TxDOT contract A00194681 bid tabulation

Surfacing/Roadway Restoration, FM 1954 (FM 2650 to SH 79). Let by Texas DOT on May 2, 2025, Archer, Wichita Falls District. 6 bids received; low bid $1,712,102 by Zack Burkett Co., -12% against the engineer's estimate of $1,935,196.

Owner
Texas DOT
Letting
02 MAY 2025
Pay items
41
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Zack Burkett Co.$1,712,102Low-12%
2A. L. Helmcamp, Inc.$1,894,595+11%-2.0%
3Duininck, Inc.$2,212,500+29%+14%
4Jagoe-Public Company$2,362,819+38%+22%
5Eurovia Atlantic Coast LLC$2,422,836+42%+25%
6Grey Sky Construction LLC$2,460,461+44%+27%
TxDOT contract A00194681: bids by rank

Engineer's estimate: $1,935,196.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Zack Burkett Co.2. A. L. Helmcamp, Inc.3. Duininck, Inc.4. Jagoe-Public Company5. Eurovia Atlantic Coast LLC6. Grey Sky Construction LLC
1Backfill (type A or B) (134-7004)STA165$220.00$250.00$165.00$355.00$700.00$285.00$250.00
2Broadcast seed (permanent_rural_sand) (164-7001)SY21,971$1.50$0.22$0.18$0.18$0.20$0.30$0.50
3Broadcast seed (temporary_warm) (164-7005)SY10,985$0.15$0.20$0.16$0.27$0.05$0.27$0.50
4Broadcast seed (temporary_cool) (164-7006)SY10,986$0.24$0.25$0.20$0.27$0.05$0.27$0.50
5Vegetative watering (168-7001)TGL185$120.00$35.00$20.00$27.50$100.00$130.00$50.00
6D-GR HMA type D sac-B PG70-28 (341-7054)TON6,042$120.00$110.00$132.00$134.00$140.00$163.00$170.00
7Tack coat (341-7082)GAL2,197$5.21$5.00$4.00$8.00$2.00$3.00$6.00
8Flexible pavement structure repair(6") (351-7005)SY4,800$55.00$50.00$62.00$70.00$50.00$65.00$60.00
9Plane & text asphalt concrete pavement(0" to 2") (354-7002)SY2,000$5.75$4.00$3.00$5.85$6.00$12.00$10.00
10Riprap (mow strip)(4 in) (432-7013)CY10.25$750.00$861.00$730.00$745.00$1,500.00$1,200.00$650.00
11CMP (gal steel 18 in) (460-7003)LF112$89.00$98.40$85.00$85.00$92.00$80.00$100.00
12CMP (gal steel 24 in) (460-7005)LF60$135.00$123.00$110.00$105.00$115.00$100.00$150.00
13Set (type II) (18 in) (CMP) (6: 1) (P) (467-7304)EACH91$1,000.00$1,722.00$1,500.00$1,500.00$1,600.00$1,400.00$1,250.00
14Set (type II) (24 in) (CMP) (6: 1) (P) (467-7324)EACH26$1,300.00$1,845.00$1,600.00$1,600.00$1,700.00$1,500.00$2,500.00
15Removing structure (set) (496-7004)EACH8$660.00$615.00$550.00$530.00$500.00$500.00$1,500.00
16Remove STR (rail) (496-7017)LF178$60.00$24.60$25.00$21.00$15.00$20.00$100.00
17Mobilization (500-7001)LS1$171,137$115,000$153,000$220,000$260,000$170,000$220,000
18Barricades, signs and traffic handling (502-7001)MO6$10,000$2,378.00$9,400.00$19,000$25,000$14,000$8,500.00
19TMA (stationary) (505-7001)DAY102$120.00$200.00$50.00$265.00$50.00$400.00$250.00
20TMA (mobile operation) (505-7003)DAY10$390.00$0.01$50.00$955.00$50.00$1,000.00$550.00
21Biodegradable erosion control logs (install) (6") (506-7042)LF320$7.62$6.46$5.50$4.75$5.00$10.53$18.00
22Biodegradable erosion control logs (remove) (506-7046)LF320$3.56$2.46$2.00$1.05$0.80$4.89$9.00
23Permanent CTB (single slope) (type 3) (42 ) (514-7002)LF140$117.00$264.45$250.00$225.00$250.00$215.00$300.00
24Driveways (ACP) (530-7010)SY557$92.00$35.00$60.00$16.50$39.00$65.00$65.00
25Turnouts (ACP) (530-7018)SY1,245$156.00$35.00$60.00$135.00$180.00$175.00$65.00
26Mill rumble strips (asphalt) (centerline) (533-7002)LF16,479$0.50$0.62$0.40$0.62$0.60$0.50$0.50
27Remove terminal anchor section (542-7002)EACH10$242.00$615.00$580.00$530.00$500.00$500.00$1,500.00
28Crash cushion attenuator (install)(R)(N)(TL3) (545-7010)EACH1$21,123$40,296$38,000$34,500$35,000$37,725$21,000
29Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH7$8,000.00$11,316$10,000$9,800.00$10,000$9,200.00$21,000
30Mailbox install-S (TWG-post) type 2 (560-7002)EACH45$382.00$645.75$230.00$235.00$420.00$885.00$1,500.00
31Mailbox install-D (TWG-post) type 2 (560-7003)EACH11$405.00$645.75$260.00$235.00$440.00$885.00$1,500.00
32Install delineator assembly (D-SW)SZ 1(WFLX)GF2(BI) (658-7002)EACH8$34.00$43.05$40.00$37.00$38.00$35.00$100.00
33Remove delin & object marker assms (658-7078)EACH8$34.00$18.45$18.00$16.00$19.00$15.00$50.00
34Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH1,129$1.89$1.20$1.00$1.55$2.00$3.85$6.00
35Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266)LF33,872$0.70$1.23$0.73$0.73$0.90$1.00$1.00
36Reflectorized pavement marking type I (W)6"(solid)(060MIL) (666-7409)LF800$0.70$1.22$0.60$0.58$0.70$1.00$1.00
37Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF3,771$0.62$0.98$0.70$0.68$0.85$0.65$1.00
38Reflectorized pavement marking type I (Y)6"(solid)(060MIL) (666-7421)LF800$0.65$1.22$0.60$0.58$0.70$1.00$1.00
39Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF7,039$0.77$0.98$0.70$0.68$0.85$0.60$1.00
40Reflectorized pavement marker type II-A-A (672-7004)EACH565$0.71$6.15$5.50$5.30$6.00$5.75$6.00
41Eliminating existing PM & markers (4") (677-7001)LF1,600$2.00$3.51$2.00$2.10$2.00$1.00$1.00
TxDOT contract A00194681: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of May 2, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy