TxDOT contract A00141242 bid tabulation

Surfacing/Roadway Restoration, SH 87 (Seawall Blvd. to Galveston Ferry Boat Landing). Let by Texas DOT on January 7, 2025, Galveston, Houston District. 2 bids received; low bid $7,342,374 by Texas Materials Group, Inc., -20% against the engineer's estimate of $9,151,363.

Owner
Texas DOT
Letting
07 JAN 2025
Pay items
106
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Texas Materials Group, Inc.$7,342,374Low-20%
2Durwood Greene Construction Co.$7,797,944+6.0%-15%
TxDOT contract A00141242: bids by rank

Engineer's estimate: $9,151,363.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Texas Materials Group, Inc.2. Durwood Greene Construction Co.
1Removing concrete (driveways) (104-7011)SY175$35.00$22.00$60.00
2Removing concrete (sidewalk, ramp or shared use path) (104-7013)SY113$50.00$22.00$50.00
3Removing concrete (curb or curb & gutter) (104-7018)LF25$42.27$11.12$25.00
4Excavation (roadway) (110-7001)CY889$33.30$50.00$50.00
5Block sodding (162-7002)SY1,143$5.15$5.00$7.00
6Fertilizer (166-7001)ACRE2$1,295.00$1,100.00$1,000.00
7Vegetative watering (168-7001)TGL51$43.00$140.00$50.00
8Salvage, haul & stockpile reclaimed asphalt PV (3") (305-7016)SY13,000$2.00$0.25$2.50
9D-GR HMA type D PG70-22 (level-UP) (341-7051)TON5,414$200.00$231.00$160.00
10D-GR HMA type D sac-A PG76-22 (341-7057)TON5,414$175.29$244.00$170.00
11Flexible pavement structure repair(14") (351-7013)SY13,000$95.00$149.00$85.00
12Planing asphalt concrete pavement(3") (354-7052)SY65,626$4.13$0.25$6.00
13Drilled shaft (traffic signal pole) (36 in) (416-7044)LF185$490.00$429.00$500.00
14Inlet(complete)(type C1)(stage II) (465-7348)EACH13$4,440.00$3,400.00$6,900.00
15Adjusting manholes (479-7001)EACH32$2,250.00$1,100.00$2,500.00
16Adjusting manholes (utility box) (479-7004)EACH27$1,285.00$1,100.00$2,800.00
17Removing structure (inlet) (496-7002)EACH13$192.05$330.00$2,300.00
18Mobilization (500-7001)LS1$805,716$613,000$780,000
19Barricades, signs and traffic handling (502-7001)MO10$9,520.48$3,800.00$17,000
20Portable changeable message sign (503-7001)DAY600$190.00$45.00$350.00
21TMA (stationary) (505-7001)DAY350$277.43$132.00$300.00
22TMA (mobile operation) (505-7003)DAY150$388.43$286.00$175.00
23Sandbags for erosion control (506-7035)EACH248$10.00$44.00$15.00
24Biodegradable erosion control logs (install) (12") (506-7044)LF5,142$8.49$5.50$7.00
25Biodegradable erosion control logs (remove) (506-7046)LF5,142$2.75$1.00$1.50
26Concrete curb (type II) (529-7002)LF2,267$30.00$9.00$45.00
27Concrete curb (slotted) (529-7013)LF3,193$32.25$9.00$45.00
28Driveways (concrete) (hes) (530-7007)SY169$159.00$88.00$240.00
29Driveways (ACP) (530-7010)SY2,447$78.33$29.00$110.00
30Concrete sidewalks (5") (531-7002)SY3,472$139.00$82.50$125.00
31Curb ramps (type 10) (531-7011)EACH41$2,692.00$2,000.00$3,500.00
32Concrete directional island (536-7004)SY1,301$1,301.00$68.00$140.00
33Concrete directional island (12") (536-7007)LF531$46.00$22.00$70.00
34Conduit (PVC) (schedule 80) (2") (618-7054)LF385$22.00$11.12$12.00
35Conduit (PVC) (schedule 80) (2") (bore) (618-7055)LF345$15.75$15.00$17.00
36Conduit (PVC) (schedule 80) (3") (618-7060)LF285$16.75$31.00$32.00
37Conduit (PVC) (schedule 80) (3") (bore) (618-7061)LF535$50.00$35.00$40.00
38Conduit (PVC) (schedule 80) (4") (618-7064)LF110$45.00$42.00$44.00
39Conduit (PVC) (schedule 80) (4") (bore) (618-7065)LF190$55.00$46.00$48.00
40Conduit (RM) (3") (618-7082)LF30$65.00$121.00$135.00
41Electrical conductor (no.10) insulated (620-7006)LF2,540$2.75$2.00$2.50
42Electrical conductor (no.8) bare (620-7007)LF1,755$3.00$3.00$4.00
43Electrical conductor (no.4) insulated (620-7012)LF430$3.50$6.00$6.00
44Tray cable (3 conductor) (12 AWG) (621-7002)LF2,165$3.50$4.00$4.50
45Tray cable (4 conductor) (12 AWG) (621-7006)LF2,530$3.50$4.00$5.00
46Ground box type D (162922)W/apron (624-7008)EACH23$2,000.00$1,100.00$1,500.00
47Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148)EACH4$10,000$10,400$11,500
48Aluminum signs (type A) (636-7001)SF11$45.00$31.00$35.00
49Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH14$850.00$500.00$563.44
50Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007)EACH1$850.00$760.00$866.25
51Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009)EACH126$850.00$680.00$775.00
52Relocate SM RD SN sup&AM type S80 (644-7067)EACH11$867.09$520.00$593.75
53Remove SM RD SN sup&AM (sign only) (644-7075)EACH3$1,200.00$39.00$43.75
54Work zone pavement marking non-removing (W)6"(broken) (662-7005)LF3,925$1.00$0.60$0.39
55Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF21,049$1.00$0.50$0.39
56Work zone pavement marking non-removing (W)8"(solid) (662-7012)LF1,847$1.00$1.20$0.75
57Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF1,641$9.00$5.00$3.00
58Work zone pavement marking non-removing (W)(arrow) (662-7018)EACH35$115.10$105.00$100.00
59Work zone pavement marking non-removing(W)(word) (662-7030)EACH10$112.02$115.00$120.00
60Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF20,562$3.00$0.50$0.39
61Work zone pavement marking non-removing (Y)24"(solid) (662-7042)LF1,006$1.00$5.00$3.00
62Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF1,847$1.90$2.00$1.00
63Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF1,641$4.00$9.00$7.00
64Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042)EACH35$50.00$187.00$200.00
65Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066)EACH10$50.00$192.00$225.00
66Ref pavement marking type I(W)36"(yld tri)(100MIL) (666-7090)EACH8$50.00$45.00$35.00
67Reflectorized pavement marking type I (Y)24"(solid)(100MIL) (666-7123)LF1,006$8.00$9.00$7.00
68Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF3,925$1.50$1.00$0.60
69Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF21,049$5.00$0.85$0.75
70Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF20,562$0.50$0.85$0.75
71Reflectorized pavement marker type II-A-A (672-7004)EACH512$10.00$6.00$6.00
72Reflectorized pavement marker type II-C-R (672-7006)EACH240$7.40$6.00$6.00
73Install highway traffic signal (system) (680-7003)EACH4$50,000$35,200$36,000
74Removing traffic signals (680-7004)EACH4$10,000$5,100.00$5,500.00
75Vehicle signal section (12")LED(green) (682-7001)EACH28$400.00$308.00$330.00
76Vehicle signal section (12")LED(green arrow) (682-7002)EACH5$400.00$308.00$330.00
77Vehicle signal section (12")LED(yel) (682-7003)EACH32$400.00$308.00$330.00
78Vehicle signal section (12")LED(yel arrow) (682-7004)EACH3$400.00$308.00$330.00
79Vehicle signal section (12")LED(red) (682-7005)EACH30$400.00$308.00$330.00
80Vehicle signal section (12")LED(red arrow) (682-7006)EACH4$400.00$308.00$330.00
81Pedestrian signal section (LED)(countdown) (682-7018)EACH10$1,000.00$935.00$1,100.00
82Backplate W/reflectorized border(4 sec) (682-7037)EACH5$300.00$265.00$280.00
83Backplate W/reflectorized border (1SEC) (682-7048)EACH2$150.00$200.00$220.00
84Backplate W/reflectorized border(3 sec) (682-7054)EACH28$200.00$242.00$250.00
85Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007)LF2,620$2.00$2.50$2.75
86Traffic signal CBL (type A)(12 AWG)(4 conductor) (684-7009)LF2,585$3.00$2.78$3.00
87Traffic signal CBL (type A)(12 AWG)(7 conductor) (684-7012)LF5,585$4.00$3.00$3.40
88Install RDSD FLSH BCN assembly (solar PWRD) (685-7004)EACH1$10,000$12,000$12,900
89Ins traffic signal PL AM (S)1 arm(20') (686-7021)EACH1$10,000$13,000$12,900
90Ins traffic signal PL AM (S)1 arm(20')ilsn (686-7022)EACH1$10,000$14,700$15,700
91Ins traffic signal PL AM(S)1 arm(20')lum&ilsn (686-7024)EACH2$9,500.00$16,200$16,900
92Ins traffic signal PL AM(S)1 arm(24')lum&ilsn (686-7028)EACH1$10,500$17,500$18,300
93Ins traffic signal PL AM(S)1 arm(32')lum&ilsn (686-7036)EACH5$11,500$18,500$22,300
94Ins traffic signal PL AM(S)1 arm(36')lum&ilsn (686-7040)EACH2$14,500$19,000$23,900
95Ins traffic signal PL AM(S)1 arm(40')lum&ilsn (686-7044)EACH1$16,500$20,100$25,900
96Ins traffic signal PL AM(S)1 arm(44')lum&ilsn (686-7048)EACH2$17,500$21,000$27,000
97Pedestrian pole assembly (687-7001)EACH13$2,500.00$2,400.00$2,500.00
98Pedestrian detect push button (APS) (688-7001)EACH13$2,850.00$1,050.00$1,100.00
99Pedestrian detector controller unit (688-7003)EACH3$1,200.00$4,200.00$4,400.00
100Full - width mowing (730-7019)CYC10$32.86$3,100.00$3,200.00
101Tree removal (24" - 30" diameter) (752-7008)EACH2$397.48$2,500.00$4,000.00
102Underseal course (3006-7001)GAL21,000$4.00$4.00$9.75
103VIVDS prosr sys (install only) (6006-7009)EACH4$475.00$220.00$500.00
104VIVDS cam assy (install only) (6006-7010)EACH13$2,000.00$660.00$750.00
105VIVDS cabling (install only) (6006-7012)LF2,450$3.50$2.78$3.00
106Bbu system (external battery cabinet) (6007-7001)EACH5$10,000$9,500.00$9,300.00
TxDOT contract A00141242: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of January 7, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy