TxDOT letting results, May 2, 2025
39 contracts let by Texas DOT on May 2, 2025, $256,503,022 in low bids, a median of 6 bidders per contract. On the 39 with an engineer's estimate, the low bid came in under it 30 times; median low bid -12% against the estimate.
- Owner
- Texas DOT
- Contracts
- 39
- Low bids, total
- $256,503,022
- Data through
- 19 NOV 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| A00183799 | Widen Road - Add Lanes, SS 320 (FM 3255 to Railroad Drive) | El Paso District | 4 | Dan Williams Company | $112,560,911 | $116,396,410 | +3.0% | -19% | TxDOT |
| A00133440 | Rehabilitate Existing Roadway, FM 50 (US 79 to BRAZOS COUNTY LINE) | Bryan District | 5 of 6 | Big Creek Construction, LTD. | $20,558,088 | $21,354,366 | +4.0% | -30% | TxDOT |
| A00045158 | Rehabilitate Existing Roadway, FM 547 (US 380 to FM 6) | Dallas District | 8 | A. K. Gillis & Sons, LLC | $16,422,403 | $16,649,077 | +1.0% | -28% | TxDOT |
| A00194968 | Widen Road - Add Lanes, SH 36 (CR 123 to CALLAHAN COUNTY) | Abilene District | 8 | A. L. Helmcamp, Inc. | $10,612,471 | $10,641,136 | 0.0% | -22% | TxDOT |
| A00124356 | Surfacing/Roadway Restoration, US 59 (LAGARTO RD. to FM 1359) | Corpus Christi District | 5 | Lone Star Paving Company | $8,329,533 | $8,440,087 | +1.0% | -26% | TxDOT |
| A00064833 | Bridge Replacement, S BELTLINE RD (BELT LINE ROAD AT GOFF BRANCH to .) | Dallas District | 6 | Highway 19 Construction LLC | $8,168,666 | $8,484,379 | +4.0% | +6.0% | TxDOT |
| A00139426 | Intersection Improvements With Right And/Or Left Turn Lanes, FM 156 (at Industrial Blvd to .) | Fort Worth District | 7 | Grey Sky Construction LLC | $6,426,835 | $6,622,014 | +3.0% | +7.0% | TxDOT |
| A00195577 | Reconstruct Existing Roadway, SH 36 (SH 159 W to SH 159 E) | Yoakum District | 5 | Texas Materials Group, Inc. | $6,157,668 | $6,889,361 | +12% | -12% | TxDOT |
| A00177444 | Hazard Elimination & Safety, SH 195 (.7 Mi S of FM 2670 to Williamson County Line) | Waco District | 6 of 7 | Big Creek Construction, LTD. | $4,930,555 | $5,448,264 | +11% | -24% | TxDOT |
| A00140955 | Bridge Replacement, SH 156 (AT STEPHENS CREEK to .) | Lufkin District | 8 | Skyline Bridge LLC | $4,304,421 | $4,346,368 | +1.0% | -3.0% | TxDOT |
| A00184738 | Hazard Elimination & Safety, SH 34 (Traders Rd to FM 1570) | Paris District | 6 | Baker & Company Construction, LLC | $4,125,934 | $4,172,221 | +1.0% | -4.0% | TxDOT |
| A00188408 | Surfacing/Roadway Restoration, FM 2432 (SH 75 to FM 1484) | Houston District | 5 | Vulcan Materials Asphalt and Construction, LLC | $4,090,557 | $4,397,565 | +8.0% | -18% | TxDOT |
| A00201205 | Construct Pedestrian Infrastructure, SH 136 (340' West of Hoyne Ave to 230' East of Canadian Dr) | Amarillo District | 6 | Westfield Insurance Company | $3,406,939 | $3,458,256 | +2.0% | -7.0% | TxDOT |
| A00193381 | Hazard Elimination & Safety, SH 316 (FM 2760 to 2.655 Mi S of FM 2760) | Yoakum District | 4 | LCR Total Transport LLC | $3,141,248 | $3,227,733 | +3.0% | -2.0% | TxDOT |
| A00212930 | Install Traffic Signal, SL 12 (South of John West to Tillman Street) | Dallas District | 5 | Select Maintenance, L.L.C. | $3,099,433 | $3,394,629 | +10% | -12% | TxDOT |
| A00205877 | Rehabilitate Bridge, Various (RR Bridges to @ Various Locations) | Tyler District | 5 | Built Right Construction of Oklahoma, LLC | $2,796,332 | $2,888,577 | +3.0% | -8.0% | TxDOT |
| A00206608 | Hazard Elimination & Safety, SL 375 (IH 10 to 0.7 MI E OF US 54) | El Paso District | 2 | International Eagle Enterprises, Inc. | $2,780,754 | $2,979,989 | +7.0% | +33% | TxDOT |
| A00184474 | Hazard Elimination & Safety, BU 54A (AT DEER AVE to .) | El Paso District | 2 | Tri State Electric, LTD. | $2,664,962 | $3,194,663 | +20% | +1.0% | TxDOT |
| A00214091 | Preventive Maintenance, Various (Various Locations within Hidalgo County to .) | Pharr District | 3 | Highway Barricades and Services, LLC | $2,409,725 | $2,842,649 | +18% | -19% | TxDOT |
| A00210581 | Maintenance & Operations Project, Various (Various to Various) | Waco District | 11 | Centerline Technologies, LLC | $2,298,505 | $2,370,209 | +3.0% | -8.0% | TxDOT |
| A00197319 | Traffic Signal Improvements, Various (VARIOUS LOCATIONS DISTRICTWIDE to .) | Austin District | 5 | E-Z Bel Construction, LLC | $2,265,741 | $2,399,451 | +6.0% | -18% | TxDOT |
| A00180846 | Bridge Replacement, COUNTY ROAD 162 (FCR 245 @ Hogpen Creek to CR 162) | Waco District | 8 | A. L. Helmcamp, Inc. | $2,238,703 | $2,426,393 | +8.0% | -21% | TxDOT |
| A00199364 | Transportation Non-Roadway, Various (DISTRICT WIDE to .) | Beaumont District | 3 | Cornerstone Paving and Construction, L.L.C. | $1,999,855 | $2,247,695 | +12% | -24% | TxDOT |
| A00213666 | THERMOPLASTIC PAVEMENT MARKINGS, IH0030 (Various locations in to Paris District) | Paris District | 5 | Striping Technology, L.P. | $1,794,779 | $1,846,995 | +3.0% | -11% | TxDOT |
| A00184690 | Hazard Elimination & Safety, SH 279 (PR 15 to SHAMROCK DR.) | Brownwood District | 8 | Scout 5 Construction LLC | $1,732,353 | $2,499,938 | +44% | -45% | TxDOT |
| A00194681 | Surfacing/Roadway Restoration, FM 1954 (FM 2650 to SH 79) | Wichita Falls District | 6 | Zack Burkett Co. | $1,712,102 | $1,894,595 | +11% | -12% | TxDOT |
| A00213309 | FLEXIBLE BASE, US0082 (Various locations in the to Paris District) | Paris District | 2 | RK Hall, LLC | $1,628,050 | $1,635,088 | 0.0% | +2.0% | TxDOT |
| A00213622 | METAL BEAM GUARD FENCE REPAIR, IH0010 (Various Locations to Various Locations) | El Paso District | 1 | Apache Barricade & Sign | $1,603,475 | +24% | TxDOT | ||
| A00184092 | Hazard Elimination & Safety, IH 10 (0.65 MI WEST OF FM 365, EAST to 0.60 MI EAST OF FM 365) | Beaumont District | 7 | Sice, Inc. | $1,596,374 | $1,690,189 | +6.0% | +15% | TxDOT |
| A00196289 | Traffic Signal Improvements, Various (Districtwide Traffic Control FY 2025 to Project 2) | San Antonio District | 4 | E-Z Bel Construction, LLC | $1,477,083 | $1,582,942 | +7.0% | -1.0% | TxDOT |
| A00212223 | PAVEMENT MARKINGS, SH0317 (Various locations to Across the Waco District) | Waco District | 6 | The Confidence Group, Inc | $1,416,896 | $1,788,966 | +26% | -35% | TxDOT |
| A00214914 | MILL AND INLAY, IH0045 (Various to Various) | Bryan District | 5 | Cornerstone Paving and Construction, L.L.C. | $1,349,975 | $1,388,150 | +3.0% | +3.0% | TxDOT |
| A00200923 | Hazard Elimination & Safety, TEXAS AVE (A St to C St) | Odessa District | 6 | O. Trevino Construction, LLC | $1,295,425 | $1,482,632 | +14% | -13% | TxDOT |
| A00214840 | PAINT AND BEADS, IH0027 (Amarillo District Warehouse to Amarillo District Warehouse) | Amarillo District | 4 | Ennis-Flint, Inc. | $1,259,250 | $1,302,000 | +3.0% | -10% | TxDOT |
| A00211540 | FLEXIBLE PAVEMENT STRUCTURE REPAIR, BI0045J (Various Roadways in the to Ellis County Maintenance Section) | Dallas District | 5 | Peachtree Construction, LTD. | $1,004,908 | $1,118,645 | +11% | -13% | TxDOT |
| A00196756 | Intersection Improvements With Right And/Or Left Turn Lanes, US 290 (0.3 miles West of FM 2679 to 0.27 miles East of FM 2679) | Bryan District | 7 | Cornerstone Paving and Construction, L.L.C. | $965,907 | $1,020,481 | +6.0% | -27% | TxDOT |
| A00212000 | Bridge Maintenance, Various (Various Locations in Burnet, Llano, to Mason, Blanco and Gillespie Counties.) | Austin District | 6 | Structural Integrity Group LLC | $865,709 | $1,024,847 | +18% | -47% | TxDOT |
| A00188032 | Bridge Maintenance, Various (Various Locations to .) | Bryan District | 6 | Premier Contractors LLC | $590,567 | $728,665 | +23% | +7.0% | TxDOT |
| A00193518 | Hazard Elimination & Safety, SH 44 (SH 358 to 0.5 mi West of International Dr) | Corpus Christi District | 6 | Third Coast Services LLC | $419,930 | $467,552 | +11% | -21% | TxDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than TxDOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.