TxDOT contract A00212000 bid tabulation
Bridge Maintenance, Various (Various Locations in Burnet, Llano, to Mason, Blanco and Gillespie Counties.). Let by Texas DOT on May 2, 2025, Travis, Austin District. 6 bids received; low bid $865,709 by Structural Integrity Group LLC, -47% against the engineer's estimate of $1,641,284.
- Owner
- Texas DOT
- Letting
- 02 MAY 2025
- Pay items
- 37
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Structural Integrity Group LLC | $865,709 | Low | -47% |
| 2 | Taylor Contracting LLC | $1,024,847 | +18% | -38% |
| 3 | SCR Civil Construction, LLC | $1,233,301 | +42% | -25% |
| 4 | Blacksmith Ventures LLC | $1,332,425 | +54% | -19% |
| 5 | Premier Contractors LLC | $1,502,302 | +74% | -8.0% |
| 6 | Built Right Construction of Oklahoma, LLC | $1,864,550 | +115% | +14% |
Engineer's estimate: $1,641,284.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Structural Integrity Group LLC | 2. Taylor Contracting LLC | 3. SCR Civil Construction, LLC | 4. Blacksmith Ventures LLC | 5. Premier Contractors LLC | 6. Built Right Construction of Oklahoma, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 10 | $3,500.00 | $400.00 | $1,500.00 | $800.00 | $500.00 | $100.00 | $2,000.00 |
| 2 | Preparation row (tree remove) (24"-36" diameter) (100-7005) | EACH | 10 | $3,500.00 | $500.00 | $1,000.00 | $1,200.00 | $1,000.00 | $200.00 | $2,000.00 |
| 3 | Removing concrete (riprap) (104-7006) | SY | 17 | $187.00 | $27.00 | $50.00 | $270.00 | $150.00 | $75.00 | $250.00 |
| 4 | Flowable backfill (401-7001) | CY | 32 | $1,700.00 | $525.00 | $750.00 | $675.00 | $500.00 | $350.00 | $500.00 |
| 5 | Class C concrete (column encasement) (420-7064) | CY | 1.50 | $3,500.00 | $4,500.00 | $2,500.00 | $17,600 | $10,000 | $2,000.00 | $15,000 |
| 6 | Concrete structure repair (epoxy mortar) (429-7002) | SF | 45 | $250.00 | $140.00 | $250.00 | $230.00 | $300.00 | $300.00 | $350.00 |
| 7 | Concrete structure repair(deck rep (full depth)) (429-7005) | SF | 32 | $250.00 | $100.00 | $750.00 | $900.00 | $200.00 | $350.00 | $350.00 |
| 8 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 534 | $425.00 | $430.00 | $750.00 | $347.00 | $175.00 | $420.00 | $325.00 |
| 9 | Concrete structure repair (standard) (429-7009) | SF | 20 | $350.00 | $225.00 | $750.00 | $500.00 | $200.00 | $400.00 | $325.00 |
| 10 | Riprap (concrete)(6 in) (432-7003) | CY | 1 | $2,045.00 | $1,000.00 | $1,000.00 | $9,160.00 | $1,000.00 | $2,000.00 | $2,500.00 |
| 11 | Riprap (stone protection)(18 in) (432-7043) | CY | 110 | $250.00 | $255.00 | $400.00 | $300.00 | $225.00 | $350.00 | $350.00 |
| 12 | Riprap (stone protection)(24 in) (432-7045) | CY | 199 | $320.00 | $250.00 | $400.00 | $300.00 | $225.00 | $350.00 | $350.00 |
| 13 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 180 | $60.00 | $70.00 | $75.00 | $58.00 | $75.00 | $65.00 | $85.00 |
| 14 | Clean & paint existing rail (system II) (446-7005) | LS | 1 | $25,000 | $156,000 | $150,000 | $180,000 | $150,000 | $50,000 | $250,000 |
| 15 | Clean and paint existing STR (ref no. 2) (446-7021) | EACH | 8 | $2,500.00 | $5,645.00 | $4,800.00 | $6,480.00 | $4,800.00 | $20,000 | $18,000 |
| 16 | Raising existing struct (495-7001) | LS | 3 | $32,000 | $15,000 | $5,000.00 | $26,200 | $75,000 | $20,000 | $100,000 |
| 17 | Mobilization (500-7001) | LS | 1 | $169,821 | $61,000 | $100,000 | $123,000 | $150,000 | $120,000 | $200,000 |
| 18 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $20,000 | $3,785.00 | $1.00 | $4,000.00 | $5,000.00 | $1.00 | $2,000.00 |
| 19 | Portable changeable message sign (503-7001) | DAY | 260 | $187.62 | $1.00 | $1.00 | $120.00 | $100.00 | $1.00 | $50.00 |
| 20 | TMA (stationary) (505-7001) | DAY | 100 | $473.03 | $100.00 | $1.00 | $225.00 | $400.00 | $1.00 | $300.00 |
| 21 | TMA (mobile operation) (505-7003) | DAY | 100 | $473.33 | $1.00 | $1.00 | $600.00 | $400.00 | $1.00 | $300.00 |
| 22 | Sandbags for erosion control (506-7035) | EACH | 100 | $40.00 | $2.00 | $10.00 | $11.00 | $10.00 | $20.00 | $10.00 |
| 23 | Temporary SDMT cont fence (inlet protection) (506-7040) | LF | 750 | $10.00 | $2.00 | $4.00 | $7.00 | $15.00 | $3.00 | $12.00 |
| 24 | Temporary sediment control fence (remove) (506-7041) | LF | 750 | $10.00 | $1.00 | $1.00 | $1.15 | $1.00 | $3.00 | $5.00 |
| 25 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 100 | $28.34 | $2.00 | $4.00 | $12.00 | $10.00 | $5.00 | $25.00 |
| 26 | Biodegradable erosion control logs (remove) (506-7046) | LF | 100 | $50.00 | $1.00 | $1.00 | $2.30 | $1.00 | $50.00 | $5.00 |
| 27 | Metal thrie-beam guard fence (timber post) (540-7003) | LF | 20 | $100.00 | $30.00 | $125.00 | $150.00 | $150.00 | $100.00 | $100.00 |
| 28 | Remove metal beam guard fence (542-7001) | LF | 20 | $80.00 | $3.00 | $75.00 | $30.00 | $5.00 | $50.00 | $20.00 |
| 29 | JT / CRCK rout / seal(rubber - asphalt) (712-7004) | LF | 50 | $1,200.00 | $45.00 | $125.00 | $65.00 | $175.00 | $50.00 | $20.00 |
| 30 | Replace timber post W/O concrete FND (770-7006) | EACH | 11 | $200.00 | $25.00 | $100.00 | $1,420.00 | $25.00 | $200.00 | $250.00 |
| 31 | Concrete rail replacement (in-kind) (778-7004) | LF | 2 | $340.00 | $145.00 | $1,000.00 | $2,500.00 | $500.00 | $400.00 | $2,500.00 |
| 32 | CNC crack repair (flood)(gravity) (780-7005) | SF | 495 | $40.00 | $12.00 | $15.00 | $29.00 | $75.00 | $20.00 | $10.00 |
| 33 | Rep steel bridge member (beam) (784-7002) | EACH | 1 | $40,000 | $5,000.00 | $2,500.00 | $9,255.00 | $50,000 | $50,000 | $50,000 |
| 34 | Rep steel bridge member (bearings) (784-7008) | EACH | 20 | $4,000.00 | $2,000.00 | $500.00 | $1,500.00 | $5,000.00 | $15,000 | $12,000 |
| 35 | Carbon fiber reinforced polymer strengthning (786-7002) | SF | 25 | $155.13 | $85.00 | $500.00 | $500.00 | $150.00 | $165.00 | $200.00 |
| 36 | Replacing elastomeric bearing pads (787-7001) | EACH | 20 | $8,000.00 | $3,180.00 | $1,000.00 | $4,900.00 | $3,000.00 | $15,000 | $5,000.00 |
| 37 | Concrete beam repair (788-7001) | EACH | 3 | $20,000 | $3,950.00 | $2,500.00 | $6,200.00 | $25,000 | $10,000 | $10,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 2, 2025. Compiled by Mirage Metrics.