TxDOT contract A00132096 bid tabulation
Widen Road - Add Lanes, SH 137 (US 62 to Dawson County Line). Let by Texas DOT on October 9, 2025, Terry, Lubbock District. 5 bids received; low bid $22,303,962 by A. L. Helmcamp, Inc., -20% against the engineer's estimate of $27,831,213.
- Owner
- Texas DOT
- Letting
- 09 OCT 2025
- Pay items
- 90
- Data through
- 19 NOV 2026
4 of the 5 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | A. L. Helmcamp, Inc. | $22,303,962 | Low | -20% |
| 2 | Duininck, Inc. | $22,737,174 | +2.0% | -18% |
| 3 | James Hamilton Construction Co. | $23,457,089 | +5.0% | -16% |
| 5 | Kiewit Infrastructure South Co. | $28,823,132 | +29% | +4.0% |
Engineer's estimate: $27,831,213.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. A. L. Helmcamp, Inc. | 2. Duininck, Inc. | 3. James Hamilton Construction Co. | 4. Kiewit Infrastructure South Co. |
|---|---|---|---|---|---|---|---|---|
| 1 | Remove (0"-12") TRT/untrt base & asphalt pavement (105-7052) | SY | 39,522.23 | $11.00 | $2.50 | $4.85 | $1.30 | $3.58 |
| 2 | Subgr widen (DC) (112-7004) | SY | 0 | $4.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 3 | Backfill (type B) (134-7002) | STA | 873.80 | $225.00 | $115.00 | $125.00 | $400.00 | $33.31 |
| 4 | Blading (150-7001) | STA | 873.80 | $180.00 | $115.00 | $52.50 | $300.00 | $32.98 |
| 5 | Prime coat (MC-30) (310-7004) | GAL | 11,433.33 | $6.00 | $5.75 | $4.85 | $4.60 | $5.48 |
| 6 | Emuls asphalt (erosion control)(CSS-1H) (314-7011) | GAL | 186,582.93 | $3.75 | $2.50 | $2.10 | $2.00 | $2.03 |
| 7 | Fog seal (CSS-1H) (315-7004) | GAL | 26,435.10 | $5.00 | $4.00 | $2.10 | $2.40 | $2.31 |
| 8 | D-GR HMA type D sac-B PG70-28 (341-7054) | TON | 27,811.64 | $150.00 | $134.00 | $130.00 | $137.00 | $141.37 |
| 9 | Tack coat (341-7082) | GAL | 0 | $4.50 | $0.00 | $0.00 | $0.00 | $0.00 |
| 10 | D-GR HMA type-B sac-B PG70-28 (341-7083) | TON | 0 | $150.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 11 | Stone-MTRX-asphalt SMA-D sac-A PG76-28 (346-7010) | TON | 46,271.32 | $180.00 | $159.75 | $168.50 | $140.00 | $212.42 |
| 12 | Tack coat (346-7028) | GAL | 17,331.53 | $6.00 | $3.50 | $1.00 | $3.70 | $3.66 |
| 13 | Flexible pavement structure repair(3") (351-7002) | SY | 12,233.20 | $38.00 | $25.00 | $30.00 | $35.00 | $35.11 |
| 14 | Flexible pavement structure repair(6") (351-7005) | SY | 8,155.47 | $60.00 | $62.00 | $60.00 | $80.00 | $72.62 |
| 15 | Planing asphalt concrete pavement(0" to 3") (354-7033) | SY | 26,025 | $3.70 | $3.00 | $3.40 | $3.70 | $3.07 |
| 16 | Cut & restore asphalt paving (400-7008) | SY | 551.02 | $230.00 | $220.00 | $95.00 | $260.00 | $310.50 |
| 17 | Cem stabil BKFL (400-7010) | CY | 380.18 | $290.00 | $270.00 | $275.00 | $360.00 | $512.37 |
| 18 | RC pipe (CL III)(18 in) (464-7003) | LF | 32 | $100.00 | $100.00 | $100.00 | $115.00 | $175.00 |
| 19 | RC pipe (CL III)(24 in) (464-7005) | LF | 1,854 | $150.00 | $100.00 | $125.00 | $165.00 | $162.96 |
| 20 | RC pipe (CL III)(36 in) (464-7009) | LF | 48 | $240.00 | $240.00 | $200.00 | $284.00 | $323.94 |
| 21 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 2 | $1,700.00 | $1,700.00 | $1,900.00 | $2,800.00 | $3,000.00 |
| 22 | Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327) | EACH | 68 | $2,500.00 | $1,800.00 | $2,400.00 | $4,020.00 | $4,000.00 |
| 23 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 4 | $2,900.00 | $2,000.00 | $2,400.00 | $4,020.00 | $3,274.34 |
| 24 | Set (type II) (36 in) (RCP) (4: 1) (C) (467-7366) | EACH | 4 | $4,100.00 | $2,600.00 | $5,500.00 | $6,960.00 | $6,402.08 |
| 25 | Clean existing culverts (480-7001) | EACH | 7 | $2,500.00 | $2,800.00 | $3,000.00 | $5,530.00 | $12,062 |
| 26 | Removing structure (pipe) (496-7037) | EACH | 20 | $850.00 | $1,600.00 | $500.00 | $3,500.00 | $1,766.12 |
| 27 | Mobilization (500-7001) | LS | 1 | $2,530,000 | $1,800,000 | $1,400,000 | $1,881,000 | $2,682,855 |
| 28 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $15,000 | $5,500.00 | $27,000 | $36,000 | $50,000 |
| 29 | Portable changeable message sign (503-7001) | DAY | 682 | $70.00 | $22.00 | $100.00 | $90.00 | $71.07 |
| 30 | TMA (stationary) (505-7001) | DAY | 382 | $200.00 | $260.00 | $250.00 | $320.00 | $508.16 |
| 31 | TMA (mobile operation) (505-7003) | DAY | 40 | $250.00 | $200.00 | $900.00 | $900.00 | $959.09 |
| 32 | Construction exits (install) (type 1) (506-7020) | SY | 222 | $30.00 | $46.00 | $44.00 | $25.00 | $52.25 |
| 33 | Construction exits (remove) (506-7024) | SY | 222 | $10.00 | $19.00 | $18.00 | $5.00 | $21.38 |
| 34 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 7,340 | $8.00 | $9.00 | $9.00 | $7.50 | $10.69 |
| 35 | Biodegradable erosion control logs (remove) (506-7046) | LF | 3,630 | $2.00 | $2.00 | $2.00 | $4.00 | $2.38 |
| 36 | Intersections (ACP) (530-7002) | SY | 6,852 | $115.00 | $31.00 | $36.50 | $52.00 | $67.58 |
| 37 | Driveways (concrete) (530-7006) | SY | 509.17 | $150.00 | $120.00 | $180.00 | $210.00 | $204.31 |
| 38 | Driveways (ACP) (530-7010) | SY | 542.48 | $75.00 | $35.00 | $79.00 | $78.00 | $85.73 |
| 39 | Turnouts (ACP) (530-7018) | SY | 688.40 | $120.00 | $170.00 | $79.50 | $157.00 | $365.46 |
| 40 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 174,760 | $0.18 | $0.20 | $0.11 | $0.20 | $0.07 |
| 41 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 87,380 | $0.19 | $0.20 | $0.12 | $0.24 | $0.10 |
| 42 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 17 | $330.00 | $250.00 | $240.00 | $264.00 | $285.02 |
| 43 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 13 | $350.00 | $290.00 | $275.00 | $302.00 | $326.58 |
| 44 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 7 | $730.00 | $580.00 | $550.00 | $605.00 | $653.16 |
| 45 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 23 | $750.00 | $740.00 | $700.00 | $770.00 | $831.30 |
| 46 | Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002) | EACH | 19 | $850.00 | $840.00 | $800.00 | $880.00 | $950.06 |
| 47 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 47 | $870.00 | $840.00 | $800.00 | $880.00 | $950.06 |
| 48 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 11 | $1,000.00 | $930.00 | $890.00 | $980.00 | $1,056.94 |
| 49 | Install small roadside sign support and assembly TYS80(1)SA(U-1EXT) (644-7032) | EACH | 3 | $1,160.00 | $930.00 | $890.00 | $980.00 | $1,056.94 |
| 50 | Remove SM RD SN sup&AM (644-7073) | EACH | 89 | $110.00 | $110.00 | $100.00 | $110.00 | $118.76 |
| 51 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 40 | $104.00 | $84.00 | $80.00 | $88.00 | $95.01 |
| 52 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 64,225 | $0.40 | $0.20 | $0.17 | $0.22 | $0.24 |
| 53 | Work zone pavement marking non-removing (W)6"(DOT) (662-7006) | LF | 1,800 | $0.90 | $0.30 | $0.23 | $0.28 | $0.30 |
| 54 | Work zone pavement marking non-removing (W)6"(lane drop) (662-7007) | LF | 4,500 | $0.76 | $0.30 | $0.23 | $0.28 | $0.30 |
| 55 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 329,758 | $0.31 | $0.20 | $0.17 | $0.22 | $0.24 |
| 56 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 240 | $4.00 | $11.00 | $3.00 | $11.00 | $11.88 |
| 57 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 412,760 | $0.33 | $0.20 | $0.17 | $0.22 | $0.24 |
| 58 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 19,708 | $1.10 | $1.00 | $1.50 | $1.50 | $2.38 |
| 59 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 20,638 | $1.25 | $1.00 | $1.50 | $1.50 | $2.38 |
| 60 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 653 | $1.32 | $1.00 | $0.98 | $1.10 | $1.19 |
| 61 | Reflectorized pavement marking type I (W)6"(lane drop)(100MIL) (666-7012) | LF | 1,655 | $1.15 | $1.00 | $0.98 | $1.10 | $1.19 |
| 62 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 10,830 | $0.85 | $0.70 | $0.68 | $0.68 | $0.74 |
| 63 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 171,076 | $0.70 | $0.60 | $0.68 | $0.63 | $0.68 |
| 64 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 174,328 | $0.70 | $0.60 | $0.68 | $0.63 | $0.68 |
| 65 | Prefabricated PM type B (W)(6")(DOT) (668-7010) | LF | 9 | $10.15 | $11.00 | $25.00 | $11.00 | $11.88 |
| 66 | Prefabricated PM type B (W)(24")(solid) (668-7021) | LF | 26 | $35.19 | $37.00 | $40.00 | $38.50 | $41.57 |
| 67 | Prefabricated PM type B (Y)(6")(solid) (668-7051) | LF | 354 | $7.19 | $11.00 | $9.50 | $11.00 | $11.88 |
| 68 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 525 | $22.80 | $14.00 | $13.00 | $14.30 | $15.44 |
| 69 | Prefabricated PM type C (W)(LN reduct arrow) (668-7100) | EACH | 10 | $455.00 | $630.00 | $650.00 | $660.00 | $712.54 |
| 70 | Reflectorized pavement marker type I-C (672-7002) | EACH | 556 | $3.74 | $5.00 | $4.25 | $4.95 | $5.34 |
| 71 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 2,180 | $4.25 | $4.00 | $3.75 | $4.40 | $4.75 |
| 72 | Eliminating existing PM & markers (4") (677-7001) | LF | 528,160 | $0.32 | $0.60 | $0.55 | $0.20 | $0.77 |
| 73 | Eliminating existing PM & markers (6") (677-7002) | LF | 389 | $0.40 | $1.00 | $0.65 | $0.94 | $1.01 |
| 74 | Eliminating existing PM & markers (24") (677-7008) | LF | 273 | $3.57 | $1.00 | $6.00 | $3.85 | $4.16 |
| 75 | Pavement surface preparation for marking (6") (678-7002) | LF | 389 | $0.10 | $2.00 | $0.55 | $2.20 | $2.38 |
| 76 | Pavement surface preparation for marking (24") (678-7008) | LF | 26 | $1.20 | $5.00 | $5.00 | $5.50 | $5.94 |
| 77 | Temporary traffic signals (681-7001) | EACH | 2 | $87,100 | $16,300 | $20,000 | $8,500.00 | $8,927.92 |
| 78 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 2 | $315.00 | $420.00 | $400.00 | $1,320.00 | $475.03 |
| 79 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 2 | $317.00 | $420.00 | $400.00 | $1,320.00 | $475.03 |
| 80 | Install RDSD FLSH BCN assembly (solar PWRD) (685-7004) | EACH | 2 | $8,300.00 | $10,400 | $9,900.00 | $10,890 | $11,757 |
| 81 | Removing RDSD FLSH BCN AM (solar PWRD) (685-7006) | EACH | 2 | $1,825.00 | $790.00 | $755.00 | $830.00 | $896.62 |
| 82 | Full - width mowing (730-7019) | CYC | 2 | $10,000 | $8,500.00 | $4,800.00 | $4,620.00 | $20,764 |
| 83 | Litter removal (734-7002) | CYC | 2 | $4,000.00 | $8,900.00 | $4,100.00 | $3,300.00 | $14,927 |
| 84 | Reinforced fab for asphalt PVMNT overlays (3002-7001) | SY | 325,381.67 | $6.50 | $6.00 | $6.30 | $6.50 | $7.70 |
| 85 | Asphalt for reinforced fab (PG76-28) (3002-7002) | GAL | 48,807.25 | $5.00 | $4.25 | $2.60 | $4.20 | $3.44 |
| 86 | Temporary speed monitor sys (6016-7001) | EACH | 2 | $12,700 | $15,300 | $7,500.00 | $20,500 | $19,131 |
| 87 | Subgr widen (DC) (112-7004) | SY | 60,025 | $4.00 | $2.00 | $3.30 | $5.40 | $6.07 |
| 88 | FL BS (compacted in place)(type A GR 4) (6") (247-7046) | SY | 57,166.67 | $25.01 | $14.00 | $15.60 | $11.30 | $16.45 |
| 89 | Tack coat (341-7082) | GAL | 67,769.97 | $4.50 | $1.00 | $1.00 | $3.70 | $3.66 |
| 90 | D-GR HMA type-B sac-B PG70-28 (341-7083) | TON | 15,284.94 | $150.00 | $130.00 | $137.50 | $137.00 | $132.66 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of October 9, 2025. Compiled by Mirage Metrics.