TxDOT contract A00186954 bid tabulation
Rehabilitate Existing Roadway, SH 350 (HOWARD COUNTY to SCURRY COUNTY). Let by Texas DOT on June 5, 2025, Mitchell, Abilene District. 6 bids received; low bid $5,996,861 by RK Hall, LLC, -20% against the engineer's estimate of $7,472,607.
- Owner
- Texas DOT
- Letting
- 05 JUN 2025
- Pay items
- 45
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | RK Hall, LLC | $5,996,861 | Low | -20% |
| 2 | CK Newberry, LLC | $6,997,697 | +17% | -6.0% |
| 3 | A. L. Helmcamp, Inc. | $7,209,800 | +20% | -4.0% |
| 4 | Zack Burkett Co. | $7,277,032 | +21% | -3.0% |
| 5 | Reece Albert, Inc. | $7,889,155 | +32% | +6.0% |
| 6 | Nobles Road Construction, Inc. | $8,185,544 | +36% | +10% |
Engineer's estimate: $7,472,607.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. RK Hall, LLC | 2. CK Newberry, LLC | 3. A. L. Helmcamp, Inc. | 4. Zack Burkett Co. | 5. Reece Albert, Inc. | 6. Nobles Road Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Backfill (type B) (134-7002) | STA | 345 | $200.00 | $176.98 | $250.00 | $200.00 | $150.00 | $408.05 | $300.00 |
| 2 | Blading (150-7001) | STA | 345 | $250.00 | $68.08 | $80.00 | $115.00 | $50.00 | $37.44 | $222.00 |
| 3 | Cement (275-7001) | TON | 2,887 | $300.00 | $271.70 | $265.00 | $250.00 | $329.40 | $312.17 | $325.00 |
| 4 | Cement TRT (existing material)(8") (275-7003) | SY | 171,792 | $4.00 | $3.22 | $2.50 | $3.00 | $6.47 | $5.07 | $5.65 |
| 5 | Prime coat (MC-30) (310-7004) | GAL | 34,359 | $5.00 | $5.45 | $5.00 | $6.00 | $4.56 | $5.22 | $6.10 |
| 6 | SP mixes SP-C sac-B PG70-22 (344-7021) | TON | 28,154 | $140.00 | $115.75 | $145.00 | $150.00 | $128.00 | $153.18 | $147.50 |
| 7 | Tack coat (344-7077) | GAL | 266 | $5.00 | $71.08 | $4.00 | $6.00 | $6.00 | $5.76 | $6.10 |
| 8 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 2,251 | $7.00 | $9.61 | $4.00 | $1.50 | $3.00 | $12.08 | $7.70 |
| 9 | Planing asphalt concrete pavement(2") (354-7051) | SY | 856 | $7.00 | $11.83 | $9.00 | $1.50 | $3.00 | $15.88 | $12.50 |
| 10 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 368 | $70.00 | $44.10 | $40.00 | $40.00 | $42.70 | $35.00 | $63.50 |
| 11 | Retrofit rail (type T631) (451-7020) | LF | 350 | $100.00 | $136.50 | $140.00 | $137.00 | $158.60 | $130.00 | $260.00 |
| 12 | Mobilization (500-7001) | LS | 1 | $660,000 | $300,388 | $675,000 | $600,000 | $650,000 | $656,022 | $798,000 |
| 13 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $30,000 | $20,704 | $15,000 | $30,000 | $5,307.00 | $10,271 | $25,000 |
| 14 | Portable changeable message sign (503-7002) | EACH | 2 | $12,000 | $13,412 | $10,000 | $20,000 | $7,500.00 | $12,182 | $16,500 |
| 15 | TMA (stationary) (505-7001) | DAY | 23 | $400.00 | $247.43 | $350.00 | $400.00 | $305.00 | $459.87 | $550.00 |
| 16 | TMA (mobile operation) (505-7003) | DAY | 36 | $600.00 | $343.05 | $750.00 | $750.00 | $0.01 | $829.82 | $550.00 |
| 17 | Rock filter dams (install) (type 2) (506-7002) | LF | 160 | $50.00 | $57.09 | $65.00 | $57.75 | $50.00 | $84.93 | $66.00 |
| 18 | Rock filter dams (remove) (506-7011) | LF | 160 | $15.00 | $37.80 | $20.00 | $15.75 | $10.00 | $26.77 | $22.00 |
| 19 | Temporary sediment control fence (install) (506-7039) | LF | 2,660 | $10.00 | $6.42 | $6.00 | $6.30 | $6.10 | $5.36 | $6.60 |
| 20 | Temporary sediment control fence (remove) (506-7041) | LF | 2,660 | $1.50 | $1.15 | $2.00 | $2.10 | $2.44 | $0.82 | $2.20 |
| 21 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 960 | $8.00 | $6.62 | $7.00 | $8.40 | $12.20 | $9.00 | $8.80 |
| 22 | Biodegradable erosion control logs (remove) (506-7046) | LF | 960 | $1.00 | $1.38 | $2.00 | $1.05 | $2.44 | $1.74 | $2.20 |
| 23 | One-way traffic control (port traffic signal) (510-7003) | MO | 5 | $10,000 | $8,168.27 | $15,000 | $15,000 | $8,296.00 | $37,442 | $19,750 |
| 24 | Driveways (base) (530-7015) | SY | 247 | $30.00 | $70.44 | $50.00 | $70.00 | $35.00 | $138.47 | $55.00 |
| 25 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 68,456 | $0.20 | $0.21 | $0.30 | $0.15 | $0.32 | $0.14 | $0.28 |
| 26 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 34,043 | $0.25 | $0.25 | $0.30 | $0.15 | $0.29 | $0.14 | $0.28 |
| 27 | Metal W-beam guard fence (timber post) (540-7001) | LF | 400 | $30.00 | $31.50 | $35.00 | $31.50 | $36.60 | $30.00 | $33.00 |
| 28 | Remove metal beam guard fence (542-7001) | LF | 400 | $5.00 | $5.25 | $5.00 | $5.25 | $6.10 | $5.00 | $5.50 |
| 29 | Remove terminal anchor section (542-7002) | EACH | 4 | $300.00 | $525.00 | $550.00 | $525.00 | $610.00 | $500.00 | $550.00 |
| 30 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,600.00 | $6,874.23 | $4,500.00 | $4,200.00 | $4,880.00 | $4,000.00 | $4,400.00 |
| 31 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 32 | $700.00 | $960.75 | $1,000.00 | $960.75 | $1,098.00 | $900.00 | $1,000.00 |
| 32 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 12 | $1,000.00 | $997.50 | $1,000.00 | $997.50 | $1,220.00 | $1,000.00 | $1,100.00 |
| 33 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 4 | $1,100.00 | $997.50 | $1,000.00 | $997.50 | $1,342.00 | $1,100.00 | $1,250.00 |
| 34 | Remove SM RD SN sup&AM (644-7073) | EACH | 48 | $130.00 | $105.00 | $110.00 | $105.00 | $122.00 | $176.69 | $110.00 |
| 35 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 10 | $45.00 | $52.50 | $50.00 | $52.50 | $61.00 | $50.00 | $55.00 |
| 36 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 2,238 | $8.00 | $4.46 | $5.00 | $5.71 | $5.19 | $4.50 | $7.70 |
| 37 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 99,840 | $1.50 | $0.76 | $0.30 | $0.30 | $0.88 | $0.24 | $0.30 |
| 38 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 89,280 | $1.50 | $0.76 | $0.30 | $0.30 | $0.88 | $0.24 | $0.30 |
| 39 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 1,911 | $0.20 | $3.72 | $1.00 | $0.46 | $1.25 | $3.06 | $3.30 |
| 40 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 80,411 | $0.50 | $0.72 | $0.80 | $0.86 | $0.84 | $0.68 | $0.80 |
| 41 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 8,570 | $0.50 | $0.72 | $1.00 | $1.05 | $0.84 | $0.83 | $0.32 |
| 42 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 34,533 | $0.50 | $0.72 | $1.00 | $1.00 | $0.84 | $0.79 | $0.95 |
| 43 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 472 | $15.00 | $14.70 | $12.00 | $13.57 | $17.08 | $10.70 | $13.25 |
| 44 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 861 | $4.50 | $4.46 | $7.00 | $8.24 | $5.19 | $6.50 | $8.90 |
| 45 | Eliminating existing PM & markers (4") (677-7001) | LF | 93,085 | $1.00 | $0.68 | $1.00 | $0.82 | $0.79 | $0.65 | $1.10 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 5, 2025. Compiled by Mirage Metrics.