,500.00 |
| 24 | Trench excavation protection (402-7001) | LF | 846 | $2.00 | $4.25 | $1.00 | $1.10 | |
| 25 | Temporary special shoring (403-7001) | SF | 1,335 | $50.00 | $60.00 | $55.00 | $55.00 | |
| 26 | Retaining wall (spread footing) (423-7015) | SF | 5,370 | $83.00 | $90.00 | $75.50 | $80.00 | |
| 27 | Riprap (concrete)(5 in) (432-7002) | CY | 30 | $750.00 | $800.00 | $703.00 | $800.00 | |
| 28 | Riprap (concrete)(flume) (432-7012) | CY | 1 | $2,500.00 | $800.00 | $2,215.00 | $2,400.00 | |
| 29 | Riprap (stone common)(dry)(6 in) (432-7029) | CY | 83 | $300.00 | $360.00 | $249.00 | $260.00 | |
| 30 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 468 | $110.00 | $40.00 | $37.00 | $23.25 | $25.00 |
| 31 | Rail (handrail)(type B) (450-7059) | LF | 1,321 | $100.00 | $75.00 | $162.00 | $136.00 | |
| 32 | Header type expansion joint (454-7009) | CF | 65 | $175.00 | $500.00 | $500.00 | $545.00 | $600.00 |
| 33 | RC pipe (CL III)(24 in) (464-7005) | LF | 775 | $200.00 | $160.00 | $101.00 | $105.00 | |
| 34 | RC pipe (CL III)(36 in) (464-7009) | LF | 24 | $400.00 | $340.00 | $360.00 | $400.00 | |
| 35 | Inlet (complete)(CO)(15 FT)(FTW) (465-7186) | EACH | 2 | $25,000 | $26,000 | $15,500 | $16,000 | |
| 36 | Inlet (complete)( CO)(20 FT)(FTW) (465-7187) | EACH | 1 | $25,000 | $25,000 | $21,000 | $22,000 | |
| 37 | Grate & frame (471-7003) | EACH | 100 | $1,700.00 | $3,200.00 | $4,650.00 | $4,750.00 | |
| 38 | Adjusting manholes (479-7001) | EACH | 28 | $2,548.52 | $2,000.00 | $700.00 | $1,800.00 | $1,800.00 |
| 39 | Removing structure (inlet) (496-7002) | EACH | 1 | $5,000.00 | $2,500.00 | $1,100.00 | $1,200.00 | |
| 40 | Mobilization (500-7001) | LS | 1 | $1,445,367 | $1,000,000 | $1,450,000 | $1,325,000 | $1,404,003 |
| 41 | Barricades, signs and traffic handling (502-7001) | MO | 13 | $20,000 | $95,000 | $50,000 | $45,000 | $65,000 |
| 42 | Portable changeable message sign (503-7002) | EACH | 2 | $25,000 | $15,000 | $25,000 | $25,000 | $17,000 |
| 43 | TMA (stationary) (505-7001) | DAY | 454 | $373.18 | $1.00 | $150.00 | $150.00 | $1.00 |
| 44 | TMA (mobile operation) (505-7003) | DAY | 79 | $380.94 | $1.00 | $150.00 | $250.00 | $1.00 |
| 45 | Temporary sediment control fence (install) (506-7039) | LF | 9,393 | $1.00 | $3.25 | $3.80 | $4.20 | |
| 46 | Temporary sediment control fence (remove) (506-7041) | LF | 9,393 | $1.00 | $1.75 | $1.30 | $1.40 | |
| 47 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 1,500 | $7.18 | $1.00 | $5.00 | $6.60 | $7.50 |
| 48 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,500 | $2.80 | $1.00 | $2.25 | $1.70 | $1.80 |
| 49 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 1,360 | $40.00 | $45.00 | $50.00 | $44.00 | |
| 50 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 120 | $60.00 | $70.00 | $75.00 | $65.00 | |
| 51 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 1,360 | $15.00 | $17.00 | $18.00 | $16.00 | |
| 52 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 120 | $20.00 | $23.00 | $24.00 | $22.00 | |
| 53 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 1,360 | $20.00 | $23.00 | $24.00 | $22.00 | |
| 54 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 120 | $30.00 | $34.00 | $35.00 | $33.00 | |
| 55 | Concrete curb (type II) (529-7002) | LF | 1,882 | $45.50 | $32.00 | $36.00 | $43.50 | $43.00 |
| 56 | Concrete curb (mono) (type II) (529-7007) | LF | 22 | $25.00 | $28.00 | $11.00 | $11.00 | |
| 57 | Concrete curb & gutter (type II) (529-7009) | LF | 9,389 | $43.00 | $60.00 | $48.70 | $50.00 | |
| 58 | Concrete curb (dowel) (529-7014) | LF | 55 | $35.00 | $55.00 | $60.00 | $27.70 | $28.00 |
| 59 | Concrete curb & gutter (armor curb) (529-7018) | LF | 462 | $215.00 | $240.00 | $245.00 | $243.00 | |
| 60 | Driveways (concrete) (530-7006) | SY | 795 | $90.00 | $120.00 | $121.50 | $125.00 | |
| 61 | Concrete sidewalks (4") (531-7001) | SY | 5,903 | $72.00 | $90.00 | $88.50 | $90.00 | |
| 62 | Curb ramps (type 1) (531-7015) | SY | 77 | $150.00 | $370.00 | $385.00 | $387.00 | |
| 63 | Curb ramps (type 2) (531-7016) | SY | 94 | $100.00 | $290.00 | $385.00 | $387.00 | |
| 64 | Curb ramps (type 3) (531-7017) | SY | 14 | $275.00 | $400.00 | $385.00 | $387.00 | |
| 65 | Curb ramps (type 7) (531-7020) | SY | 84 | $100.00 | $390.00 | $321.00 | $321.00 | |
| 66 | Curb ramps (type 10) (531-7021) | SY | 62 | $300.00 | $360.00 | $321.00 | $321.00 | |
| 67 | Concrete sidewalks (special) (531-7025) | SY | 298 | $115.00 | $280.00 | $285.00 | $282.00 | |
| 68 | Pipe underdrains (type 6) (6") (556-7006) | LF | 1,306 | $45.00 | $50.00 | $49.80 | $50.00 | |
| 69 | Ground box type D (162922)W/apron (624-7008) | EACH | 1 | $1,651.92 | $7,000.00 | $7,000.00 | $7,000.00 | $6,900.00 |
| 70 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 8 | $600.00 | $600.00 | $700.00 | $745.00 | |
| 71 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 2 | $1,000.00 | $900.00 | $1,000.00 | $850.00 | |
| 72 | Remove SM RD SN sup&AM (644-7073) | EACH | 10 | $100.00 | $130.00 | $140.00 | $100.00 | |
| 73 | Install object marker assembly (OM-3L)(TWT)GND (658-7066) | EACH | 1 | $400.00 | $550.00 | $579.00 | $330.00 | |
| 74 | Remove delin & object marker assms (658-7078) | EACH | 1 | $25.00 | $70.00 | $75.00 | $28.00 | |
| 75 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 26,970 | $2.23 | $0.30 | $0.40 | $0.40 | $0.35 |
| 76 | Work zone pavement marking non-removing (W)6"(DOT) (662-7006) | LF | 470 | $1.52 | $0.90 | $1.00 | $1.00 | $1.10 |
| 77 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 102,372 | $1.27 | $0.27 | $0.40 | $0.35 | $0.32 |
| 78 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 11,738 | $1.54 | $0.55 | $0.70 | $0.64 | $0.62 |
| 79 | Work zone pavement marking non-removing (W)12"(solid) (662-7015) | LF | 500 | $6.00 | $1.00 | $2.00 | $1.94 | $1.10 |
| 80 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 7,428 | $7.31 | $2.50 | $3.00 | $3.04 | $2.75 |
| 81 | Work zone pavement marking non-removing (W)(arrow) (662-7018) | EACH | 116 | $115.85 | $49.00 | $90.00 | $83.04 | $60.00 |
| 82 | Work zone pavement marking non-removing(W)(word) (662-7030) | EACH | 112 | $138.68 | $40.00 | $100.00 | $94.11 | $48.00 |
| 83 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 189,582 | $0.73 | $0.27 | $0.40 | $0.35 | $0.33 |
| 84 | Work zone pavement marking removing (reflectorized) type I-C (662-7049) | EACH | 2,140 | $5.80 | $3.50 | $5.00 | $4.93 | $5.00 |
| 85 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 3,026 | $4.96 | $3.50 | $5.00 | $4.93 | $5.00 |
| 86 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 235 | $2.15 | $0.80 | $0.90 | $0.89 | $0.88 |
| 87 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 5,869 | $2.24 | $0.85 | $1.00 | $1.00 | $0.93 |
| 88 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 250 | $5.31 | $3.00 | $3.50 | $3.32 | $3.30 |
| 89 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 3,714 | $11.43 | $6.00 | $7.00 | $6.64 | $6.50 |
| 90 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 58 | $200.31 | $139.00 | $160.00 | $154.99 | $151.00 |
| 91 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 56 | $246.17 | $155.00 | $190.00 | $188.20 | $169.00 |
| 92 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 13,485 | $3.00 | $0.60 | $0.80 | $0.74 | $0.65 |
| 93 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 51,186 | $2.34 | $0.56 | $0.70 | $0.64 | $0.61 |
| 94 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 94,791 | $2.02 | $0.55 | $0.70 | $0.64 | $0.60 |
| 95 | Reflectorized pavement marker type I-C (672-7002) | EACH | 970 | $6.77 | $4.00 | $4.25 | $4.04 | $4.40 |
| 96 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,513 | $19.71 | $4.00 | $4.25 | $4.04 | $4.40 |
| 97 | Remove traffic signal (690-7100) | EACH | 1 | $3,500.00 | $20,000 | $6,000.00 | $5,500.00 | $5,500.00 |
| 98 | Drain inlet cleaning (764-7001) | EACH | 42 | $521.75 | $500.00 | $1,300.00 | $1,100.00 | $1,150.00 |
| 99 | Rais and underseal concrete SLBS W foam sys (3010-7001) | LB | 61,365 | $7.50 | $3.85 | $4.50 | $4.50 | $4.70 |
| 100 | VDS prosr sys (6017-7001) | EACH | 1 | $11,893 | $5,000.00 | $3,400.00 | $3,300.00 | $3,300.00 |
| 101 | VDS atspm (6017-7010) | EACH | 1 | $2,500.00 | $5,000.00 | $3,400.00 | $3,300.00 | $3,300.00 |
| 102 | VDS cabling (6017-7012) | LF | 950 | $3.00 | $10.00 | $5.00 | $5.30 | $5.25 |
| 103 | VDS (HVDS) (VIVDS and RVDS) (6017-7014) | EACH | 3 | $26,082 | $5,000.00 | $4,000.00 | $4,000.00 | $4,000.00 |
| 104 | Highway traffic signals (cofw) (6040-7001) | EACH | 1 | $55,000 | $50,000 | $85,000 | $89,000 | $90,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 4, 2025. Compiled by Mirage Metrics.