TxDOT contract A00139426 bid tabulation
Intersection Improvements With Right And/Or Left Turn Lanes, FM 156 (at Industrial Blvd to .). Let by Texas DOT on May 2, 2025, Tarrant, Fort Worth District. 7 bids received; low bid $6,426,835 by Grey Sky Construction LLC, +7.1% against the engineer's estimate of $6,000,822.
- Owner
- Texas DOT
- Letting
- 02 MAY 2025
- Pay items
- 144
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Grey Sky Construction LLC | $6,426,835 | Low | +7.0% |
| 2 | O. Trevino Construction, LLC | $6,622,014 | +3.0% | +10% |
| 3 | Urban Infraconstruction LLC | $6,659,390 | +4.0% | +11% |
| 4 | Ragle Construction, Inc. | $6,687,688 | +4.0% | +11% |
| 5 | Ed Bell Construction Company | $6,848,037 | +7.0% | +14% |
| 6 | Xit Paving and Construction Inc. | $7,191,761 | +12% | +20% |
| 7 | Jagoe-Public Company | $7,266,812 | +13% | +21% |
Engineer's estimate: $6,000,822.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Grey Sky Construction LLC | 2. O. Trevino Construction, LLC | 3. Urban Infraconstruction LLC | 4. Ragle Construction, Inc. | 5. Ed Bell Construction Company | 6. Xit Paving and Construction Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 2 | $24,000 | $250,000 | $10,350 | $20,000 | $291,400 | $100,000 | $68,000 |
| 2 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 26 | $700.00 | $1,000.00 | $600.00 | $1,500.00 | $260.00 | $300.00 | $287.00 |
| 3 | Preparation row (tree remove) (24"-36" diameter) (100-7005) | EACH | 2 | $800.00 | $5,000.00 | $3,500.00 | $2,500.00 | $1,800.00 | $2,250.00 | $1,990.00 |
| 4 | Removing concrete (pavement) (104-7001) | SY | 2,580 | $52.00 | $20.00 | $32.00 | $20.00 | $21.00 | $21.00 | $36.00 |
| 5 | Removing concrete (pavers) (104-7010) | SY | 12 | $100.00 | $50.00 | $50.00 | $90.00 | $96.00 | $75.00 | $67.00 |
| 6 | Removing concrete (driveways) (104-7011) | SY | 1,340 | $22.00 | $20.00 | $27.00 | $22.00 | $16.00 | $21.00 | $31.00 |
| 7 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 81 | $64.00 | $30.00 | $25.00 | $18.00 | $27.00 | $73.50 | $15.00 |
| 8 | Removing concrete (curb) (104-7016) | LF | 2,428 | $29.50 | $20.00 | $4.00 | $8.00 | $2.30 | $5.25 | $6.00 |
| 9 | Removing concrete (sawcut) (104-7020) | LF | 1,039 | $25.00 | $30.00 | $3.00 | $14.00 | $3.20 | $10.50 | $10.00 |
| 10 | Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002) | SY | 4,805 | $18.50 | $20.00 | $12.50 | $10.00 | $7.40 | $6.30 | $12.00 |
| 11 | Excavation (roadway) (110-7001) | CY | 6,329 | $58.75 | $20.00 | $35.00 | $53.00 | $41.10 | $21.00 | $38.00 |
| 12 | Embankment (final)(OC)(type C) (132-7005) | CY | 215 | $44.50 | $50.00 | $135.00 | $85.00 | $415.00 | $73.50 | $60.00 |
| 13 | Block sodding (162-7002) | SY | 7,538 | $22.00 | $10.00 | $6.00 | $5.00 | $12.00 | $4.63 | $5.00 |
| 14 | Drill seed (temporary_warm) (164-7013) | SY | 3,769 | $0.15 | $1.00 | $0.50 | $0.60 | $0.37 | $0.58 | $0.50 |
| 15 | Drill seed (temporary_cool) (164-7014) | SY | 3,769 | $0.15 | $1.00 | $0.50 | $0.60 | $0.38 | $0.58 | $0.50 |
| 16 | Vegetative watering (168-7001) | TGL | 264 | $50.00 | $20.00 | $100.00 | $59.00 | $55.00 | $73.50 | $65.00 |
| 17 | Lime (com or QK)(slurry) or QK(dry) (260-7001) | TON | 194 | $425.00 | $400.00 | $336.00 | $350.00 | $310.00 | $375.00 | $400.00 |
| 18 | Lime TRT (existing material)(8") (260-7007) | SY | 11,593 | $6.80 | $12.00 | $15.00 | $11.50 | $7.80 | $10.00 | $30.00 |
| 19 | Prime coat (MC-30) (310-7004) | GAL | 2,319 | $8.29 | $10.00 | $32.00 | $33.00 | $10.25 | $29.68 | $19.00 |
| 20 | D-GR HMA type-B PG64-22 (341-7001) | TON | 3,999 | $133.47 | $170.00 | $186.00 | $182.00 | $119.00 | $178.50 | $201.00 |
| 21 | Tack coat (341-7082) | GAL | 2,087 | $21.42 | $10.00 | $2.00 | $2.00 | $10.75 | $1.50 | $7.00 |
| 22 | Concrete pavement (CRCP) (8") (360-7002) | SY | 7,600 | $147.00 | $110.00 | $120.00 | $100.00 | $79.25 | $125.00 | $135.00 |
| 23 | Concrete pavement (CRCP)(hes) (8") (360-7047) | SY | 3,341 | $85.00 | $125.00 | $135.00 | $150.00 | $90.50 | $165.00 | $176.00 |
| 24 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 52 | $730.00 | $450.00 | $700.00 | $1,200.00 | $590.00 | $483.04 | $354.00 |
| 25 | RC pipe (CL III)(30 in) (464-7007) | LF | 55 | $140.50 | $150.00 | $275.00 | $230.00 | $182.00 | $300.00 | $249.00 |
| 26 | RC pipe (CL III)(36 in) (464-7009) | LF | 48 | $222.00 | $175.00 | $325.00 | $310.00 | $243.00 | $360.00 | $307.00 |
| 27 | Inlet (complete)(AD)(3FT X 3FT)(FTW) (465-7234) | EACH | 3 | $12,500 | $12,500 | $8,500.00 | $110.00 | $6,750.00 | $15,750 | $8,846.00 |
| 28 | Manh (complete)(type SD)(7'X 5'-3'X 3')(FTW) (465-7271) | EACH | 1 | $14,000 | $15,000 | $35,000 | $26,000 | $6,800.00 | $17,850 | $10,505 |
| 29 | Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348) | EACH | 1 | $3,775.00 | $6,500.00 | $6,000.00 | $5,100.00 | $2,650.00 | $3,000.00 | $13,269 |
| 30 | Removing structure (headwall) (496-7006) | EACH | 1 | $1,835.00 | $2,500.00 | $500.00 | $2,500.00 | $1,300.00 | $3,000.00 | $2,211.00 |
| 31 | Mobilization (500-7001) | LS | 1 | $534,857 | $600,000 | $660,000 | $600,000 | $680,000 | $685,000 | $400,000 |
| 32 | Barricades, signs and traffic handling (502-7001) | MO | 19 | $9,500.00 | $8,500.00 | $25,000 | $20,000 | $35,500 | $26,250 | $12,400 |
| 33 | Portable changeable message sign (503-7002) | EACH | 4 | $11,000 | $20,000 | $12,500 | $37,000 | $20,000 | $10,000 | $15,480 |
| 34 | TMA (stationary) (505-7001) | DAY | 330 | $250.00 | $250.00 | $180.00 | $225.00 | $276.00 | $157.50 | $374.00 |
| 35 | Rock filter dams (install) (type 2) (506-7002) | LF | 30 | $42.50 | $30.00 | $45.00 | $84.00 | $53.00 | $74.20 | $82.00 |
| 36 | Rock filter dams (remove) (506-7011) | LF | 30 | $17.00 | $15.00 | $20.00 | $18.00 | $25.00 | $37.10 | $17.00 |
| 37 | Construction exits (install) (type 1) (506-7020) | SY | 116 | $33.00 | $40.00 | $45.00 | $40.00 | $35.00 | $31.80 | $38.00 |
| 38 | Construction exits (remove) (506-7024) | SY | 116 | $13.10 | $20.00 | $15.00 | $14.00 | $12.00 | $17.49 | $13.00 |
| 39 | Temporary sediment control fence (install) (506-7039) | LF | 985 | $4.00 | $4.00 | $5.00 | $5.00 | $3.50 | $2.92 | $5.00 |
| 40 | Temporary sediment control fence (remove) (506-7041) | LF | 985 | $1.25 | $2.00 | $1.50 | $1.00 | $1.20 | $1.33 | $1.00 |
| 41 | Constructing detours (508-7001) | SY | 1,408 | $130.00 | $50.00 | $100.00 | $150.00 | $300.00 | $150.00 | $350.00 |
| 42 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 140 | $70.00 | $100.00 | $112.00 | $95.00 | $45.50 | $75.00 | $63.00 |
| 43 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 140 | $25.00 | $22.00 | $25.00 | $25.00 | $20.00 | $50.00 | $59.00 |
| 44 | Concrete curb (mono) (type II) (529-7007) | LF | 5,127 | $16.00 | $14.00 | $10.00 | $8.00 | $5.50 | $10.00 | $6.00 |
| 45 | Driveways (concrete) (530-7006) | SY | 1,188 | $128.00 | $85.00 | $130.00 | $105.00 | $91.00 | $180.00 | $153.00 |
| 46 | Concrete sidewalks (4") (531-7001) | SY | 202 | $140.00 | $65.00 | $115.00 | $75.00 | $74.50 | $95.00 | $98.00 |
| 47 | Concrete sidewalks (6") (531-7003) | SY | 560 | $158.00 | $85.00 | $110.00 | $85.00 | $69.00 | $115.00 | $135.00 |
| 48 | Curb ramps (type 1) (531-7005) | EACH | 3 | $3,550.00 | $3,850.00 | $4,000.00 | $2,000.00 | $2,100.00 | $3,000.00 | $2,184.00 |
| 49 | Curb ramps (type 5) (531-7008) | EACH | 1 | $4,150.00 | $3,850.00 | $9,000.00 | $3,300.00 | $8,100.00 | $6,000.00 | $4,436.00 |
| 50 | Curb ramps (type 21) (531-7013) | EACH | 2 | $4,250.00 | $3,850.00 | $4,500.00 | $2,300.00 | $2,400.00 | $3,000.00 | $2,184.00 |
| 51 | Curb ramps (type 22) (531-7014) | EACH | 3 | $5,325.00 | $3,850.00 | $5,200.00 | $3,300.00 | $3,200.00 | $6,000.00 | $3,802.00 |
| 52 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 25 | $25.90 | $25.00 | $18.00 | $35.00 | $16.25 | $27.67 | $13.00 |
| 53 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 102 | $27.00 | $35.00 | $25.00 | $40.00 | $21.75 | $27.98 | $17.00 |
| 54 | Conduit (PVC) (schedule 40) (4") (618-7040) | LF | 12 | $33.25 | $45.00 | $42.00 | $42.00 | $38.00 | $34.45 | $21.00 |
| 55 | Conduit (PVC) (schedule 40) (4") (bore) (618-7041) | LF | 571 | $60.00 | $80.00 | $41.00 | $65.00 | $37.25 | $40.28 | $31.00 |
| 56 | Electrical conductor (no.6) bare (620-7009) | LF | 701 | $3.25 | $3.00 | $2.75 | $4.50 | $2.25 | $3.50 | $3.00 |
| 57 | Electrical conductor (no.6) insulated (620-7010) | LF | 32 | $3.50 | $3.00 | $3.50 | $4.50 | $3.00 | $5.72 | $4.00 |
| 58 | Tray cable (4 conductor) (12 AWG) (621-7006) | LF | 821 | $3.00 | $3.00 | $3.75 | $4.50 | $3.25 | $5.09 | $2.00 |
| 59 | Ground box type D (162922) (624-7007) | EACH | 3 | $1,690.00 | $1,500.00 | $2,500.00 | $2,100.00 | $1,870.00 | $1,864.86 | $1,437.00 |
| 60 | Ground box type D (162922)W/apron (624-7008) | EACH | 4 | $2,500.00 | $1,500.00 | $2,500.00 | $3,100.00 | $2,000.00 | $2,186.78 | $1,659.00 |
| 61 | Remove ground box (624-7013) | EACH | 5 | $520.00 | $500.00 | $350.00 | $725.00 | $320.00 | $469.58 | $553.00 |
| 62 | Elc SRV type D 120/240 070(NS)SS(E)SP(O) (628-7191) | EACH | 1 | $11,000 | $12,500 | $10,000 | $15,200 | $8,785.00 | $11,202 | $6,491.00 |
| 63 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 13 | $800.00 | $1,150.00 | $900.00 | $695.00 | $790.00 | $689.00 | $503.00 |
| 64 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 15 | $900.00 | $1,150.00 | $1,500.00 | $820.00 | $1,320.00 | $779.10 | $719.00 |
| 65 | Install small roadside sign support and assembly type 10BWG(2)SA(P) (644-7017) | EACH | 2 | $1,400.00 | $1,150.00 | $2,000.00 | $1,660.00 | $1,695.00 | $1,431.00 | $995.00 |
| 66 | Remove SM RD SN sup&AM (644-7073) | EACH | 21 | $157.00 | $500.00 | $250.00 | $90.00 | $215.00 | $106.00 | $332.00 |
| 67 | Work zone pavement marking removing (W)4"(broken) (662-7061) | LF | 1,210 | $1.95 | $2.00 | $1.00 | $2.15 | $1.50 | $2.12 | $2.00 |
| 68 | Work zone pavement marking removing (W)4"(solid) (662-7064) | LF | 15,450 | $1.35 | $2.00 | $1.00 | $1.60 | $1.25 | $1.59 | $1.00 |
| 69 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 188 | $6.60 | $20.00 | $7.00 | $7.00 | $7.00 | $13.99 | $6.00 |
| 70 | Work zone pavement marking removing (W)(arrow) (662-7082) | EACH | 20 | $220.00 | $250.00 | $350.00 | $70.00 | $175.00 | $302.10 | $55.00 |
| 71 | Work zone pavement marking removing (W)(double arrow) (662-7083) | EACH | 18 | $146.00 | $500.00 | $510.00 | $98.00 | $325.00 | $424.00 | $76.00 |
| 72 | Work zone pavement marking removing (W)(TPL arrow) (662-7090) | EACH | 2 | $130.00 | $500.00 | $510.00 | $142.00 | $475.00 | $673.10 | $111.00 |
| 73 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 130 | $3.50 | $6.00 | $2.25 | $2.85 | $2.00 | $3.18 | $2.00 |
| 74 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 648 | $2.00 | $6.00 | $1.10 | $1.75 | $1.50 | $2.12 | $1.00 |
| 75 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 1,653 | $5.00 | $6.00 | $4.50 | $4.75 | $3.50 | $4.24 | $4.00 |
| 76 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 234 | $11.50 | $20.00 | $8.00 | $11.40 | $7.00 | $10.60 | $9.00 |
| 77 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 5 | $190.00 | $250.00 | $160.00 | $250.00 | $200.00 | $212.00 | $188.00 |
| 78 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 6 | $215.00 | $250.00 | $200.00 | $250.00 | $250.00 | $371.00 | $194.00 |
| 79 | Reflectorized pavement marking type I (Y)12"(solid)(100MIL) (666-7117) | LF | 96 | $4.00 | $6.00 | $4.50 | $5.00 | $3.50 | $4.24 | $4.00 |
| 80 | Pavement sler 6" (666-7347) | LF | 10,964 | $0.50 | $1.00 | $0.25 | $0.14 | $0.20 | $0.48 | $0.25 |
| 81 | Pavement sler 8" (666-7348) | LF | 778 | $10.00 | $3.00 | $0.35 | $0.17 | $0.20 | $0.69 | $0.25 |
| 82 | Pavement sler 12" (666-7350) | LF | 1,749 | $0.50 | $6.00 | $1.00 | $0.80 | $0.40 | $1.06 | $0.50 |
| 83 | Pavement sler 24" (666-7352) | LF | 234 | $55.00 | $20.00 | $2.00 | $1.50 | $0.80 | $2.12 | $1.00 |
| 84 | Pavement sler (arrow) (666-7353) | EACH | 5 | $45.00 | $250.00 | $31.00 | $26.00 | $20.00 | $63.60 | $20.00 |
| 85 | Pavement sler (word) (666-7354) | EACH | 6 | $45.00 | $250.00 | $37.00 | $26.00 | $20.00 | $74.20 | $20.00 |
| 86 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 1,768 | $1.75 | $3.00 | $0.90 | $1.40 | $0.80 | $1.86 | $1.00 |
| 87 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 5,889 | $2.50 | $3.00 | $0.90 | $1.10 | $0.70 | $1.59 | $0.75 |
| 88 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 3,307 | $3.50 | $3.00 | $0.90 | $1.10 | $0.70 | $1.59 | $0.75 |
| 89 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 111 | $7.00 | $6.00 | $6.00 | $5.70 | $5.00 | $7.42 | $4.00 |
| 90 | Pavement surface preparation for marking (6") (678-7002) | LF | 10,964 | $0.70 | $3.00 | $0.05 | $0.40 | $0.05 | $0.37 | $0.25 |
| 91 | Pavement surface preparation for marking (8") (678-7004) | LF | 778 | $0.75 | $6.00 | $0.10 | $0.40 | $0.07 | $0.58 | $0.25 |
| 92 | Pavement surface preparation for marking (12") (678-7006) | LF | 1,749 | $1.75 | $6.00 | $0.30 | $0.60 | $0.15 | $0.80 | $0.50 |
| 93 | Pavement surface preparation for marking (24") (678-7008) | LF | 234 | $1.75 | $20.00 | $0.55 | $1.50 | $0.30 | $1.86 | $1.00 |
| 94 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 5 | $40.00 | $250.00 | $13.00 | $21.00 | $10.00 | $53.00 | $17.00 |
| 95 | Pavement surface preparation for marking (word) (678-7016) | EACH | 6 | $40.00 | $250.00 | $16.00 | $21.00 | $10.00 | $63.60 | $17.00 |
| 96 | Install highway traffic signal (isolated) (680-7002) | EACH | 1 | $55,000 | $350,000 | $55,000 | $50,000 | $42,768 | $55,004 | $35,384 |
| 97 | Removing traffic signals (680-7004) | EACH | 1 | $14,000 | $15,000 | $25,000 | $100,000 | $135,000 | $9,390.96 | $13,269 |
| 98 | Temporary traffic signals (681-7001) | EACH | 1 | $82,000 | $160,000 | $100,000 | $150,000 | $153,000 | $144,030 | $149,275 |
| 99 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 10 | $575.00 | $350.00 | $400.00 | $520.00 | $360.00 | $456.22 | $326.00 |
| 100 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 4 | $605.00 | $350.00 | $400.00 | $520.00 | $360.00 | $456.23 | $331.00 |
| 101 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 10 | $595.00 | $350.00 | $400.00 | $520.00 | $360.00 | $456.22 | $326.00 |
| 102 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 8 | $590.00 | $350.00 | $400.00 | $520.00 | $360.00 | $456.22 | $331.00 |
| 103 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 10 | $1,000.00 | $350.00 | $400.00 | $520.00 | $360.00 | $456.22 | $326.00 |
| 104 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 4 | $590.00 | $350.00 | $400.00 | $520.00 | $360.00 | $456.23 | $331.00 |
| 105 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 8 | $1,500.00 | $6,500.00 | $800.00 | $920.00 | $730.00 | $724.51 | $369.00 |
| 106 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 10 | $255.00 | $350.00 | $330.00 | $260.00 | $300.00 | $228.11 | $108.00 |
| 107 | Backplate W/ref border(4 sec)(vent)aluminum (682-7043) | EACH | 4 | $310.00 | $350.00 | $330.00 | $360.00 | $300.00 | $300.51 | $170.00 |
| 108 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 1,256 | $4.65 | $3.00 | $3.50 | $4.00 | $3.00 | $3.39 | $3.00 |
| 109 | Traffic signal CBL (type A)(14 AWG)(16 conductor) (684-7042) | LF | 741 | $7.90 | $3.00 | $6.50 | $7.75 | $6.00 | $7.00 | $3.00 |
| 110 | Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079) | LF | 1,538 | $3.00 | $3.00 | $2.25 | $3.00 | $2.00 | $3.07 | $3.00 |
| 111 | Ins traffic signal PL AM(S)1 arm(36')lum (686-7039) | EACH | 4 | $15,500 | $18,500 | $18,000 | $44,000 | $15,800 | $19,184 | $15,878 |
| 112 | Pedestrian pole assembly (687-7001) | EACH | 3 | $4,750.00 | $6,500.00 | $5,200.00 | $4,800.00 | $4,750.00 | $4,551.96 | $3,096.00 |
| 113 | Pedestrian detect push button (APS) (688-7001) | EACH | 8 | $1,500.00 | $1,850.00 | $1,100.00 | $1,400.00 | $1,000.00 | $1,274.54 | $885.00 |
| 114 | Pedestrian detector controller unit (688-7003) | EACH | 1 | $5,000.00 | $6,500.00 | $4,500.00 | $9,000.00 | $3,940.00 | $5,403.88 | $2,884.00 |
| 115 | Bbu system (external battery cabinet) (6007-7001) | EACH | 1 | $8,700.00 | $8,500.00 | $9,500.00 | $18,000 | $8,600.00 | $9,712.99 | $8,293.00 |
| 116 | RVDS (presence det)(install only) (6008-7004) | EACH | 4 | $2,000.00 | $15,000 | $1,200.00 | $920.00 | $1,100.00 | $1,953.69 | $608.00 |
| 117 | RVDS (advance det)(install only) (6008-7005) | EACH | 2 | $2,000.00 | $15,000 | $1,200.00 | $920.00 | $1,100.00 | $2,029.16 | $608.00 |
| 118 | CCTV field equipment (digital) (6018-7002) | EACH | 1 | $9,725.00 | $6,500.00 | $6,100.00 | $10,000 | $5,600.00 | $8,586.00 | $9,731.00 |
| 119 | CCTV mount (pole) (6018-7003) | EACH | 1 | $865.00 | $2,000.00 | $385.00 | $650.00 | $350.00 | $496.40 | $608.00 |
| 120 | 24" concrete AWWA C303 wtrpipe,CSS bkfill (7026-7001) | LF | 176 | $700.00 | $500.00 | $1,600.00 | $950.00 | $1,300.00 | $1,575.00 | $1,144.00 |
| 121 | 24" concrete AWWA C303 water pipe (7026-7002) | LF | 136 | $650.00 | $500.00 | $360.00 | $850.00 | $334.78 | $420.00 | $584.00 |
| 122 | 42" casing by other than open cut* (7026-7003) | LF | 136 | $2,000.00 | $1,650.00 | $2,500.00 | $1,200.00 | $2,050.00 | $2,625.00 | $1,508.00 |
| 123 | 6" water pipe, CSS backfill (7026-7004) | LF | 20 | $90.00 | $500.00 | $900.00 | $350.00 | $750.00 | $795.00 | $210.00 |
| 124 | 24" gate valve W/ vault* (7026-7005) | EACH | 1 | $50,000 | $50,000 | $95,000 | $86,000 | $80,000 | $84,800 | $113,891 |
| 125 | 6" gate valve* (7026-7006) | EACH | 1 | $3,500.00 | $3,850.00 | $2,500.00 | $7,300.00 | $2,000.00 | $2,120.00 | $3,207.00 |
| 126 | Water line grouting (7026-7007) | CY | 13.40 | $300.00 | $1,000.00 | $1,200.00 | $725.00 | $1,000.00 | $1,060.00 | $1,305.00 |
| 127 | 24" water abandonment plug (7026-7008) | EACH | 2 | $3,500.00 | $1,500.00 | $6,000.00 | $725.00 | $5,000.00 | $5,300.00 | $10,173 |
| 128 | 24" pressure plug (7026-7009) | EACH | 2 | $5,000.00 | $2,500.00 | $6,000.00 | $10,000 | $5,000.00 | $5,300.00 | $10,062 |
| 129 | Salvage fire hydrant (7026-7010) | EACH | 1 | $1,500.00 | $2,500.00 | $1,800.00 | $1,600.00 | $1,500.00 | $1,590.00 | $774.00 |
| 130 | Remove concrete water vault (EX 24"BFV) (7026-7011) | EACH | 1 | $10,000 | $5,000.00 | $6,000.00 | $24,000 | $5,000.00 | $5,300.00 | $16,586 |
| 131 | Concrete water vault (EX 24" BFV) (7026-7012) | EACH | 1 | $50,000 | $25,000 | $155,000 | $71,000 | $150,000 | $147,000 | $117,208 |
| 132 | Fire hydrant* (7026-7013) | EACH | 1 | $8,500.00 | $7,500.00 | $15,000 | $14,000 | $12,500 | $13,250 | $10,947 |
| 133 | Connection to existing 24" water main (7026-7014) | EACH | 2 | $30,000 | $3,500.00 | $77,000 | $65,000 | $65,000 | $73,500 | $170,284 |
| 134 | Ductile iron water fittings W/restraint (7026-7015) | TON | 1 | $8,500.00 | $15,000 | $3,000.00 | $43,000 | $2,500.00 | $2,650.00 | $23,221 |
| 135 | Manhole adjustment, major W/ cover* (7026-7016) | EACH | 1 | $4,000.00 | $8,500.00 | $15,000 | $4,000.00 | $12,500 | $13,250 | $9,509.00 |
| 136 | Valve box adjustment (7026-7017) | EACH | 3 | $1,500.00 | $1,500.00 | $6,000.00 | $2,500.00 | $5,000.00 | $5,300.00 | $1,880.00 |
| 137 | Exploratory excavation of existing utility (7026-7018) | EACH | 2 | $2,000.00 | $1,500.00 | $580.00 | $20,000 | $500.00 | $530.00 | $7,408.00 |
| 138 | Utility markers (7026-7019) | EACH | 3 | $500.00 | $1,500.00 | $115.00 | $485.00 | $100.00 | $106.00 | $1,769.00 |
| 139 | Trench safety (7026-7020) | LF | 196 | $10.00 | $10.00 | $3.50 | $240.00 | $3.00 | $3.18 | $7.00 |
| 140 | Seeding, hydromulch (7026-7021) | SY | 300 | $10.00 | $3.00 | $4.35 | $6.50 | $4.00 | $4.20 | $6.00 |
| 141 | SWPPP = 1 acre (7026-7022) | EACH | 1 | $5,000.00 | $8,500.00 | $5,000.00 | $17,000 | $2,500.00 | $1,000.00 | $7,500.00 |
| 142 | Construction staking (7026-7023) | EACH | 1 | $10,000 | $50,000 | $4,100.00 | $125,000 | $2,500.00 | $3,710.00 | $100,000 |
| 143 | As-built survey (7026-7024) | EACH | 1 | $5,000.00 | $20,000 | $4,100.00 | $5,000.00 | $2,500.00 | $3,710.00 | $3,000.00 |
| 144 | 2" temporary water services (miscellaneous only) (7026-7025) | LF | 400 | $15.00 | $95.00 | $43.00 | $40.00 | $37.00 | $39.22 | $133.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 2, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.