TxDOT contract A00184576 bid tabulation
Hazard Elimination & Safety, ALAMO PKWY N (Alamo Pkwy from 0.1 Mi N of Wild Pine/Ro to 0.1 mi S of Wild Pine/Rockwall Mill). Let by Texas DOT on April 3, 2025, Bexar, San Antonio District. 3 bids received; low bid $689,689 by E-Z Bel Construction, LLC, -21% against the engineer's estimate of $878,041.
- Owner
- Texas DOT
- Letting
- 03 APR 2025
- Pay items
- 105
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | E-Z Bel Construction, LLC | $689,689 | Low | -21% |
| 2 | Elecnor Belco Electric, Inc. | $818,268 | +19% | -7.0% |
| 3 | The Levy Company, Inc. | $834,148 | +21% | -5.0% |
Engineer's estimate: $878,041.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. E-Z Bel Construction, LLC | 2. Elecnor Belco Electric, Inc. | 3. The Levy Company, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 178 | $25.00 | $25.00 | $57.00 | $55.00 |
| 2 | Removing concrete (curb) (104-7016) | LF | 262 | $24.00 | $15.00 | $33.00 | $35.00 |
| 3 | Drilled shaft (30 in) (416-7005) | LF | 11.30 | $300.00 | $350.00 | $375.00 | $472.92 |
| 4 | Drilled shaft (36 in) (416-7006) | LF | 39.60 | $325.00 | $425.00 | $402.00 | $531.50 |
| 5 | Mobilization (500-7001) | LS | 1 | $114,401 | $28,852 | $74,000 | $83,415 |
| 6 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $10,000 | $2,500.00 | $1,992.00 | $5,200.43 |
| 7 | Portable changeable message sign (503-7001) | DAY | 77 | $100.00 | $85.00 | $111.00 | $59.38 |
| 8 | TMA (stationary) (505-7001) | DAY | 48 | $220.00 | $215.00 | $285.00 | $61.18 |
| 9 | TMA (mobile operation) (505-7003) | DAY | 16 | $0.01 | $1,138.00 | $61.18 | |
| 10 | Concrete curb (type II) (529-7002) | LF | 291 | $42.00 | $40.00 | $40.00 | $69.00 |
| 11 | Concrete sidewalks (4") (531-7001) | SY | 126 | $66.83 | $110.00 | $179.00 | $88.00 |
| 12 | Curb ramps (type 1) (531-7005) | EACH | 4 | $2,700.00 | $2,900.00 | $4,666.00 | $2,900.00 |
| 13 | Curb ramps (type 2) (531-7006) | EACH | 4 | $2,500.00 | $3,500.00 | $4,666.00 | $2,900.00 |
| 14 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 295 | $20.00 | $18.00 | $26.00 | $23.37 |
| 15 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 445 | $32.00 | $28.00 | $43.00 | $29.86 |
| 16 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 265 | $22.00 | $26.00 | $31.00 | $22.63 |
| 17 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 190 | $34.00 | $35.00 | $60.00 | $50.00 |
| 18 | Conduit (prepare) (618-7090) | LF | 680 | $2.00 | $6.00 | $1.58 | |
| 19 | Electrical conductor (no.8) bare (620-7007) | LF | 2,985 | $1.68 | $2.00 | $1.95 | $1.88 |
| 20 | Electrical conductor (no.6) bare (620-7009) | LF | 350 | $2.00 | $2.00 | $2.48 | $2.36 |
| 21 | Electrical conductor (no.6) insulated (620-7010) | LF | 400 | $2.52 | $2.50 | $2.48 | $2.39 |
| 22 | Ground box type D (162922) (624-7007) | EACH | 2 | $1,159.00 | $1,200.00 | $1,495.00 | $1,400.76 |
| 23 | Ground box type D (162922)W/apron (624-7008) | EACH | 2 | $1,900.00 | $1,500.00 | $1,755.00 | $1,884.51 |
| 24 | Elc SRV type D 120/240 060(NS)AL(E)PS(U) (628-7120) | EACH | 1 | $6,675.00 | $8,500.00 | $7,453.00 | $8,406.91 |
| 25 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 30 | $670.00 | $850.00 | $948.00 | $715.00 |
| 26 | Remove SM RD SN sup&AM (644-7073) | EACH | 28 | $110.00 | $200.00 | $114.00 | $105.00 |
| 27 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 827 | $1.35 | $1.45 | $1.72 | $2.00 |
| 28 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 242 | $8.85 | $10.00 | $9.10 | $10.00 |
| 29 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 8 | $250.00 | $225.00 | $228.00 | $350.00 |
| 30 | Reflectorized pavement marking type I(W)(double arrow)(100MIL) (666-7045) | EACH | 2 | $237.00 | $275.00 | $285.00 | $450.00 |
| 31 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 8 | $237.00 | $225.00 | $285.00 | $450.00 |
| 32 | Pavement sler 4" (666-7346) | LF | 2,763 | $0.32 | $0.30 | $0.58 | $0.45 |
| 33 | Pavement sler 6" (666-7347) | LF | 4,960 | $0.60 | $0.65 | $0.55 | |
| 34 | Pavement sler 8" (666-7348) | LF | 827 | $0.58 | $0.90 | $0.75 | $0.65 |
| 35 | Pavement sler 12" (666-7350) | LF | 1,520 | $1.61 | $1.20 | $2.29 | $1.00 |
| 36 | Pavement sler 24" (666-7352) | LF | 1,197 | $1.82 | $2.40 | $4.56 | $1.50 |
| 37 | Pavement sler (arrow) (666-7353) | EACH | 8 | $42.00 | $40.00 | $100.00 | $25.00 |
| 38 | Pavement sler (word) (666-7354) | EACH | 8 | $42.00 | $40.00 | $100.00 | $25.00 |
| 39 | Pavement sler (med nose) (666-7355) | EACH | 4 | $105.00 | $40.00 | $228.00 | $25.00 |
| 40 | Pavement sler (double arrow) (666-7356) | EACH | 2 | $105.00 | $40.00 | $171.00 | $25.00 |
| 41 | Reflectorized pavement marking type I (W)4"(broken)(100MIL) (666-7402) | LF | 430 | $2.08 | $0.75 | $2.29 | $1.50 |
| 42 | Reflectorized pavement marking type I (W)6"(solid)(060MIL) (666-7409) | LF | 3,380 | $0.85 | $1.32 | $1.25 | |
| 43 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 4,960 | $0.85 | $1.32 | $1.25 | |
| 44 | Reflectorized pavement marking type I (Y)4"(broken)(100MIL) (666-7414) | LF | 60 | $0.75 | $1.32 | $2.00 | |
| 45 | Reflectorized pavement marking type I (Y)4"(solid)(100MIL) (666-7417) | LF | 2,273 | $2.17 | $0.75 | $1.15 | $1.00 |
| 46 | Reflectorized pavement marking type I (Y)6"(solid)(060MIL) (666-7421) | LF | 8,340 | $0.85 | $1.15 | $1.00 | |
| 47 | Prefabricated PM type C (W)(12")(solid) (668-7087) | LF | 1,520 | $10.07 | $6.00 | $10.25 | $6.00 |
| 48 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 760 | $12.00 | $12.00 | $19.35 | $12.00 |
| 49 | Prefabricated PM type C (Y)(24")(solid) (668-7127) | LF | 195 | $12.00 | $12.00 | $19.35 | $12.00 |
| 50 | Prefabricated PM type C (Y)(med nose) (668-7129) | EACH | 4 | $250.00 | $750.00 | $1,138.00 | $450.00 |
| 51 | Reflectorized pavement marker type I-C (672-7002) | EACH | 57 | $5.05 | $6.00 | $8.55 | $10.00 |
| 52 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 330 | $3.50 | $6.00 | $8.54 | $10.00 |
| 53 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 9 | $5.24 | $6.00 | $8.60 | $10.00 |
| 54 | Eliminating existing PM & markers (4") (677-7001) | LF | 2,872 | $0.25 | $0.75 | $2.28 | $1.25 |
| 55 | Eliminating existing PM & markers (8") (677-7004) | LF | 769 | $1.95 | $1.50 | $2.28 | $1.50 |
| 56 | Eliminating existing PM & markers (24") (677-7008) | LF | 1,013 | $3.07 | $4.50 | $4.56 | $2.00 |
| 57 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 7 | $71.96 | $60.00 | $114.00 | $75.00 |
| 58 | Eliminating existing PM & markers (double arrow) (677-7010) | EACH | 1 | $141.99 | $60.00 | $171.00 | $100.00 |
| 59 | Eliminating existing PM & markers (word) (677-7015) | EACH | 6 | $77.36 | $60.00 | $114.00 | $100.00 |
| 60 | Eliminating existing PM & markers (med nose) (677-7021) | EACH | 4 | $200.00 | $90.00 | $228.00 | $150.00 |
| 61 | Pavement surface preparation for marking (4") (678-7001) | LF | 2,763 | $0.19 | $0.20 | $0.18 | $0.10 |
| 62 | Pavement surface preparation for marking (6") (678-7002) | LF | 4,960 | $0.30 | $0.29 | $0.11 | |
| 63 | Pavement surface preparation for marking (8") (678-7004) | LF | 827 | $0.15 | $0.40 | $0.41 | $0.15 |
| 64 | Pavement surface preparation for marking (12") (678-7006) | LF | 1,520 | $0.17 | $0.50 | $0.64 | $0.20 |
| 65 | Pavement surface preparation for marking (24") (678-7008) | LF | 1,197 | $0.48 | $1.00 | $1.26 | $0.25 |
| 66 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 8 | $21.11 | $30.00 | $57.00 | $10.00 |
| 67 | Pavement surface preparation for marking (double arrow) (678-7010) | EACH | 2 | $21.05 | $50.00 | $126.00 | $15.00 |
| 68 | Pavement surface preparation for marking (word) (678-7016) | EACH | 8 | $21.05 | $30.00 | $57.00 | $15.00 |
| 69 | Pavement surface preparation for marking (med nose) (678-7024) | EACH | 4 | $75.00 | $75.00 | $171.00 | $15.00 |
| 70 | Install highway traffic signal (isolated) (680-7002) | EACH | 1 | $26,000 | $5,000.00 | $25,667 | $13,350 |
| 71 | Install highway traffic signal (upgrade) (680-7011) | EACH | 1 | $3,000.00 | $5,000.00 | $7,797.73 | |
| 72 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 14 | $260.00 | $275.00 | $252.00 | $324.00 |
| 73 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 6 | $260.00 | $275.00 | $252.00 | $324.00 |
| 74 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 14 | $260.00 | $275.00 | $252.00 | $324.00 |
| 75 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 8 | $260.00 | $275.00 | $252.00 | $324.00 |
| 76 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 14 | $260.00 | $275.00 | $252.00 | $324.00 |
| 77 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 5 | $260.00 | $275.00 | $252.00 | $324.00 |
| 78 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 12 | $760.00 | $625.00 | $708.00 | $808.95 |
| 79 | Backplate W/reflectorized border(3 sec)aluminum (682-7039) | EACH | 15 | $150.00 | $140.00 | $291.00 | $173.09 |
| 80 | Backplate W/reflectorized border(4 sec)aluminum (682-7040) | EACH | 4 | $212.00 | $200.00 | $479.00 | $259.04 |
| 81 | Remove backplate (682-7051) | EACH | 7 | $20.00 | $150.00 | $17.11 | |
| 82 | Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007) | LF | 1,775 | $1.80 | $1.00 | $3.10 | $1.71 |
| 83 | Traffic signal CBL (type A)(12 AWG)(4 conductor) (684-7009) | LF | 638 | $2.34 | $2.00 | $3.58 | $2.56 |
| 84 | Traffic signal CBL (type A)(12 AWG)(5 conductor) (684-7010) | LF | 2,425 | $3.51 | $3.00 | $3.70 | $2.97 |
| 85 | Traffic signal CBL (type A)(12 AWG)(20 conductor) (684-7025) | LF | 1,075 | $28.89 | $11.00 | $7.00 | $13.39 |
| 86 | Ins traffic signal PL AM(S)1 arm(32')lum (686-7035) | EACH | 1 | $19,000 | $15,000 | $14,854 | $13,335 |
| 87 | Ins traffic signal PL AM(S)1 arm(36')lum (686-7039) | EACH | 1 | $15,500 | $16,000 | $16,185 | $15,149 |
| 88 | Ins traffic signal PL AM(S)1 arm(44')lum (686-7047) | EACH | 2 | $15,500 | $17,000 | $17,443 | $17,027 |
| 89 | Pedestrian pole assembly (687-7001) | EACH | 8 | $3,669.00 | $2,100.00 | $2,728.00 | $3,350.27 |
| 90 | Pedestrian detect push button (APS) (688-7001) | EACH | 12 | $1,200.00 | $1,500.00 | $1,150.00 | $998.33 |
| 91 | Pedestrian detector controller unit (688-7003) | EACH | 2 | $4,200.00 | $0.01 | $651.00 | $4,137.65 |
| 92 | Replace of ground boxes (690-7007) | EACH | 4 | $1,500.00 | $228.00 | $2,144.72 | |
| 93 | Removal of signal head assembly (690-7024) | EACH | 7 | $50.00 | $114.00 | $34.43 | |
| 94 | Removal of pedestrian push buttons (690-7030) | EACH | 4 | $25.00 | $114.00 | $17.18 | |
| 95 | Removal of control cabinet(GRND MNT) (690-7038) | EACH | 1 | $1,500.00 | $569.00 | $384.72 | |
| 96 | Install of control cabinet(GRND MNT) (690-7040) | EACH | 2 | $4,000.00 | $30,000 | $6,803.00 | $39,644 |
| 97 | Removal of luminaire head (690-7064) | EACH | 2 | $100.00 | $114.00 | $68.89 | |
| 98 | Install of luminaire head (690-7066) | EACH | 2 | $650.00 | $495.00 | $445.09 | |
| 99 | Remove vid image vehicle det sys (VIVDS) (690-7086) | EACH | 5 | $175.00 | $456.00 | $32.26 | |
| 100 | Removing pedestrian signal LED traffic signal lamp unit (690-7094) | EACH | 4 | $50.00 | $1,805.00 | $34.44 | |
| 101 | Install bbu system (690-7131) | EACH | 2 | $7,500.00 | $7,500.00 | $8,585.00 | $9,636.05 |
| 102 | RVDS (presence and advance detection) (6008-7003) | EACH | 7 | $9,550.00 | $10,000 | $1,441.00 | $10,388 |
| 103 | LED roadside sign (6066-7001) | EACH | 4 | $1,750.00 | $4,727.00 | $1,990.52 | |
| 104 | Lead LED chevron W/ monitor sys (6068-7002) | EACH | 6 | $3,200.00 | $4,320.00 | $3,522.32 | |
| 105 | LED chevron (6068-7003) | EACH | 20 | $2,500.00 | $3,780.00 | $2,413.97 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 3, 2025. Compiled by Mirage Metrics.