TxDOT contract A00140549 bid tabulation
Rehabilitate Existing Roadway, FM 2100 (San Jacinto River Authority Canal to S of BU 90-U). Let by Texas DOT on April 7, 2026, Harris, Houston District. 4 bids received; low bid $1,798,696 by Forde Construction Company, Inc., +14% against the engineer's estimate of $1,578,950.
- Owner
- Texas DOT
- Letting
- 07 APR 2026
- Pay items
- 69
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Forde Construction Company, Inc. | $1,798,696 | Low | +14% |
| 2 | Texas Materials Group, Inc. | $1,824,787 | +1.0% | +16% |
| 3 | Environmental Allies, Inc. | $1,909,875 | +6.0% | +21% |
| 4 | Durwood Greene Construction Co. | $1,948,559 | +8.0% | +23% |
Engineer's estimate: $1,578,950.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Forde Construction Company, Inc. | 2. Texas Materials Group, Inc. | 3. Environmental Allies, Inc. | 4. Durwood Greene Construction Co. |
|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7003) | SY | 26 | $32.00 | $160.00 | $188.00 | $40.00 | $150.00 |
| 2 | Asphalt (AC-20-5TR or AC-20XP) (316-7067) | GAL | 16,328 | $4.00 | $3.20 | $4.00 | $4.25 | $4.25 |
| 3 | Aggregate (type-PB or PL, GR-4)(sac-B) (316-7245) | CY | 349 | $155.00 | $250.00 | $313.00 | $290.00 | $290.00 |
| 4 | SP mixes SP-D sac-A PG76-22 (344-7064) | TON | 3,742 | $135.00 | $153.00 | $169.00 | $168.00 | $183.00 |
| 5 | Flexible pavement structure repair(12") (351-7011) | SY | 1,766 | $120.00 | $110.00 | $132.00 | $135.00 | $110.00 |
| 6 | Planing asphalt concrete pavement (1.5") (354-7074) | SY | 45,357 | $1.20 | $3.75 | $3.00 | $2.50 | $4.00 |
| 7 | Full - depth repair CRCP (10") (361-7005) | CY | 17 | $800.00 | $1,250.00 | $1,635.00 | $1,500.00 | $850.00 |
| 8 | Riprap (mow strip)(4 in) (432-7013) | CY | 27 | $650.00 | $900.00 | $1,050.00 | $900.00 | $1,100.00 |
| 9 | Mobilization (500-7001) | LS | 1 | $140,000 | $122,000 | $115,000 | $102,000 | $100,000 |
| 10 | Barricades, signs and traffic handling (502-7001) | MO | 4 | $6,000.00 | $22,000 | $7,450.00 | $8,000.00 | $4,000.00 |
| 11 | Portable changeable message sign (503-7001) | DAY | 28 | $150.00 | $250.00 | $50.00 | $150.00 | $300.00 |
| 12 | TMA (stationary) (505-7001) | DAY | 43 | $250.00 | $200.00 | $450.00 | $250.00 | $300.00 |
| 13 | TMA (mobile operation) (505-7003) | DAY | 9 | $200.00 | $200.00 | $650.00 | $450.00 | $250.00 |
| 14 | Metal W-beam guard fence (timber post) (540-7001) | LF | 450 | $28.00 | $32.00 | $29.00 | $30.00 | $23.25 |
| 15 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 2 | $2,000.00 | $2,300.00 | $1,995.00 | $2,500.00 | $1,965.00 |
| 16 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,200.00 | $1,300.00 | $2,185.00 | $1,600.00 | $1,450.00 |
| 17 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 25 | $70.00 | $117.00 | $265.00 | $95.00 | $85.00 |
| 18 | Remove metal beam guard fence (542-7001) | LF | 450 | $3.00 | $3.30 | $4.50 | $4.40 | $4.00 |
| 19 | Remove terminal anchor section (542-7002) | EACH | 2 | $250.00 | $245.00 | $550.00 | $440.00 | $350.00 |
| 20 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 2 | $325.00 | $290.00 | $550.00 | $245.00 | $200.00 |
| 21 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $2,400.00 | $3,800.00 | $2,350.00 | $3,500.00 | $3,085.00 |
| 22 | Guardrail end treatment (remove) (544-7003) | EACH | 4 | $300.00 | $368.00 | $275.00 | $300.00 | $250.00 |
| 23 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 330 | $18.00 | $27.00 | $20.00 | $21.00 | $19.00 |
| 24 | Conduit (prepare) (618-7090) | LF | 35 | $1.70 | $1.10 | $5.00 | $12.00 | $1.00 |
| 25 | Electrical conductor (no.8) bare (620-7007) | LF | 330 | $1.80 | $1.60 | $1.75 | $2.50 | $2.00 |
| 26 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 6 | $20.00 | $26.00 | $56.50 | $30.00 | $25.00 |
| 27 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 5 | $25.00 | $33.00 | $56.50 | $35.00 | $32.50 |
| 28 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 11,940 | $0.35 | $0.30 | $0.35 | $0.65 | $0.30 |
| 29 | Work zone pavement marking non-removing (W)6"(DOT) (662-7006) | LF | 121 | $0.90 | $0.27 | $0.30 | $1.00 | $0.25 |
| 30 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 22,760 | $0.30 | $0.30 | $0.35 | $0.65 | $0.30 |
| 31 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 2,260 | $0.70 | $0.50 | $0.55 | $1.25 | $0.50 |
| 32 | Work zone pavement marking non-removing (W)(arrow) (662-7018) | EACH | 24 | $95.00 | $79.00 | $85.00 | $175.00 | $75.00 |
| 33 | Work zone pavement marking non-removing (W)(double arrow) (662-7019) | EACH | 6 | $110.00 | $90.00 | $95.00 | $220.00 | $85.00 |
| 34 | Work zone pavement marking non-removing(W)(word) (662-7030) | EACH | 28 | $90.00 | $79.00 | $85.00 | $165.00 | $75.00 |
| 35 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 4,380 | $0.30 | $0.30 | $0.35 | $0.65 | $0.30 |
| 36 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 27,350 | $0.30 | $0.30 | $0.35 | $0.65 | $0.30 |
| 37 | Work zone pavement marking non-removing (Y)12"(solid) (662-7040) | LF | 180 | $1.50 | $0.95 | $1.00 | $4.50 | $1.00 |
| 38 | Work zone pavement marking removing (reflectorized) type I-C (662-7049) | EACH | 714 | $4.00 | $4.50 | $5.00 | $6.60 | $4.25 |
| 39 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 8,906 | $3.50 | $4.50 | $4.75 | $6.60 | $4.25 |
| 40 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 1,526 | $1.15 | $2.10 | $0.55 | $2.00 | $1.90 |
| 41 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 2,544 | $0.55 | $2.10 | $0.55 | $2.00 | $1.40 |
| 42 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,130 | $1.50 | $1.05 | $1.00 | $1.50 | $1.00 |
| 43 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 1,867 | $8.00 | $6.30 | $7.00 | $8.80 | $6.20 |
| 44 | Reflectorized pavement marking type III (W)(6")(solid) (666-7236) | LF | 213 | $0.70 | $1.70 | $1.80 | $3.50 | $1.60 |
| 45 | Reflectorized pavement marking type III (W)(6")(broken) (666-7237) | LF | 3,110 | $0.90 | $1.00 | $1.00 | $2.25 | $0.95 |
| 46 | Reflectorized pavement marking type III (W)(12")(solid) (666-7242) | LF | 16 | $3.00 | $6.30 | $7.00 | $10.00 | $6.00 |
| 47 | Reflectorized pavement marking type III (W)(24")(solid) (666-7244) | LF | 348 | $8.00 | $15.50 | $17.00 | $17.50 | $15.00 |
| 48 | Reflectorized pavement marking type III (Y)(6")(solid) (666-7248) | LF | 1,256 | $1.50 | $1.00 | $1.00 | $2.25 | $0.95 |
| 49 | Reflectorized pavement marking type III (Y)(6")(broken) (666-7249) | LF | 310 | $0.90 | $1.70 | $1.80 | $4.50 | $1.60 |
| 50 | Reflectorized pavement marking type III (Y)(12")(solid) (666-7252) | LF | 198 | $4.00 | $6.40 | $6.75 | $10.00 | $6.00 |
| 51 | Reflectorized pavement marking type III (BLK)(6")(shadow) (666-7262) | LF | 3,110 | $0.80 | $1.05 | $1.15 | $2.25 | $1.02 |
| 52 | All-wther PM type I (W)6"(solid)(100MIL) (666-7309) | LF | 11,256 | $0.90 | $0.88 | $0.95 | $1.15 | $0.82 |
| 53 | All-wther PM type I (W)6"(broken)(100MIL) (666-7310) | LF | 2,860 | $0.80 | $0.95 | $1.00 | $1.15 | $0.90 |
| 54 | All-wther PM type I (W)6"(DOT)(100MIL) (666-7311) | LF | 60 | $5.00 | $0.95 | $1.00 | $1.15 | $0.90 |
| 55 | All-wther PM type I (Y)6"(solid)(100MIL) (666-7315) | LF | 11,136 | $0.90 | $0.88 | $0.95 | $1.15 | $0.82 |
| 56 | All-wther PM type I (Y)6"(broken)(100MIL) (666-7316) | LF | 1,710 | $0.90 | $0.95 | $1.00 | $1.15 | $0.90 |
| 57 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 18 | $200.00 | $264.00 | $280.00 | $300.00 | $250.00 |
| 58 | Prefabricated PM type C (W)(LN reduct arrow) (668-7100) | EACH | 1 | $500.00 | $529.00 | $565.00 | $550.00 | $500.00 |
| 59 | Prefabricated PM type C (W)(number) (668-7102) | EACH | 2 | $200.00 | $132.00 | $141.00 | $260.00 | $125.00 |
| 60 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 18 | $275.00 | $265.00 | $280.00 | $315.00 | $250.00 |
| 61 | Reflectorized pavement marker type I-C (672-7002) | EACH | 361 | $5.00 | $6.30 | $6.75 | $7.75 | $6.00 |
| 62 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 453 | $5.00 | $6.30 | $6.75 | $7.75 | $6.00 |
| 63 | Ins traffic signal PL AM (S)lum arm(10') (686-7004) | EACH | 4 | $200.00 | $1,700.00 | $2,400.00 | $2,250.00 | $1,995.00 |
| 64 | Continuous grinding-concrete pavement (3017-7001) | SY | 19,250 | $12.00 | $8.50 | $6.40 | $9.00 | $13.57 |
| 65 | VIVDS prosr sys (6006-7001) | EACH | 3 | $5,000.00 | $12,200 | $14,000 | $4,025.00 | $12,750 |
| 66 | VIVDS cam assy FXD LNS (6006-7002) | EACH | 12 | $4,000.00 | $2,290.00 | $2,665.00 | $6,250.00 | $2,750.00 |
| 67 | VIVDS CNTRL software (6006-7005) | EACH | 1 | $650.00 | $1,720.00 | $750.00 | $775.00 | $900.00 |
| 68 | VIVDS cabling (6006-7007) | LF | 2,220 | $2.60 | $3.80 | $2.35 | $3.50 | $2.00 |
| 69 | Ground box (prepare) (6013-7006) | EACH | 6 | $400.00 | $246.00 | $360.00 | $400.00 | $600.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.